In terms of Rules 65 of Public Procurement Rules, 2026 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and also available on EPADS v2.0 as well as Authority’s website at (www.ppra.gov.pk).
Material Management (Peshawar Electric Supply Company (PESCO)), Assistant
Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
+92-919-211-994
dm.mm@pesco.com.pk
The following specific data for the procurement of Consultancy Services to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
BDS Clause Number
ITB Number
Amendments of, and Supplements to, Clauses in the Instruction to Bidders
BDS Clause Number 1
ITB Number 1.1
Name of Procuring Agency: Material Management (Peshawar Electric Supply Company (PESCO))
The subject of procurement is: MM-44 Procurement of an External Quality Assessment (EQA) Firm for Internal Audit Directorate PESCO
Financial year for the operations of the Procuring Agency: 2026-27
Name and identification number of the Contract: P167124
BDS Clause Number 2
ITB Number 1.2 & 9.1
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Friday, December 4, 2026
BDS Clause Number 3
ITB Number 4.1
The language of the proposals is: English
BDS Clause Number 4
ITB Number 6.1
Participation of Sub-consultants, Key Experts and Non-Key Experts in more than one Proposal is permissible? No
BDS Clause Number 5
ITB Number 7.1
Proposals shall be valid until 120 Days
BDS Clause Number 6
ITB Number 9.1
List of documents required along with the bid: No
BDS Clause Number 7
ITB Number 10.2
The Consultant’s Proposal must include the minimum Key Experts’ time-input of __________person-months.
For the evaluation and comparison of Proposals only: if a Proposal includes less than the required minimum time-input, the missing time-input (expressed in person-month) is calculated as follows:
The missing time-input is multiplied by the highest remuneration rate for a Key Expert in the Consultant’s Proposal and added to the total remuneration amount. Proposals that quoted higher than the required minimum of time-input will not be adjusted. ]
BDS Clause Number 8
ITB Number 10.5
The price shall be Fixed.
Price schedule will be provided according to the format defined and acquired. see section price schedule.
BDS Clause Number 9
ITB Number 11.1
The qualification criteria to establish the supply / production capability of the bidder.
see Eligibility Criteria
BDS Clause Number 10
ITB Number 7.6
Services and Their related documents:
See section Required Services and ToR
BDS Clause Number 11
ITB Number 8.1 & 8.2
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6
Instrument of Bid Security Shall be in the Name of : Chief Executive Officer PESCO
The Bid Security shall be in the form of: Call at Deposit, Bank Guarantee
BDS Clause Number 12
ITB Number 13.1
Currency of the Bids shall be : PKR
BDS Clause Number 13
ITB Number 14.1
Proposal shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following;
Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
Bids that are not submitted on EPADS v2.0 shall be disqualified.
The deadline for Bids submission is: Monday, December 7, 2026 10:00 AM
BDS Clause Number 14
ITB Number 15.1
The Bids opening shall take place on EPADS v2.0.
Day : Monday
Date: Monday, December 7, 2026
Time : 10:30 AM
BDS Clause Number 15
ITB Number 20
Selection technique adopted will be: Quality and Cost Based Selection (QCBS)
see Evaluation Criteria
BDS Clause Number 16
ITB Number 21.5
The Performance guarantee shall: 5.00%.
The Performance Guarantee shall be acceptable in the form of: Call at Deposit, Bank Guarantee
BDS Clause Number 17
ITB Number 24.1
Grievence against this procurement shall be submitted online on EPADS v2.0.
All Active Taxpayers shall be eligible to participate in the procurement process, unless expressly excluded or otherwise restricted under the Eligibility Criteria specified by the Procuring Agency.
| Required Registration |
|---|
|
None |
| Eligibility Criteria | Document |
|---|---|
| Firm must be registered with the Federal Board of Revenue (FBR) and appear on the Active Taxpayers List (ATL) for Income Tax and Sales Tax (where applicable to the firm's registered activity). | Yes |
| Signed undertaking, on the firm's letterhead, confirming it is not blacklisted by any Government / semi-Government organization, regulatory body or international institution. | Yes |
| Signed undertaking that the firm is not currently under investigation for fraud, tax evasion, money laundering, or any criminal offence. | Yes |
| Conflict of Interest / Independence Declaration confirming no financial, business or employment relationship with PESCO or its key officials within the preceding 2 years, and disclosure of any actual, potential or perceived conflict | Yes |
| At least one member of the proposed assessment team must hold an active Certified Internal Auditor (CIA) credential issued by the IIA, per Standard 8.4 of the Global Internal Audit Standards (2024) and TOR. | Yes |
| Firm must have completed at least one (1) external quality assessment, quality assurance review, internal audit maturity assessment, or benchmarking engagement against a recognized standard (IIA Standards, COSO, ISO 31000, or equivalent) within the last 5 years, evidenced by a completion certificate, client reference letter, or contract copy. | Yes |
| Firm undertakes to execute a Non-Disclosure / Confidentiality Agreement as part of the contract, given the sensitivity of IAD's working papers and PESCO data | Yes |
| Joint Ventures / Associations of firms are eligible to bid, provided the JV agreement names a lead firm and the combined team meets the eligibility and technical requirements above.(If not applicable, upload "NA Certiifcate") | Yes |
Quality and Cost Based Selection (QCBS)
Weightage
| Technical Evaluation % | Financial Evaluation % |
|---|---|
| 80 | 20 |
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 50 | |
| Firm's Relevant Experience [Section Total: 30] | ||
| Years of relevant IA Quality Assessment / Advisory experience (highest band applies) (Quantitative)(Doc Required) 6 or more years of verifiable experience (20) 1 – 5 years of verifiable experience (10) | 20 | |
| Completed EQA-type assignments in the last 5 years (documentary evidence required): (Quantitative)(Doc Required) 4 or more completed assignments (10) 1 – 3 completed assignments (5) | 10 | |
| Qualifications & Competence of Engagement Lead [Section Total: 20] | ||
| Relevant certification beyond CIA — CRMA, CCSA, QIAL, CGAP, or equivalent (Quantitative)(Doc Required) | 5 | |
| Postgraduate degree in Accounting / Finance / Business / Audit or a related field (Quantitative)(Doc Required) | 5 | |
| Years of Experience as EQA / IA Advisory engagement lead (Quantitative)(Doc Required) 5 or more years as EQA / IA Advisory engagement lead (10) 1 – 4 years as EQA / IA Advisory engagement lead (4) | 10 | |
| Qualifications & Competence of Supporting Team [Section Total: 10] | ||
| At least 1 additional team member with relevant internal audit / governance / risk qualifications; CVs of all key personnel mandatory (Quantitative)(Doc Required) | 5 | |
| Additional recognized certifications held across the team — CRMA, ICAP / ACCA / CA / CPA, QIAL, or CFE (1 mark each, max 5) (Qualitative)(Doc Required) | 5 | |
| Methodology & Work Plan [Section Total: 30] | ||
| Understanding of PESCO IAD's objectives and scope (TOR/SOW Sections 1 & 2) (Qualitative)(Doc Required) | 5 | |
| Proposed EQA methodology — Standards conformance, risk-based planning, RCSA design, and benchmarking approach (Qualitative)(Doc Required) | 15 | |
| Work plan, timeline, and reporting / knowledge-transfer approach (TOR Sections 6 & 8) (Qualitative)(Doc Required) | 10 | |
| Financial Capacity of the Firm [Section Total: 10] | ||
| D1. Average annual turnover for the last 3 years (audited financial statements, or bank statements where the firm is not statutorily required to maintain audited accounts) — highest applicable band: (Qualitative)(Doc Required) Above PKR 15 Million (10) PKR 10 – 15 Million (6) | 10 | |
Positions Without Lots :
| Position | Delivery Schedule | Quantity | Bid Security |
|---|---|---|---|
| Procurement of an External Quality Assessment (EQA) Firm |
Address: Internal Audit Directorate Peshawar Schedule: 30 days Quantity: 1/job Quantity: 1 job |
1/job | 20000 PKR |
No
Positions Without Lots :
Position: Procurement of an External Quality Assessment (EQA) Firm
TORs (Terms of Reference):
1221
Terms of Reference for External Quality Assessment (EQA)
Â
1. Objective
PESCO’s Internal Audit Directorate (IAD/the Directorate) seeks to engage a qualified external firm to conduct a comprehensive External Quality Assessment (EQA) of the IAD in conformance with the 2024 IIA Global Internal Audit Standards (“the Standards”).
The EQA will evaluate internal audit function in conformance with the Internal Audit Manual, 2012 (“the IAM”), approved by the Board of Directors in 2012, and the Standards covering governance and positioning, organization’s control environment, practical implications, risk assessment and planning, execution and reporting. It will also include a review of the IAM in line with the Standards.
This engagement will provide the Directorate with an independent baseline against which its transformation, as envisaged in the three-year Comprehensive Transformation Roadmap and Strategy for the Internal Audit Function shared with the competent forums, can be measured. Timely completion of the EQA is critical to supporting the Directorate’s Transformation Roadmap/Strategy.
2. Scope
2.1. External Quality Assessment (EQA)
    Under this component, the IAD will be assessed for the last three financial years, from 1 July 2022 to 30 June 2025, in accordance with the Standards and in fulfilment of the requirements of Standard 8.4. The Standard requires that a full external assessment be conducted at least once every five years by a qualified and independent assessor or assessment team, including at least one active Certified Internal Auditor. The EQA will include:
2.1.1. Conformance with the Standards and Review of the IAM. Examine the IAM by reviewing and aligning it with the IAD’s Internal Audit Universe and risk frameworks, in the context of the organization’s control environment, practical implications, adequacy of its resources and budget to fulfil its mandate and implementation requirements, and to address conflicts of interest and other related matters. Assess departmental challenges in conformance with the Five Domains i.e (Purpose, Ethics, Governing Framework, Performance of internal audit services) of the Standards to identify gaps and opportunities for improvement, with the objective of achieving the “Three Personas” envisaged under the IIA 2035 Vision. Establish a sustainable mechanism for the continuous progress of PESCO’s Internal Audit Function (IAF), enabling it to attain best international practices in the years ahead. It also includes assessing the adequacy of the organization-wide first and second lines of defense against national and international best practices, relevant professional-body standards, and the Standards.
2.1.2. Risk Assessment Practices. Conduct a risk assessment of PESCO’s business processes and formations, and assess the adequacy of the First-Line Risk, Control Ownership and Audit Observation Remediation Accountability Framework (FCRAF) and the proposed Second-Line Risk Management and Compliance Framework, including Risk and Control Self-Assessment (RCSA), with active communication with all stakeholders. Further, examine the concentration of the current audit universe across various risk bands (activity wise, circle wise/formation wise) assess the sampling techniques specified in the IAM 2012 and updated revised IAM. It should Identify formations and activities where audit frequency or scope may be reduced, as specified in the IAM. Revise the proposed IAM to enable the IAD to achieve the desired risk maturity level and provide independent assurance and advisory services to the Board of Directors, in accordance with the mandate envisaged in the organization’s governing framework. Additionally, suggest value additions to achieve the objectives of the governing framework and align the function with best practices.
2.1.3. Adherence and Resourcing Review. Assess recent engagements for adherence to the IAM, the available man-day schedule, and the coverage of complete Audit Universe, including complete compliance universe, the adequacy of audit resources and skill sets against the key steps required to revamp the IAD in line with the Standards, and the impact of current vacancies, including at supervisory level, on delivery of the Annual Internal Audit Plan.
2.1.4. Benchmarking and Gap Analysis. Benchmark the Directorate against the Standards practice to identify areas of non-conformance or potential improvement, focusing on risk-based planning, reporting formats, resources and skill sets. This includes assessing the potential for digitization and process automation across the audit cycle, application of data analytics techniques, evaluating audit turnaround time to cover complete Internal Audit Universe, and assessing the robustness of the Directorate's follow-up mechanism for tracking audit observations to verified closure.
3. Deliverables
3.1. External Quality Assessment (EQA) Final Report
3.1.1. Conformance Review. Evaluates the Internal Audit Department's alignment with PESCO's internal policies and procedures and with the Standards.
3.1.2. Risk Assessment Evaluation. Assesses the approach to identifying and prioritizing risk for audit planning, including the design and execution of Risk and Control Self-Assessment (RCSA), including annual audit plan gauging adherence to recognized frameworks such as COSO and ISO 31000.
3.1.3. Performance Gaps and Revised Internal Audit Manual. Identifies gaps between the current IA Manual (2012) and the Standards, having regard to the organization’s control environment, application of sampling techniques, internal audit formats and delivers a reviewed, upgraded Internal Audit Manual aligned with the Standards.
3.1.4. Actionable Recommendations. Presents a prioritized plan to address identified gaps in the organization, strengthen risk-based planning, and standard Quality and Assurance Plan.
4. Engagement Approach and Work Plan
The selected firm shall submit an inception report setting out its methodology, information requirements, stakeholder-engagement plan, milestones, quality-control arrangements, and a detailed work schedule for approval before fieldwork begins.
5. Independence and Professional Competence
The firm and proposed team shall disclose any actual, potential or perceived conflicts of interest and remain independent throughout the engagement. Consistent with Standard 8.4 of the Standards, at least one member of the assessment team shall be an active Certified Internal Auditor. The engagement lead should have relevant EQA experience and appropriate professional qualifications, and the assessment team should collectively demonstrate expertise in internal audit, governance, risk management, and the applicable Standards.
6. Validation, Reporting and Implementation Roadmap
Significant observations shall be discussed with relevant stakeholders and supported by sufficient, reliable, relevant and useful evidence. A draft report will be provided for factual validation before finalization. The final report shall include an executive summary, an overall conformance conclusion, major internal control weaknesses, root-cause analysis, prioritized recommendations, and a practical implementation roadmap showing suggested ownership, sequencing and timelines. The firm shall present the final results to the Chief Executive Officer, the Chief Internal Auditor, and the Audit & Finance Committee of the Board of Directors.
7. Confidentiality, Data Protection and Ownership
All information obtained during the engagement shall be treated as confidential and used solely for this assignment. The firm shall apply appropriate safeguards to working papers and data, comply with applicable information-security and data-protection requirements, and return or securely dispose of information when instructed. All final deliverables and the updated Internal Audit Manual prepared under this engagement shall be the property of PESCO.
Â
8. Knowledge Transfer
The firm shall conduct a necessary workshop for relevant IAD personnel and key stakeholders covering key findings, risk assessment, revamping exercise, the revised/updated Manual and its presentation before the CEO & A&F Committee of the Board, recommended quality-assurance practices, and the approach for sustaining conformance through the Directorate's own periodic internal assessments under its Quality Assurance and Improvement Program.
9. Quality of Work
The firm is expected to deliver high-quality, professional work with laid down action plan that adheres to the highest standards of internal audit practice. The firm must ensure that the documents not only meet PESCO's objectives but also aligned with the best int
For Individual Positions
| # | Position Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract>
Number of GC Clause 3.1
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 4.1
The language is English
Number of GC Clause 6.1 and 6.2
The addresses are:
The Procuring Agency is: Material Management (Peshawar Electric Supply Company (PESCO)), Assistant Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
The Consultant Address:
The title of the subject procurement is:MM-44 Procurement of an External Quality Assessment (EQA) Firm for Internal Audit Directorate PESCO
Number of GC Clause 8.1
[Note: If the Consultant consists only of one entity, state “N/A”;Or
The Lead Member on behalf of the JV is ___________ ______________________________ [insert name of the member]
Number of GC Clause 9.1
The Authorized Representatives are:
For the Procuring Agency:
Material Management (Peshawar Electric Supply Company (PESCO)), Assistant
Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
+92-919-211-994
dm.mm@pesco.com.pk
For the Bidder:
Name: ………………………
Designation: ……………..
Address: ……………………………..
Number of GC Clause 11.1
[Note: If there are no effectiveness conditions, state “N/A”]OR
List here any conditions of effectiveness of the Contract]
The effectiveness conditions are the following: [insert “N/A” or list the conditions]
Termination of Contract for Failure to Become Effective:
The time period shall be _______________________ [insert time period, e.g.: four months].
Commencement of Services:
The number of days shall be_________________ [e.g.: ten].
Confirmation of Key Experts’ availability to start the Assignment shall be submitted to the Procuring Agency in writing as a written statement signed by each Key Expert.
Expiration of Contract:
The time period shall be ________________________ [insert time period, e.g.: twelve months].
Number of GC Clause 23
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 0.07% to 10.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 23.1
No additional provisions.
The following limitation of the Consultant’s Liability towards the Procuring Agency can be subject to the Contract’s negotiations:
Number of GC Clause 24
Performance Guarantee:
Instrument of Performance Guarantee shall be in the Name of : Chief Executive Officer PESCO
The amount of performance guarantee shall be 5.00% of the contract price in acceptable form of Call at Deposit, Bank Guarantee
Number of GC Clause 24.1
The insurance coverage against the risks shall be as follows:
(a) Professional liability insurance, with a minimum coverage of ______________________ [insert amount and currency which should be not less than the total ceiling amount of the Contract];
Number of GC Clause 33. Removal of Experts or Sub-consultants
[Note to Procuring Agency: include the following for supervision of infrastructure contracts (such as Plant or Works) and for other consulting service where the social risks are substantial or high, otherwise delete.]
Price adjustment on the remuneration : Nil [insert “applies” or “ does not apply”]
The currency of payment shall be the following: PKR
[The advance payment could be in either the foreign currency, or the local currency, or both; select the correct wording in the Clause here below. The advance bank payment guarantee should be in the same currency(ies)]
The following provisions shall apply to the advance payment and the advance bank payment guarantee:
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract unless they otherwise agree that the Authority shall pay the Bidder any monies due to the Bidder.
Arbitrator’s fee:
The fee shall be specified in Pak Rupees, as determined by the Arbitrator, which shall be shared equally by both parties.
Appointing Authority for Arbitrator:
By the Mutual Consent or in accordance with the provisions of Arbitration Act, 1940, in case the parties fail to reach a consensus on the name of sole arbitrator, any party may submit an application to the Chief Justice Islamabad High Court for appointment of sole arbitrator. The Chief Justice IHC may appoint a former judge of any High Court or Supreme Court as the sole arbitrator to resolve the dispute between the parties.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder who is a national of the Islamic Republic of Pakistan arising in connection with the present Contract shall be referred to adjudication or arbitration in accordance with the laws of the Islamic Republic of Pakistan including Arbitration Act 1940, however above provision shall prevail in referring the case to the Arbitrator.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place of arbitration shall be at Islamabad. The award of the arbitrator shall be final and shall be binding on the parties.
Date: [insert date (as day, month and year)]
Bid No.:P167124
To: Material Management (Peshawar Electric Supply Company (PESCO)), Assistant Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
This CONTRACT (hereinafter called the “Contract”) is made the [number] day of the month of [month], [year], between, on the one hand, [name of Procuring Agency or Recipient] (hereinafter called the “Procuring Agency”) and, on the other hand, [name of Consultant] (hereinafter called the “Consultant”).
[If the Consultant consist of more than one entity, the above should be partially amended to read as follows: “…(hereinafter called the “Procuring Agency”) and, on the other hand, a Joint Venture consisting of the following entities, each member of which will be jointly and severally liable to the Procuring Agency for all the Consultant’s obligations under this Contract, namely, [name of member] and [name of member] (hereinafter called the “Consultant”).]
WHEREAS
NOW THEREFORE the parties hereto hereby agree as follows:
The following documents attached hereto shall be deemed to form an integral part of this Contract:
In the event of any inconsistency between the documents, the following order of precedence shall prevail: the Special Conditions of Contract; the General Conditions of Contract, including Attachment 1; Appendix A; Appendix B; Appendix C and Appendix D; and Appendix E. Any reference to this Contract shall include, where the context permits, a reference to its Appendices.
2. The mutual rights and obligations of the Procuring Agency and the Consultant shall be as set forth in the Contract, in particular:
(a) the Consultant shall carry out the Services in accordance with the provisions of the Contract; and
(b) the Procuring Agency shall make payments to the Consultant in accordance with the provisions of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their respective names as of the day and year first above written.
For and on behalf of [Name of Procuring Agency]
[Authorized Representative of the Procuring Agency – name, title and signature]
For and on behalf of [Name of Consultant or Name of a Joint Venture]
[Authorized Representative of the Consultant – name and signature]
[For a joint venture, either all members shall sign or only the lead member, in which case the power of attorney to sign on behalf of all members shall be attached.]
For and on behalf of each of the members of the Consultant [insert the name of the Joint Venture]
[Name of the lead member]
[Authorized Representative on behalf of a Joint Venture]
[add signature blocks for each member if all are signing]
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: Material Management (Peshawar Electric Supply Company (PESCO)), Assistant Room # 313, PESCO HQ, Peshawar City, Peshawar (District), Peshawar Division (Division), Khyber Pakhtunkhwa (KP) (Province).
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}