In terms of Rule 65 of Public Procurement Rules, 2026 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.gov.pk).
Institute of Space Technology (Institute of Space Technology), Procurement
Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
+92-301-509-8817
mgr.proc@ist.edu.pk
1.1 The Procuring Agency (PA), as indicated in the Bids Data Sheet (BDS) invites Bids through EPADS v2.0 for the provision of Goods as specified in the BDS and in Section V – Evaluation Criteria, Specifications & Schedule of Requirements. The name, identification, and number of items/deliverables are provided in the BDS. The successful Bidders will be expected to provide the goods within the specified period and timeline(s) as stated in the BDS.
2.1 Source of funds is referred in Clause-2 I of Invitation for Bids.
3.1 A Bidder may be natural person, company or firm or public or semi-public agency of Pakistan or any foreign country, or any combination of them with a formal existing agreement (on Judicial Papers) in the form of a joint venture, consortium, or association. In the case of a joint venture, consortium, or association, all members shall be jointly and severally liable for the execution of the Contract in accordance with the terms and conditions of the Contract. The joint venture, consortium, or association shall nominate a Lead Member as nominated in the BDS, who shall have the authority to conduct all business for and on behalf of any and all the members of the joint venture, consortium, or association during the Bidding process, and in case of award of contract, during the execution of the contract.
Verifiable copy of the agreement that forms a joint venture, consortium or association shall be required to be submitted as part of the Bid.
The appointment of Lead Member in the joint venture, consortium, or association shall be confirmed by submission of a valid Power of Attorney to the Procuring Agency.
Any bid submitted by the joint venture, consortium or association shall indicate the part of proposed contract to be performed by each party and each party shall be evaluated (or post qualified if required) with respect to its contribution only, and the responsibilities of each party shall not be substantially altered without prior written approval of the Procuring Agency and in line with any instructions issued by the Authority.
(The limit on the number of members of JV or Consortium or Association may be prescribed in BDS, in accordance with the guidelines issued by the PPRA).
3.2 The invitation for Bids is open to all prospective suppliers, manufacturers, or authorized agents / dealers subject to any provisions of incorporation or licensing by the respective national incorporating agency or statutory body established for that particular trade or business. Procuring agencies shall specify the registration/licensing requirements for the foreign bidders keeping in view the requirement of that business.
3.3 A Bidder shall not have a conflict of interest. All Bidders found to have a conflict of interest shall be disqualified. A Bidder may be considered to have a conflict of interest with one or more parties in this Bidding process, if they:
3.4 A Bidder may be ineligible if –
3.5 As and when required, bidders shall provide to the Procuring Agency evidence of their eligibility, proof of compliance with the necessary legal requirements to carry out the contract effectively.
3.6 Bidders shall submit Bids relating to the nature, conditions and modalities of sub-contracting wherever the sub-contracting of any elements of the contract amounting to more than ten (10) percent of the Bid price is envisaged.
4.1 All goods and related services to be supplied under the contract shall have their origin in eligible source countries, and all expenditures made under the contract will be limited to such goods and services. For purpose of this Bid, ineligible countries are the countries declared ineligible by the Federal Government.
5.1 A bidder shall submit only one Bid, in the same bidding process, either individually as a Bidder or as a member in a joint venture or any similar arrangement.
5.2 The Bidder shall not engage a subcontractor for any portion of the contract if the value of such subcontracting exceeds thirty percent (30%) of the total contract amount.
6.1 Any cost incurred by the bidder relating to the preparation and submission of its Bid shall be borne by the bidder, and the Procuring Agency shall in no case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding process.
7.1 The Goods required, Bidding procedures, and terms and conditions of the contract are prescribed in the Bidding Documents. In addition to the Invitation for Bids, the Bidding documents which should be read in conjunction with any addenda issued in accordance with ITB 10.1 include:
Section I -Invitation to Bids
Section II Instructions to Bidders (ITB)
Section III Bid Data Sheet (BDS)
Section IV Evaluation Criteria, Specifications, Schedule of Requirements
Section V Bid Forms
Section VI General Conditions of Contract (GCC)
Section VII Special Conditions of Contract (SCC)
Section VIII Contract Forms
Section IX Integrity Pact
Section X Declaration of Beneficial Ownership Information.
7.2 The Bidder is expected to examine all instructions, forms, terms and specifications in the Bidding documents. Failure to furnish all the information required in the Bidding documents through EPADS v2.0 will be at the Bidder’s risk and may result in the rejection of its Bids.
8.1 A prospective Bidder requiring any clarification of the Bidding documents may notify the Procuring Agency through EPADS v2.0.
8.2 The Procuring Agency will within two (02) working days after receiving the request for clarification, respond to any request for clarification through EPADS v2.0 provided that such request is received not later than three (03) days, prior to the deadline for the submission of Bids as prescribed in ITB 22
8.3 The Procuring Agency's response will be forwarded to all identified Prospective Bidders through EPADS v2.0, including a description of the inquiry, but without identifying its source.
8.4 Should the Procuring Agency deem it necessary to amend the Bidding document as a result of a clarification, it shall do so following the procedure under ITB 9.
8.5 If indicated in the BDS, the Bidder’s designated representative is invited at the Bidder’s cost to attend a pre-Bid meeting at the place, date and time mentioned in the BDS. During this pre-Bid meeting, prospective Bidders may request clarification of the schedule of requirement, the Evaluation Criteria or any other aspects of the Bidding document.
8.6 Minutes of the pre-Bid meeting, if applicable, including the text of the questions asked by Bidders, including those during the meeting (without identifying the source) and the responses given, together with any responses prepared after the meeting will be uploaded on EPADS v2.0. Any modification to the Bidding documents that may become necessary as a result of the pre-Bid meeting shall be made by the Procuring Agency exclusively through the use of an Addendum pursuant to ITB 9. Non-attendance at the pre-Bid meeting will not be a cause for disqualification of a Bidder.
9.1 Before the deadline for submission of Bids, the Procuring Agency for any reason, whether at its own initiative or in response to a clarification requested by a prospective Bidder or Pre-Bid meeting may modify the Bidding documents by issuing addenda through EPADS v2.0.
9.2 The Procuring Agency shall promptly publish the addendum through EPADS v2.0.
Any addendum issued including the notice of any extension of the deadline shall also be communicated through EPADS v2.0 to all the bidders who have already submitted their bids. Such bidders shall have the right to withdraw their already submitted bid and re-submit the revised bid prior to the original or extended bid submission deadline.
9.3 To give prospective Bidders reasonable time in which to take an addendum/corrigendum into account in preparing their Bids, the Procuring Agency may, at its discretion, extend the deadline for the submission of Bids through EPADS v2.0:
Provided that the Procuring Agency shall extend the deadline for submission of Bids, if such an addendum is issued within last three (03) days of the Bids submission deadline.
10.1 The Bid prepared by the bidder, as well as all correspondence and documents relating to the Bids exchanged by the Bidder and the Procuring Agency shall be written in the English language unless otherwise specified in the BDS. Supporting documents and printed literature furnished by the Bidder may be in another language provided they are accompanied by an accurate translation of the relevant pages in the English language unless otherwise specified in the BDS, in which case, for purposes of interpretation of the Bidder, the translation shall govern.
11.1 The Bid prepared by the Bidder shall constitute the documents required in the BDS.
Details of sample(s) where applicable and requested in the BDS.
Documentary evidence established in accordance with ITB 13 that the Bidder is eligible and/or qualified for the subject bidding process;
Documentary evidence established in accordance with ITB 03 that the Bidder has been authorized by the manufacturer to deliver the goods into Pakistan, where required and where the supplier is not the manufacturer of those goods;
Documentary evidence established in accordance with ITB 12 that the goods and related services to be supplied by the Bidder are eligible goods and services, and conform to the Bidding Documents;
Bid security or Bid Securing Declaration furnished in accordance with ITB ---.
12.1 To establish the conformity of the bidder to the Bidding document, the Bidder shall furnish as part of its Bids the documentary evidence that Goods provided conform to the technical specifications and standards.
13.1 Pursuant to ITB 10, the Bidder shall furnish, as part of its Bid, all those documents establishing the Bidder’s eligibility to participate in the Bidding process and/or its qualification to perform the contract if its Bid is accepted.
14.1 The Bidder shall fill the Form of Bid furnished in the Bidding document. The Bid Form must be completed without any alterations to its format and no substitute shall be accepted.
15. Bid Prices
15.1 The Bid Prices quoted by the Bidder in the Form of Bid and in the Price Schedules shall conform to the requirements specified below or exclusively mentioned hereafter in the Bidding documents.
15.2 All items in the Schedule of Requirement must be listed and priced separately in the Price Schedule(s). If a Price Schedule shows items listed but not priced and neither explicitly denied, their prices shall be construed to be included in the prices of other items.
15.3 In the event that any item(s) in the Price Schedule are not quoted, and such omission is determined by the Procuring Agency not to materially affect the responsiveness of the Bid, the Procuring Agency may, for the sole purpose of bid evaluation and comparison, assign a price to the unquoted item(s) in accordance with the following methodology:
(a) The assigned price shall be the average of the prices quoted for the same item(s) by all substantially responsive bidders; or
(b) In cases where no comparable quotations are available, the Procuring Agency shall apply the corresponding item price from its duly approved cost estimate for evaluation purposes.
The prices so assigned shall be utilized exclusively for bid evaluation and comparison, and shall not, under any circumstances, be incorporated into or form part of the Contract Price.
15.4 The Bid price to be quoted in the Form of Bid in accordance with ITB 13.1 shall be the total price of the Bid.
15.5 The Bidder shall indicate on the appropriate Price Schedule, the unit prices (where applicable) and total Bid price of the Goods it proposes to provide under the contract.
15.6 Prices quoted by the Bidder shall be fixed during the Bidder’s performance of the contract and not subject to variation on any account. A Bid submitted with an adjustable price will be treated as non-responsive and shall be rejected.
16.1 Prices shall be quoted in Pakistani Rupees unless otherwise specified in the BDS in accordance with Rule 42 (2) of the Public Procurement Rules, 2026.
17.1 Such extensions may be more than one time but the total period of such extension shall not exceed the original bid validity period.
17.2 Bids shall remain valid for the period specified in the BDS after the Bid submission deadline prescribed by the Procuring Agency. A Bid valid for a shorter period shall be rejected by the Procuring Agency as non-responsive. The period of Bid validity will be determined from the complementary Bid securing instrument, i.e. the expiry period of Bid Security or Bids Securing Declaration as the case may be.
The procuring agency shall ordinarily be under an obligation to process and evaluate the bid and to issue letter of award within the stipulated bid validity period.
17.3 Under exceptional circumstances, prior to the expiration of the initial Bid validity period, the Procuring Agency may request the Bidders’ consent to an extension of the period of validity of their Bids through EPADS v2.0,. The Bid Security provided under ITB 17 shall also be suitably extended. A Bidder may refuse the request without forfeiting its Bid security or causing to be executed its Bid Securing Declaration. A Bidder agreeing to the request will not be required nor permitted to modify its Bid, but will be required to extend the validity of its Bid Security or Bid Securing Declaration for the period of the extension.
18.1 The Bidder shall furnish as part of its Bid, a Bid Security in accordance with Rule 36 of the Public Procurement Rules, 2026.
18.2 The original Bid Security shall be enclosed within the sealed envelope and to be submitted physically before closing time for submission of bids. Whereas, scanned copy of bid security shall be uploaded electronically through EPADS v2.0 before closing hours for submission of bids.
18.3 The Bidder who failed to submit the original Bids security before the submission deadline shall be disqualified straightaway.
18.4 The Bid Security or Bid Securing Declaration is required to protect the Procuring Agency against the risk of Bidder’s conduct which would warrant the security’s forfeiture, pursuant to ITB 18.7.
18.5 The Bid Security shall be denominated in the local currency or in another freely convertible currency, and it shall be in the form specified in the BDS which shall be in any of the following:
a) a bank guarantee, a bank draft, an irrevocable letter of credit issued by a Scheduled bank in the form provided in the Bidding Documents or another form acceptable to the Procuring Agency;
b) a cashier’s or certified cheque; or
c) another security if indicated in the BDS.
The Bid Security shall be valid for twenty-eight (28) days beyond the end of the validity of the Bid. This shall also apply if the period for Bid Validity is extended. In either case, the form must include the complete name of the Bidder.
18.6 The Bid Security shall be payable promptly upon written demand by the Procuring Agency in case any of the conditions listed in ITB 18.7 are invoked.
18.7 Unsuccessful Bidders' Bid Security will be discharged or returned as promptly as possible, however in no case later than thirty (30) days after the expiration of the period of Bid Validity prescribed by the procuring agency pursuant to ITB 17. The Procuring Agency shall make no claim to the amount of the Bid Security, and shall promptly return the Bid Security documents, after whichever of the following that occurs earliest:
18.8 The successful Bidder’s Bid Security will be discharged upon the Bidder signing the contract, or furnishing the Performance Guarantee.
18.9 The Bid Security may be forfeited or the Bid Securing Declaration executed:
19.1 Before Bid submission deadline, any Bidder may withdraw, substitute, or modify its Bid after it has been submitted through EPADS v2.0.
20.1 The Bidder shall prepare and submit Bids with due diligence after carefully reading all the terms and condition before bid submission deadline through EPADS v2.0.
21. Submission of Bids through EPADS v2.0 before bid submission deadline.
21.1 The Technical and Financial Bids, shall be submitted electronically through EPADS, before bid submission deadline. The bid submission option shall be automatically disabled once the deadline is over.
22. Deadline for Submission of Bids
22.1 Bids shall be received by the Procuring Agency through EPADS v2.0 before bid submission deadline.
22.2 The Procuring Agency may, under exceptional circumstances, extend the deadline for the submission of Bids, after recording reasons in writing and in an equal opportunity manner.
In such case, all rights and obligations of the Procuring Agency and the Bidders that were previously governed by the original deadline shall thereafter be subject to the revised deadline.
23.1 The respective Bid Evaluation Committee of the Procuring Agency shall open all Bids through the EPADS v2.0, on the date and time specified in the Bid Data Sheet (BDS).
23.2 The respective Bid Evaluation Committee shall generate minutes through EPADS v2.0 containing brief details of bid opening process. The record of the Bid opening shall include, as a minimum: the name of the Bidder, the Bid price if applicable, and the presence or absence of a Bid Security or Bid Securing Declaration.
23.3 The procuring agency shall live broadcast the opening of bids on national media or on their website or digital channels, if the volume of procurement exceeds five hundred million rupees in case of goods and services and one thousand million rupees in case of works.
23.4 In case the date of opening of bid has been declared as public holiday or the procuring agency fails to open bid due to any EPADS v2.0 related issues, the submission and opening of bids shall be shifted to the next working day at the same time.
23.5 In case of Single Stage One Envelope Procedure, the Bidders names, the Bid prices, the total amount of each Bid and, the presence or absence of Bid Security, Bid Securing Declaration and such other details as the Procuring Agency may consider appropriate, will be announced by the Bid respective Evaluation Committee.
23.6 No bid will be rejected at the time of bid openning except for bids whose original bid security has not been provided to the procuring agency before bid submission deadline.
24.1 To assist in the examination, evaluation and comparison of Bids of the Bidders, the respective Bid Evaluation Committee may, ask any Bidder for a clarification of its Bid including breakdown of prices.
24.2 The request for clarification and the response shall be sought through EPADS v2.0 before three days prior to the deadline for submission of bids. No change in the prices or substance of the Bids shall be sought, offered, or permitted.
24.3 The alteration or modification in the bids which in any way affect the following parameters will be considered as a change in the substance of a Bid:
24.4 From the time of bid(s) opening to the time of Contract award if any Bidder wishes to contact the Procuring Agency on any matter related to the Bids it should do so through EPADS v2.0.
25.1 Prior to the detailed evaluation of Bids, the respective Bid Evaluation Committee will determine whether each Bid:
25.2 The respective Bid Evaluation Committee's determination of a Bid's responsiveness will be based on the contents of the Bid itself.
25.3 A substantially responsive Bid is one which conforms to all the terms, conditions, and specifications of the Bidding documents, without material deviation or reservation. A material deviation or reservation is one that: -
25.4 If a Bid is not substantially responsive, it will be rejected by the respective Bid Evaluation Committee and may not subsequently be evaluated for complete technical responsiveness.
26.1 The respective Bid Evaluation Committee shall examine the Bids to confirm that all terms and conditions specified in the GCC and the SCC have been accepted by the Bidder without any material deviation or reservation.
26.2 The respective Bid Evaluation Committee shall evaluate the technical aspects of the Bids submitted, to confirm that all requirements specified in Schedule of Requirements and Technical Specifications of the Bidding documents have been met without material deviation or reservation.
26.3 If after the examination of the terms and conditions and the technical evaluation, the respective Bid Evaluation Committee determines that the Bid is not substantially responsive in accordance with ITB, it shall reject the Bid.
27.1 Bids determined to be substantially responsive will be checked for any arithmetic errors. Errors will be corrected as follows: -
27.2 The amount stated in the Bid will be adjusted by the respective Bid Evaluation Committee in accordance with the above procedure for the correction of errors and, with the concurrence of the Bidder, shall be considered as binding upon the Bidder. If the Bidder does not accept the corrected amount, its Bid will then be rejected, and the Bid Security may be forfeited or the Bids Securing Declaration may be executed.
28.1 For the purposes of comparison of bids quoted in different currencies, the price shall be converted into a single currency in accordance with Rule 42(2) of Public Procurement Rules,2026.
29.1 The Bids, quotations, or proposals shall be evaluated by the respective evaluation committees as per evaluation criteria prescribed in the Bidding Documents in accordance with Rule 11, 12 and 13 of the Public Procurement Rules, 2026.
29.2 While evaluating the bids, the procuring agency shall consider the following:
i. Bids will be evaluated on lump sum bid basis or items wise or Lot wise (contracts), as specified in the BDS; and the Bid Price;
ii. correction of arithmetic errors in accordance with ITB 27;
30.1 The respective Bid Evaluation Committee shall evaluate and compare bids, allow for preference to domestic bidders, while competing with the international bidders in accordance with the policies of the Federal Government.
The percentage of preference, to be accorded shall be clearly mentioned in the bidding documents under the bid evaluation criteria.
31.1 Selection technique will be adopted for determining the Successful Bid in accordance with the criteria referred in the BDS or prescribed in the separate section titled as Evaluation Criteria.
31.2 Least Cost Based Selection (LCBS)
After meeting the requirements of eligibility, qualification and substantial responsiveness, the bid in compliance with all the mandatory (technical) specifications/requirements and/or requisite quality threshold (if any), and having lowest evaluated cost (or financial proposal) shall be considered Successful Bid.
31.3 Quality and Cost Based Selection (QCBS)
In such combination, there shall be some specific weightage of both the technical features and financial aspects of the proposal. The financial marks shall be awarded on the basis of inverse proportion calculations. The successful bid shall be declared, on the basis of combined evaluation.
31.4 Quality Based Selection (QBS)
After meeting the requirements of eligibility, qualification and substantial responsiveness the bid in compliance with all the mandatory (technical) specifications/requirements and attaining highest marks in the Technical Evaluation considering all other qualitative and/or quantitative parameters (or point rated criteria) for technical proposal(s) such as working methodology, implementation plan, resource allocation, additional functionalities, risk management approach, knowledge transfer techniques, post implementation methodology etc. shall be treated as highest ranked bid. Later on, the financial proposal of highest ranked bidder shall be opened, however, in case of failure to proceed further with such a bidder, the procuring agency may resort to second highest bidder and so on.
31.5 The Procuring Agency may adopt the Quality & Cost Based Selection Technique due to the following two reasons:
1. Where the Procuring Agency knows about the main features, usage and output of the products; however not clear about the complete features, technical specifications and functionalities of the goods to be procured and requires the bidders to submit their proposals defining those features, specifications and functionalities; or
2. Where the Procuring Agency, in addition to the mandatory requirements and mandatory technical specifications, requires parameters specified in Evaluation Criteria to be evaluated while determining the quality of the goods.
31.6 In such cases, the Procuring Agency may allocate certain weightage to these factors as a part of Evaluation Criteria, and may determine the ranking of the bidders on the basis of combined evaluation in accordance with provisions of Rule 2(1)(xxviii) of the Public Procurement Rules, 2026.
32.1 An abnormally low bid is a bid that, in light of the Procuring Agency's cost estimate, market conditions, or other received bids, appears to be unrealistically low and may not be sustainable for successfull contract execution.
32.2 Where the Bid price is considered to be abnormally low, the Procuring Agency shall perform price analysis either during determination of Successful Bids or as a part of the post-qualification process.
32.3 The Procuring Agency may reject an Abnormally low financial bid in accordance with Rule 43 of the Public Procurement Rules, 2026.
32.4 In order to identify the Abnormally Low Bids (ALB) following approaches can be considered to minimize the scope of subjectivity:
32.5 The respective Bid Evaluation Committee will determine to its satisfaction whether the Bidder that is selected as having submitted the successful bid is qualified to perform the contract satisfactorily.
32.6 The determination will take into account the Bidder’s financial, technical, and production capabilities. It will be based upon an examination of the documentary evidence of the Bidder’s qualifications submitted by the Bidder, as well as such other information as the Procuring Agency deems necessary and appropriate. Factors not included in these Bidding documents shall not be used in the evaluation of the Bidders’ qualifications.
32.7 Respective Bid Evaluation Committee may seek “Certificate for Independent Price Determination” from the Bidder and the results of reference checks may be used in determining an award of contract.
Explanation: The Certificate shall be furnished by the Bidder. The Bidder shall certify that the price is determined keeping in view of all the essential aspects such as raw material, its processing, value addition, optimization of resources due to economy of scale, transportation, insurance and margin of profit etc.
32.8 An affirmative determination will be a prerequisite for award of the contract to the Bidder. A negative determination will result in rejection of the Bidder’s Bid, in which event the respective Bid Evaluation Committee will proceed to the next ranked Bidder to make a similar determination of that Bidder’s capabilities to perform satisfactorily.
33. Criteria of Award
33.1 The Procuring Agency will award the Contract to the Bidder whose Bids has been determined to be substantially responsive to the Bidding documents and who has been declared as Successful Bidder.
34. Negotiations
34.1 In accordance with Rule 52A of Public Procurement Rules, 2026, without changing the cost and scope of work or services, the procuring agency may negotiate with the successful bidder (with a view to streamline the work or task execution, at the time of contract finalization) on methodology, work plan, staffing and special conditions of the contract.
There shall be no limitation on the successful bidder offering voluntary reduction in bid price without affecting the quality or scope of the procurement.
35.1 The Procuring Agency reserves the right to reject all bids or proposals at any time prior to the issuance of the Letter of Award, without incurring any liability, in accordance with Rule 45 of the Public Procurement Rules, 2026.
36.1 The procuring agency reserves the right to cancel the procurement proceedings in accordance with Rule 46 of the Public Procurement Rules, 2026.
37.1 The Procuring Agency reserves the right at the time of contract award to increase or decrease the quantity of Goods originally specified in these Bidding documents provided this does not exceed by 15%, without any change in unit price or other terms and conditions of the Bids and Bidding documents.
38.1 Prior to the award of contract, the procuring agency shall announce and publish the result of bid evaluation on EPADS v2.0 in accordance with Rule 48 of the Public Procurement Rules, 2026.
The Bidder whose Bids has been accepted will be notified of the award by the Procuring Agency prior to expiration of the Bids/Bid Validity period. The Letter of Award will state the sum that the Procuring Agency will pay the successful Bidder in consideration for the delivery of Goods as prescribed by the Contract (hereinafter and in the Contract called the "Contract Price).
38.2 The Letter of award will constitute the formation of the Contract, subject to the Bidder furnishing the Performance Guarantee and signing of the contract.
39.1 Promptly after issuance of Letter of award, Procuring Agency shall send the successful Bidder the draft Contract, incorporating all terms and conditions as agreed by the parties to the contract.
39.2 Immediately after the Redressal of grievance by the GRC (if any), and after fulfillment of all conditions precedent of the Contract Form, the successful Bidder and the Procuring Agency shall sign the Contract.
40.1 Procuring Agencies (including beneficiaries of Government funded projects and procurement) as well as Bidders/Contractors under Government financed contracts, observe the highest standard of ethics during the procurement and execution of such contracts, and will avoid engaging in any corrupt and fraudulent practices.
41. Constitution of Grievance Redressal Committee
41.1 The Grievance Redressal Committee shall address the grievance, if any submitted by any party, including the bidder, in accordance with Rule 65 of the Public Procurement Rules, 2026 read with Redressal of Grievances Regulations, 2021.
In case if any party or the bidder is not satisfied with the decision of the GRC or if it fails to decide within ten days, the bidder or the party may file an appeal before the Appellate Committee of the Authority in accordance with Rule 65(7) of the Public Procurement Rules, 2026 to be read with Redressal of Grievances Regulations, 2021.
42. Mechanism of Blacklisting
42.1 The Procuring Agency shall initiate blacklisting proceedings against any bidder, supplier, or contractor in accordance with the Rule 25 of the Public Procurement Rules, 2026.
42.2 The blacklisted/debarred bidder may file the review petition before the Authority in accordance with Rule 25 (6) of the Public Procurement Rules, 2026 to be read with Procedure of filing and disposal of Review Petitions Regulations, 2021.
43.1 For each procurement, the Procuring Agency shall designate a Contract Manager, who shall be duly responsible for the efficient management and administration of the contract in strict compliance with the provisions set forth under Rules 58, 59, and 60 of the Public Procurement Rules, 2026.
44.1 The Inspection Committee or the Firm shall have the right to conduct inspections of the goods in accordance with Rule 61 of the Public Procurement Rules, 2026.
45.1 In accordance with Rule 63 of the Public Procurement Rules, 2026, preference may be granted to small and medium enterprises and marginalized groups in accordance with the policies notified by the Federal Government.
46.1 As per Rule 64 of the Public Procurement Rules, 2026, the procuring agency may seek to procure goods with a reduced environmental impact throughout their life cycle when compared to goods services with the same primary function that may otherwise be procured.
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
BDS Clause Number 1
ITB Number 1.1
Name of Procuring Agency: Institute of Space Technology (Institute of Space Technology)
The subject of procurement is: Purchase of Lab Equipment for NCFA Department
Period for Provision of Goods:
Extension Period (if applicable):
Expected commencement date: Wednesday, December 23, 2026
BDS Clause Number 2
ITB Number 2.1
Source of funds [Enter source of funds]
Financial year for the operations of the Procuring Agency: 2026-27
Name and identification number of the Contract: P210297
Identification Number:
BDS Clause Number 3
ITB Clause Number 3.1
Eligible Bidder [Enter eligibility of bidder]
JV/Consortium or Association Allowed: No
Number of JV/Consortium Members: Nil
see section of eligibility criteria.
BDS Clause Number 4
ITB Clause Number 4.1
Eligible goods and related services [Enter requirements for eligible goods and related services, if any]
ITB Number 8.1
The Bidders may seek clarifications through EPADS v2.0 : Clarification Date: Monday, November 30, 2026
ITB Number 8.2
The Bidders may seek clarifications through EPADS v2.0 : Clarification Date: Monday, November 30, 2026
ITB Number 8.3
The Bidders may seek clarifications through EPADS v2.0 : Clarification Date: Monday, November 30, 2026
ITB Number 8.5
Pre-bid meeting will be/will not be held [Tick the appropriate] If yes write down the time, and date of the pre-Bid meeting:
[The meeting should take place not later than one weeks before the deadline for Bid submission.]
BDS Clause Number 5
ITB Number 10.1
The Language of all correspondences and documents related to the Bids shall be in: English
List of documents required along with the bid:
BDS Clause Number 6
ITB Number 11.1
Documents required / not required with bid submission [enter list of documents] Samples required / not required with the bid [Enter the names and number of samples]
Items/Lots and their related documents:
See section items and Lots
BDS Clause Number 7
ITB Number 12.1
Items / Lots Specifications:
see section of items specifications.
BDS Clause Number 8
ITB Number 15.6
The price shall be Fixed.
BDS Clause Number 9
ITB Number 16.1
Currency of the Bids shall be : PKR
BDS Clause Number 10
ITB Number 17.1
The Bids/Bid Validity period shall be: 90 Days
BDS Clause Number 11
ITB Number 18.1
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6
Instrument of Bid Security shall be in the Name of : Institute of Space Technology
The Bid Security shall be in the form of: Pay Order, Call at Deposit, Demand Draft
ITB Number 18.2
The address for submission of original bid security is [ Insert the address for bid security submission]
BDS Clause Number 12
ITB Number 20.1
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following;
Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory before bid submission deadline.
Bids that are not submitted on EPADS v2.0 shall be disqualified.
The deadline for Bids submission is: Thursday, December 3, 2026 10:00 AM
Day : Thursday
Date: Thursday, December 3, 2026
Time : 10:30 AM
BDS Clause Number 13
ITB Number 23.1
The Bids opening shall take place on EPADS v2.0.
Day : Thursday
Date: Thursday, December 3, 2026
Time : 10:30 AM
ITB Number 29.2
The procuring agency shall consider the following:
lump sum bid basis; or
items wise; or
Lot wise (contracts),
ITB Number 30.1
BDS Clause Number 14
ITB Number 31.1
Domestic Preference [applicable / not applicable]
ITB Number 31.2
Selection technique adopted will be:
The Procuring Agency shall use any of the following evaluation techniques for determination of successful bid.
Least Cost Base Selection (LCBS)
Quality and Cost Based Selection (QCBS)
Quality Based Selection (QBS)
[Insert the Evaluation Technique]
Selection technique adopted will be: Least Cost Based Selection (LCBS)
see Evaluation Criteria
BDS Clause Number 15
ITB Number 41.1
Grievence against this procurement shall be submitted online on EPADS v2.0.
Arbitrator shall be appointed by mutual consent of the both parties.
ITB Number 42.2
The Address of PPRA Grievance Redressal Appellate Committee to submit a copy of grievance:
Grievance Redressal Appellate Committee,
Public Procurement Regulatory Authority
1st Floor, G-5/2, Islamabad, Pakistan
Tel: +92-51-9202254
All Active Taxpayers shall be eligible to participate in the procurement process, unless expressly excluded or otherwise restricted under the Eligibility Criteria specified by the Procuring Agency.
| Required Registration |
|---|
|
NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) |
| Eligibility Criteria | Document |
|---|---|
| CNIC of Owner/CEO/Authorized Rep of bidder along with authorization letter. | Yes |
| NTN Certificate (Filer) with FBR | Yes |
| GST Certificate (Active) with FBR | Yes |
| Affidavit of Non blacklisting and acceptance of terms and conditions of bidding documents on E-stamp paper | Yes |
| Bid Security of required amount of quoted equipment to be submitted in hardcopy and softcopy | Yes |
| Authorization letter from OEM for participating and quoting in this tender and providing after sales services | Yes |
Eligibile bidder(s) with substantially responsive bid(s) offering Least Cost Based Selection (LCBS) shall be consider for the award of contract(s).
Least Cost Based Selection (LCBS)
Weightage
| Technical Evaluation % |
|---|
| 100 |
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 75 | |
| Technical Evaluation Criteria | ||
| NTN Certificate Filer with FBR (Quantitative)(Doc Required) | 10 | |
| GST Active certificate with FBR (Quantitative)(Doc Required) | 10 | |
| SECP incorporation certificate (Quantitative)(Doc Required) | 10 | |
| Affidavit of non blacklisting and acceptance of terms and conditions of bidding documents on e stamp paper (Quantitative)(Doc Required) | 10 | |
| Bid security of required amount for each quoted equipment (Quantitative)(Doc Required) | 10 | |
| 100 percent compliance of quoted equipment with required specifications along with valid authorization letter from OEM (Quantitative)(Doc Required) | 50 | |
Items Without Lots :
| Item | UNSPSC | Delivery Schedule | Quantity | Bid Security | Manufacturer / Dealer Authorization | Warranty |
|---|---|---|---|---|---|---|
| X Ray Diffractometer (XRD System )(RFQ-2627-00076-L) | X ray diffraction equipment |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 1300000 PKR | -- | 5 Years |
| X-Ray Fluorescence Spectrometer-Floor Mounted( RFQ-2627-00078-L) | Spectrometers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 1800000 PKR | -- | 5 Years |
| X-Ray Fluorescence Spectrometer-Hand Held (RFQ-2627-00079-L) | Spectrometers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 240000 PKR | -- | 5 Years |
| Impact Testing Machine for NCFA Lab(RFQ-2627-00085-L) | Impact testers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 800000 PKR | -- | 5 Years |
| Universal Macro Hardness Tester(RFQ-2627-00077-L) | Hardness testers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 800000 PKR | -- | 5 Years |
| Portable Hardness Tester (RFQ-2627-00077-L) | Hardness testers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 300000 PKR | -- | 5 Years |
| Shore Hardness Tester (RFQ-2627-00077-L) | Hardness testers |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 60000 PKR | -- | 5 Years |
| Cold Mounting (RFQ-2627-00080-L) | Adhesive mounts |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 120000 PKR | -- | 5 Years |
| Power Hacksaw Machine (RFQ-2627-00080-L) | Hacksaw |
Address: Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
Schedule: 120 days
Quantity: 1/Qty
|
1/Qty | 60000 PKR | -- | 5 Years |
Yes
| Item | UNSPSC | Related Services |
|---|---|---|
| X Ray Diffractometer (XRD System )(RFQ-2627-00076-L) | X ray diffraction equipment | With installation, commissioning and training |
| X-Ray Fluorescence Spectrometer-Floor Mounted( RFQ-2627-00078-L) | Spectrometers | With installation, commissioning and training |
| X-Ray Fluorescence Spectrometer-Hand Held (RFQ-2627-00079-L) | Spectrometers | With installation, commissioning and training |
| Impact Testing Machine for NCFA Lab(RFQ-2627-00085-L) | Impact testers | With installation, commissioning and training |
| Universal Macro Hardness Tester(RFQ-2627-00077-L) | Hardness testers | With installation, commissioning and training |
| Portable Hardness Tester (RFQ-2627-00077-L) | Hardness testers | With installation, commissioning and training |
| Shore Hardness Tester (RFQ-2627-00077-L) | Hardness testers | With installation, commissioning and training |
| Cold Mounting (RFQ-2627-00080-L) | Adhesive mounts | With installation, commissioning and training |
| Power Hacksaw Machine (RFQ-2627-00080-L) | Hacksaw | With installation, commissioning and training |
Items Without Lots :
Item: X Ray Diffractometer (XRD System )(RFQ-2627-00076-L)
UNSPSC: X ray diffraction equipment
Specifications / Requirementsss:
X-RAY DIFFRACTOMETRY (XRD) SYSTEM – TECHNICAL SPECIFICATIONS System & Configuration: Fully automated, floor-standing XRD system for qualitative and quantitative identification of compounds and phases in bulk solids, powders and thin films, with provision for future upgrades, including high-temperature in-situ measurements. X-ray Source & Generator: High-resolution Cu Kα tube with selectable line/point focus (line focus for routine operation); sealed high-power solid-state generator; power 3–4 kW; operating range 20–60 kV and 2–60 mA or better. Provision for optional Co Kα source with required optics, alignment, safety arrangements and software modifications for Fe/steel-based materials and corrosion products. Goniometer & Measurement: Vertical Theta/Theta goniometer with horizontal sample mounting; angular resolution approximately 0.00001° and FWHM approximately 0.03°; optical encoder-controlled automatic alignment; 2θ measurement range approximately -5° to 160° or wider. Optics & Slits: Switchable Bragg-Brentano and parallel-beam optics; adjustable beam-shaping slits for precise sample illumination and analysis of rough surfaces/corrosion layers. Variable receiving slit 0.05–20 mm (0.01 mm steps). Required accessories: Incident Soller Slits (2.5/5/open), Receiving Soller Slits (2.5/5), Parallel Slit Analyzer (0.22/5), short incident Soller slit masks, Ni-beta filter, knife edge/blade and 0.3 mm × 8 mm collimator, attenuator and scattered-radiation protection. Detector & Sample Handling: High-end, ultra-fast 0D/1D detector with high angular and energy resolution and active area approximately 384 mm² or closest available. Bulk sample attachment for 1–20 mm thickness/height. Twenty (20) aluminium/glass sample holders and ten (10) Si low-background holders for multisampling and small powder quantities. Cooling & Electrical Requirements: Chiller preferably 7,000 W cooling capacity at 25°C, with bypass valve, meeting equipment/site requirements. Operating supply 220–240 V, 50/60 Hz. Two UPS systems, each providing minimum 30-minute backup at full system load (one optional), and suitable high-sensitivity voltage stabilizer (optional). Computer & Software: Dedicated PC with Intel Core i7 or better, Windows 11, MS Office, 64 GB RAM, 2 TB SSD and separate 32-inch LCD monitor. One licence for the latest software version, including powder XRD, qualitative/quantitative analysis, crystallite size, lattice strain, crystalline/amorphous ratio and Rietveld analysis. Fluorescence mode with selectable energy windows for suppressing Fe fluorescence. ICDD PDF-2+ database or better, with five-year licence. Software updates, activation keys and passwords shall remain free of cost throughout equipment life. Calibration & Safety: Supply of NIST-certified Si and LaB₆ powder standards for peak-position and FWHM calibration/verification. Certified radiation-safety enclosure with relevant ISO certification; radiation leakage/safety test certificates. Supply of a portable, high-sensitivity calibrated Geiger-Müller survey meter with audible/visual alarms and digital dose/count-rate display. Complete five-year spare-parts kit. Installation & Site Preparation: Supplier shall undertake complete installation, commissioning and performance verification through OEM/factory-trained engineers, including all necessary laboratory/site preparations, flooring, levelling, vibration control, separate protective earthing/grounding and civil/electrical works required for safe and optimum operation. All transportation, insurance, port clearance, duties and taxes up to IST shall be included in the quoted price. Documentation & Technical Support: Complete soft and hard copies of operation, application, service and maintenance manuals in English, parts catalogue, error codes, parameters, activation keys, passwords, diagnostic/interface software, drivers and complete system backup. OEM shall provide remote technical support, lifetime availability of spares, attachments, repairs and free software/manual updates. Training: Minimum five days' on-site operational, maintenance and advanced application training at IST for at least four faculty members, preferably by OEM specialists. Additionally, five days' factory-site application training for two nominated persons, with all associated expenses borne by supplier. Performance verification using standard samples shall be conducted during training. Warranty & After-Sales Service: Minimum five-year comprehensive warranty covering parts and services, including replacement of the Cu X-ray tube once required. Supplier shall ensure lifetime availability of spare parts, accessories, repairs and technical support. Bidders shall provide details of Pakistani institutions where the offered equipment or its closest model has been supplied, including end-user contact details and after-sales service history (maintenance, calibration, spares and attachments).Item: X-Ray Fluorescence Spectrometer-Floor Mounted( RFQ-2627-00078-L)
UNSPSC: Spectrometers
Specifications / Requirementsss:
EDXRF SYSTEM - TECHNICAL SPECIFICATIONS Supply/install/commission new, manufacturer-supported, fully shielded laboratory EDXRF for qualitative, semi-quantitative and validated quantitative analysis of minerals/ores/concentrates. Include software/methods, preparation equipment, small-sample kit, CRMs, 2,000-sample consumables, training and 5-year warranty. M=mandatory; O=optional; equivalents require proof. **1. ANALYSER** Range: Na(Z=11) to U(Z=92), or closest; state limitations, ranges, LOD/LOQ by matrix/analyte. Majors wt%, traces ppm; oxides labelled calculated. Accept powder cups, pellets, flat solids (fused beads optional); declare limits. Tube up to 50 kV or proven equivalent, anode/cooling, auto-filters and secondary targets/polarizing optics/equivalent. Thermo-cooled SDD/equivalent, no liquid nitrogen; Mn K-alpha FWHM <=150 eV (<=140 preferred), >=4096 channels, raw spectra, deconvolution/export. Chamber for 32-40 mm cups/pellets; air/low-absorption and vacuum/pump with powder protection or approved equivalent Na/Mg/Al/Si/P results. >=10-position changer/equal throughput, rotation/equivalent. Declare make/model, source, detector, optics, atmosphere, accessories. Helium optional. **2. EIGHT MANDATORY MATRICES** Demonstrate FP and calibrated quantitative modes on iron ore (hematite/magnetite), chromite, talc/soapstone, rock phosphate, copper ore, copper concentrate, lead-zinc ore and limestone/dolomite. Copper ore/concentrate separate; carbonates may share approved method. Use matrix CRMs or approved characterized samples. Iron: Fe,Si,Al,P,S,Mn,Ca,Mg,Ti; As,Pb,Zn,Cu,Ni,Cr,V. Chromite: Cr,Fe,Mg,Al,Si,Ca,Ti; V,Ni,Mn,Co,Zn,P,S. Talc: Mg,Si,Ca,Fe,Al,K,Na; Cr,Ni,Mn,As,Pb. Phosphate: P,Ca,Si,Al,Fe,Mg,S,Sr; Cd,As,Pb,U,Th (F if validated). Copper ore/concentrate: Cu,Fe,S,Zn,Pb; As,Mo,Ag,Au if validated. Lead-zinc: Pb,Zn,Fe,Cu,S; As,Cd,Ag. Limestone/dolomite: Ca,Mg,Si,Al,Fe,S,Mn; Sr. State quant/screening/unsupported status, range, LOD/LOQ for each matrix/analyte/mode. Declare Hg,Sb,Ba,Co,Zr,Nb,Mo,Ag,Au; demonstrate overlap corrections (As/Pb, Ti/V, Fe/Co). Optional: bauxite, barite, fluorspar, quartz, gypsum, REEs, F/B/C/O methods; price/validate separately. **3. SOFTWARE, CALIBRATION, QC** Licensed selectable standardless FP, no empirical matrix calibration applied to FP results. Identify FP reports; disclose factory models; show all 8 matrices without tuning against test CRMs. Train for new-matrix calibration. Provide licensed user-created/edited multipoint matrix calibrations with background/overlap corrections; deliver 8 methods. List analytes/ranges, atmosphere, prep, time, LOD/LOQ. Use matrix CRMs (>=3 levels if available); verify with independent CRMs not used for calibration; report bias/recovery/RSD. Hand over methods/files/SOPs/QC; perpetual licences, no annual fees; raw data access. **4. SAMPLE PREPARATION AND SUPPLIES** Itemize oven >=110 C, jaw crusher, mill >=95% passing 75 um, vessels/spares, splitter, 75/150/250 um sieves, guarded pressure-controlled pellet press, 32/40 mm dies, 0.001 g balance, dust control/SOPs. Declare contamination; fusion optional. Include small-sample holders, micro-cups, reusable 3/5 mm masking disks (or nearest), spares; demonstrate. Consumables for >=2,000 preparations/measurements: cups/rings, films/seals, binder; state mix, quantities, part numbers, shelf life, refill prices. Include CRMs, independent QC and spares; preparation/kit M/O itemized. **5. PERFORMANCE, SAFETY, ACCEPTANCE** Pre-award submit exact-model data per matrix/mode: ranges, LOD/LOQ, CRMs, prep, atmosphere, time, bias/recovery/RSD; demonstrate both modes; agree pass/fail schedule. Site IQ/OQ/PQ for all 8; >=5 repeats of one specimen and >=3 independently prepared aliquots on >=2 matrices. At >=10xLOQ, CRM RSD <=2% (>=1 wt%) and <=5% (0.1-<1 wt%); agree others. Verify decision-level LOQ/accuracy (phosphate As/Cd; iron P/S). Provide raw spectra/signed reports; retest failures free; acceptance/payment after PQ. Shielding, fail-safe interlocks, warnings, emergency stop, leakage check, PNRA licensing documents/support. 220-240 V, 50 Hz; load/earthing; UPS/printer priced; remote access only if approved. **6. WARRANTY AND BID** 5-year comprehensive on-site warranty from final acceptance: tube, detector, analyser, changer, vacuum, workstation, software, preparation equipment, parts/labour/travel; declare exclusions. Annual maintenance, Pakistan service, >=7-year spares, security updates. Include delivery, installation, training, manuals, licences, essentials; no later essential purchases or unapproved substitutions. Submit datasheets, clause-wise compliance, matrix/analyte/mode schedule (Excel+signed PDF), BOQ, warranty/service plan, separate prices for analyser, software, preparation/kit, CRMs, 2,000 consumables, UPS, helium/fusion, installation, training, warranty and recurring costs.Item: X-Ray Fluorescence Spectrometer-Hand Held (RFQ-2627-00079-L)
UNSPSC: Spectrometers
Specifications / Requirementsss:
Handheld X-Ray Fluorescence (XRF) Analyzer Handheld, tube-based XRF analyzer with dedicated mining/geochemical applications for rapid elemental analysis of rocks, ores, minerals, drill cores, soil, sediment and outcrop samples. Manufacturer shall be American, European, Japanese or equivalent. Equivalent or superior commercially available models may be offered, with limitations clearly identified. 1. X-Ray Source & Detector Miniature X-ray tube, selectable voltage approximately 6–50 kV, Ag/Rh/W or equivalent anode; declare power, current and operating parameters. Large-area SDD or equivalent detector with cooling and protection. Energy resolution ≤150 eV FWHM at Mn Kα (5.9 keV); declare count-rate performance. Automatic multi-filter system with minimum 5 positions or equivalent. 2. Measurement & Elemental Analysis Analysis spot ≤8 mm, optional collimated spot ≤5 mm; laser targeting and preferably integrated camera. Measurement time 1–60 seconds, with repeat readings and averaging. Results in ppm/mg/kg and wt%; oxide values, if provided, must be identified as calculated. Desirable elemental range Mg (Z=12) to U (Z=92), including Mg, Al, Si, P, S, Cl, K, Ca, Ti, V, Cr, Mn, Fe, Co, Ni, Cu, Zn, As, Se, Rb, Sr, Y, Zr, Nb, Mo, Ag, Cd, Sn, Sb, Ba, W, Hg, Pb, Bi, Th and U. Clearly identify quantitatively supported, qualitative and unsupported elements. State quantitative capability for La, Ce, Pr and Nd; quote optional REE package separately. Include mining/geochemistry, rock/ore and soil/sediment modes with applicable element lists and calibrations. Provide element-wise LOD/LOQ, accuracy, precision and measurement time for representative geological matrices, including light-element performance (Mg, Al, Si, P, S) and required accessories. 3. Calibration & Quality Control Include Fundamental Parameters (FP) and mining/geochemical calibration, with empirical/matrix-matched calibration where available. Provide calibration scope, matrices, element coverage, limitations, interference corrections and semi-quantitative elements. Include standardization, diagnostics, drift/repeatability checks and suitable certified reference materials (CRMs) with certificates; quote CRM set separately. 4. Samples, Software & Data Support direct analysis of rocks, ores, drill cores, soil and sediment, and prepared powders/pellets where compatible; specify preparation requirements. Onboard spectra/results display, sample/operator records, date/time and access to raw/processed spectra. CSV/XLSX and PDF data export, GPS/geotagging, USB and Wi-Fi/Bluetooth connectivity. Include compatible PC software, licenses, custom sample IDs, repeated readings, averaging, backup and data transfer. 5. Construction, Power & Safety Operating temperature at least -10°C to +50°C and humidity 10–90% non-condensing; declare IP and drop/shock ratings. Rechargeable battery providing minimum 8 hours typical operation; include charger and 220–240V, 50Hz adapter. Quote spare battery separately. Declare dimensions and operating weight. Include X-ray interlock, automatic shutdown, shielding, warning indicators, safety instructions and applicable certifications. 6. Supply, Installation & Training Complete analyzer with software, battery, charger, carrying case, protective accessories, interfaces, licenses and all operational accessories. Provide soft/hard copies of operation, service and maintenance manuals, parts catalogue, error codes and applicable activation keys/passwords. Free on-site installation, commissioning and OEM-led practical training of at least four faculty members at IST, Islamabad, covering operation, safety, sample preparation, calibration, maintenance, troubleshooting and data export. Demonstrate performance using standard geological samples. Include all delivery, freight, clearance, duties and taxes up to IST. 7. Warranty, Service & Acceptance 5-year manufacturer warranty; specify coverage, exclusions, response time and extended warranty options. Guarantee spare parts, accessories, repairs and technical/software support; declare tube life, maintenance and service arrangements in Pakistan. Provide references of Pakistani organizations using the offered or closest model, with end-user contacts and service history. Before acceptance, demonstrate performance using agreed geological CRMs/check samples against pre-agreed element- and matrix-specific criteria for accuracy, repeatability and LOD. 8. Bid Submission Provide manufacturer, exact model/configuration, official datasheet, element/mode list, performance and calibration data, accessories/software, compliance statement, warranty, training plan, delivery schedule and itemized price inclusive of all costs up to IST, Islamabad.Item: Impact Testing Machine for NCFA Lab(RFQ-2627-00085-L)
UNSPSC: Impact testers
Specifications / Requirementsss:
Impact Testing Machine • Impact testing machine for metallic, composites and polymeric materials capable of performing Charpy (V-notch/U-notch) and Izod impact tests. • Pendulums for 300J and 50J Test capacity desirable. Conforming to ASTM E23, ASTM A370, ISO 148-1, ISO 14556 and EN ISO 148. • ASTM/ISO Charpy and Izod specimen supports. • Calibration Attachment. Optional cryogenic testing, • Sample preparation setup (Charpy notch milling machine, motorized broaching machine, notch profile projector/optical comparator, lathe machine, precision specimen milling machine, etc., all as option). • Online UPS compatible with equipment (5Kv or higher) • 5 years’ warranty. Should be of a reputable manufacture. Operation, Service, Maintenance and Calibration Manuals • Soft and hard copy of the operation, service & maintenance manuals including parts catalogue; error code & parameters list should be provided. Installation & training: • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentItem: Universal Macro Hardness Tester(RFQ-2627-00077-L)
UNSPSC: Hardness testers
Specifications / Requirementsss:
Universal Macro Hardness Tester Make: America/EU/Germany/Japan or Equivalent Type: Rockwell, Vickers, or Brinell Load range 3 KGf-3000 KGf or closest Accuracy: ±0.5 HRC/HV/HB Automatic calculation of hardness. Must comply following latest edition of ASTM Standards (Brinell E-10, Rockwell E018, Vickers E92) for Verification, Accuracy and Error Repeatability. Features: Digital display, automatic load selection, Camera: 20 Megapixels, Full HD camera system, with zoom and auto-focus Objectives: Wide Range of Objectives 7 or more Position Auto Turret: For Indenters & Objectives (in addition – manual optional) Spindle: motorized Z-Axis XY-Stage: 370 mm x 447 mm or closest Work piece Acc.: 500mm (H) X 310mm (D) or closest 220 VAC/50Hz Display: 22” full color touch screen (If Not built in with equipment a separate complete compatible PC latest version of windows or upgradeable to latest version system should be supplied) Control: Fully integrated Windows Controller, SSD hard disk, Windows 11 operated advanced workflow software, includes automatic measurement, keyboard & mouse. Software: No. of tests, Mean, St. Deviation, Min., Max., Range, individual readings list, storage memory, Dwell time, test force setting, scale selection, calibration etc. Load App. System: Fully automatic, Load cell, closed loop, force feedback Illumination: Power LED or better List of Certified Reference Test Blocks for Rockwell, Vickers, Brinell & Knoop (Basic to superficial levels) for selection may be provided. Indenters Vickers (Rockwell, Vickers, or Brinell). Reference blocks with calibration certificate traceable to international standards (specify the reference value of hardness test block) Maintenance gadgets, Operational/safety manuals, guide CDs, etc. Indenters 05 Extra each (Rockwell, Vickers, or Brinell) Table for different geometry products (to be discussed with supplier) Advanced Output: Multi USB, CSV files, single readings, reports • All possible holders/grips for holding samples of different geometries (Different sizes of rods, bars or small to large samples) may be quoted as option. Stage Micrometer (Optional) • Two UPS systems and each capable of providing a minimum backup time of 30 Minutes at full system load. (1 Optional) • A Stabilizing system with high sensitivity and suitability with the above equipment. (Optional) • Efficient support by OEM through remote access to equipment parameters and software if required. Operation, Service, Maintenance and Calibration Manuals • Soft and hard copy of the operation, service & maintenance manuals including activation keys, passwords; parts catalogue; error code & parameters list should be provided. • Availability of spares parts. The vendor has to guarantee the availability of attachments, spares support, repair and free of cost update throughout life of Equipment. • Update of Software and Manuals should be free of cost with provision of passwords throughout life of equipment. Complete backup of equipment system • software with interfacing & diagnostic software and drives. Installation & training: • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Minimum Warranty for 5 years • Should not require update in software on payment (It should be life time valid) • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentItem: Portable Hardness Tester (RFQ-2627-00077-L)
UNSPSC: Hardness testers
Specifications / Requirementsss:
Portable Hardness Tester Preferably Equotip 550 (2 in 1, Leeb + UCI) GE/Baker Hughes (Krautkramer), INNOVATEST, TIME Group, Beijing ERA or Equivalent Measurement range Up to 850 HLD Up to 950 HV Up to 65 HRC Units HLD, HV, HB, HRA, HRB, HRC, HS or equivalent Accuracy ± 4HLD, ±2% HV or closest Display Minimum 7 inches, Touch Screen or closest Display resolution 800 × 480 pixels or closest Protection class Minimum IP 54 or closest Operating temperature Up to 40 °C Battery Rechargeable, Minimum 4 hours operation time, Kindly quote separate battery as an option Power adapter , charger 100 – 240 V AC Memory Minimum 8 GB Data recorder Data saving and report generation PC Interface Via USB Cable, PC software to see and manage data. Package Required Main Unit Portable Hardness Tester (2 in 1) Leeb + UCI D type Probe with cable and calibration block UCI Probe with cable, special foot Leeb D type probe with cable Leeb D type block 75HLD UCI probe with cable (HV1 – HV10) or closest UCI Test Block ̴850HV (Other probes may be quoted as option) Battery, Charger, USB cable, Operating Manual, Certificates Carry Case Efficient support by OEM through remote access to equipment parameters and software if required. Supplier to have and submit OEM Authorized Approval Certificate for Training and After Sale Support along with references of last 3 sales in Pakistan • Efficient support by OEM through remote access to equipment parameters and software if required. Operation, Service, Maintenance and Calibration Manuals: • Soft and hard copy of the operation, service & maintenance manuals including activation keys, passwords; parts catalogue; error code & parameters list should be provided. • Availability of spares parts. The vendor has to guarantee the availability of attachments, spares support, repair and free of cost update throughout life of Equipment. • Update of Software and Manuals should be free of cost with provision of passwords throughout life of equipment. Complete backup of equipment system • software with interfacing & diagnostic software and drives. Installation & training: • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Preferrable Warranty for 5 years • Should not require update in software on payment (It should be life time valid) • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentItem: Shore Hardness Tester (RFQ-2627-00077-L)
UNSPSC: Hardness testers
Specifications / Requirementsss:
Shore Hardness Tester Type: Digital Shore Hardness Tester, Shore A and Shore D, suitable for rubber, elastomers, plastics and polymeric materials. Scales: Shore A and Shore D with interchangeable/separate indenters or equivalent dual-scale configuration. Measuring Range: 0–100 HA/HD. Resolution: 0.1 Shore Unit or better. Accuracy: ±1 Shore Unit or better. Repeatability: ±0.5 Shore Unit or better. Standards: ASTM D2240 and ISO 868; ISO 48-4/DIN ISO 7619-1 or equivalent preferred where applicable. Display: Digital LCD with clear hardness reading and measurement status. Measurement Functions: Instantaneous/peak hold, average and statistical measurement functions. Test Stand: Bench-mounted test stands with controlled test-force application and adjustable dwell time to minimize operator-dependent variation. Calibration/Verification: Supplied with certified Shore A and Shore D reference blocks; calibration certificate preferably traceable to ISO/IEC 17025. Data Management: Internal data storage with USB/PC connectivity and data-transfer software. Construction: Robust digital durometer suitable for laboratory and field use. Power: Rechargeable batteries or standard replaceable batteries. Accessories: Shore A & D indenters (qty 5 each as option), test stand, certified reference blocks, carrying case, USB/data cable, software, operating manual and calibration certificate. Preferred Make/Model: Bareiss HPE III / Digi Test II, Mitutoyo, Reputed Chinese manufacturers such as TIME Group, Sinowon or equivalent. • Efficient support by OEM through remote access to equipment parameters and software if required. Operation, Service, Maintenance and Calibration Manuals: • Soft and hard copy of the operation, service & maintenance manuals including activation keys, passwords; parts catalogue; error code & parameters list should be provided. • Availability of spares parts. The vendor has to guarantee the availability of attachments, spares support, repair and free of cost update throughout life of Equipment. • Update of Software and Manuals should be free of cost with provision of passwords throughout life of equipment. Complete backup of equipment system • Software with interfacing & diagnostic software and drives. Installation & training: • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Preferably Warranty for 5 years • Should not require update in software on payment (It should be life time valid) • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentItem: Cold Mounting (RFQ-2627-00080-L)
UNSPSC: Adhesive mounts
Specifications / Requirementsss:
Cold Mounting Preferred Model: VACUMET 52 or Equivalent Manufacturer: Metkon, Struers, QATM, Buehler, PRESI, Akasel, Times or equivalent reputed manufacturer. Desktop-type, self-contained vacuum impregnation and cold mounting unit. Vacuum: ≥ -0.65 bar or closest, with built-in vacuum gauge/manometer. Adjustable/controlled vacuum cycle with facility to maintain vacuum for effective resin penetration. Transparent, vacuum-rated cover/chamber for visual monitoring. Suitable for multiple specimens, including porous, cracked, hollow, composite and coated samples. Suitable for vacuum impregnation, cold mounting and gluing specimens to glass slides for thin-section analysis. Curing time: preferably ≤10 minutes, 5–10 minutes, using supplied/approved fast-curing resin system. Suitable for metals, composites, ceramics, rocks/minerals, electronic components and thermal-spray coatings. Power: 220–240 V, 1-phase, 50 Hz. Supplied with 30 mixing bowls, 30 silicone hoses, 30 wooden stirrers, 10 graduated syringes and required mounting molds. General-purpose low-shrinkage epoxy: minimum 5 kg resin + 2.5 kg hardener. Conductive resin for SEM: minimum 1 kg resin + 0.5 kg hardener. Equipment shall preferably accept commercially available equivalent mounting resins and shall not be restricted exclusively to OEM consumables. Spares & Consumables for 5 Years The supplier shall quote sufficient essential consumables and recommended spare parts for a minimum operational period of five (5) years. • Efficient support by OEM through remote access to equipment parameters and software if required. Operation, Service, Maintenance and Calibration Manuals: • Soft and hard copy of the operation, service & maintenance manuals including activation keys, passwords; parts catalogue; error code & parameters list should be provided. • Availability of spares parts. The vendor has to guarantee the availability of attachments, spares support, repair and free of cost update throughout life of Equipment. • Update of Software and Manuals should be free of cost with provision of passwords throughout life of equipment. Complete backup of equipment system • software with interfacing & diagnostic software and drives. Installation & training: • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from preferably OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Preferably Warranty for 5 years • Should not require update in software on payment (It should be life time valid) • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentItem: Power Hacksaw Machine (RFQ-2627-00080-L)
UNSPSC: Hacksaw
Specifications / Requirementsss:
Power Hacksaw Preferred Origin: China, Taiwan, Japan, or other reputed manufacturer The Power Hacksaw shall be heavy-duty industrial reciprocating type for cutting ferrous/non-ferrous metals, bars, pipes and sections, with minimum 320 mm round and 290 × 290 mm square cutting capacity. It shall operate on 380–415 V, 3-Phase, 50 Hz supply with a minimum 3.0 kW (4 HP) motor and provide adjustable blade speeds of approximately 40–70 strokes/minute, emergency stop and necessary safety guards. The machine shall have hydraulic/mechanical adjustable down-feed and cutting-pressure control, heavy-duty vice with angular cutting facility, and automatic cut-off. It shall include blade lifting/return-stroke mechanism, integrated coolant tank, pump and coolant delivery system. Two UPS systems and each capable of providing a minimum backup time of 30 Minutes at full system load. (1 Optional) OPTIONAL: • The machine shall be supplied with HSS/bi-metal hacksaw blades, blade tensioning tools, work piece support/roller arrangement and all standard operating accessories • The supplier shall provide critical spare parts and consumables for 10 years of normal operation, including blades, belts, bearings, seals, fuses/relays and other recommended wear parts. • Minimum 40 heavy-duty HSS/bi-metal power hacksaw blades, compatible with the offered machine, in assorted tooth pitches (4, 6, 8 and 10 TPI or equivalent) suitable for cutting mild/alloy steels, hard steels, stainless steels, duplex stainless steels and nickel-base alloys. • Blades shall be of reputed manufacturer/industrial grade, with blade length, width and thickness suitable for the offered machine, and shall be supplied with appropriate blade tensioning/mounting accessories. • Efficient support by OEM through remote access to equipment parameters and software if required. • A Stabilizing system with high sensitivity and suitability with the above equipment. Operation, Service, Maintenance and Calibration Manuals • Soft and hard copy of the operation, service & maintenance manuals including activation keys, passwords; parts catalogue; error code & parameters list should be provided (where applicable) • Availability of spares parts. The vendor has to guarantee the availability of attachments, spares support, repair and free of cost update throughout life of Equipment. Installation & training • Free of cost on-site installation, maintenance and troubleshooting training for at least 04 persons from faculty will be given in IST from OEM expert. • Verification of performance at the time of training. • All charges within Pakistan till delivery in IST including port clearances and taxes should be mentioned in quote. • Testing of the standard samples to validate the specifications. • Preferably Warranty for 5 years • Organizations where the equipment or its closest model has been supplied in Pakistan; name and contact number of the end user. Services provided to the end user since it has been sold; include maintenance; calibration; supply of spares and, or attachments. Note: Above mentioned specifications are desirable for the selection of the equipmentFor Individual Items
| # | Item Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
1. Definitions
For the purposes of this Contract, “Force Majeure” means an event which is beyond the reasonable control of a Party, is not foreseeable, is unavoidable, and its origin is not due to negligence or lack of care on the part of a Party, and which makes a Party’s performance of its obligations hereunder impossible or so impractical as reasonably to be considered impossible in the circumstances. and includes, but is not limited to, war, riots, civil disorder, earthquake, fire, explosion, storm, flood, epidemics, or other adverse weather conditions, strikes, lockouts or other industrial action (except where such strikes, lockouts or other industrial action are within the power of the Party invoking Force Majeure to prevent), confiscation or any other action by Government agencies.
2. Application and Interpretation
2.1 These General Conditions shall apply to the extent that they are not superseded by provisions of other parts of the Contract.
2.2 In interpreting these Conditions of Contract headings and marginal notes are used for convenience only and shall not affect their interpretations unless specifically stated; references to singular include the plural and vice versa; and masculine include the feminine. Words have their ordinary meaning under the language of the Contract unless specifically defined.
3. Applicable Law
3.1 The contract shall be governed and interpreted in accordance with the laws of Pakistan, unless otherwise specified in SCC.
4. Governing Language
4.1 The Contract as well as all correspondence and documents relating to the Contract exchanged between the Bidder and the Procuring Agency, shall be written in the English language unless otherwise stated in the SCC. Supporting documents and printed literature that are part of the Contract may be in another language provided these are accompanied by an accurate translation of the relevant passages in English, in which case, for purposes of interpretation of the Contract, this translation shall govern.
5. Notices
5.1 Any notice, request, or consent made pursuant to this Contract shall be in writing and shall be deemed to have been made when delivered in person to an authorized representative of the Party to whom the communication is addressed, or when sent by registered mail, telex, telegram, or facsimile to such Party at the address specified in the SCC.
6. Standard
6.1 The Goods supplied under this Contract shall conform to the standards mentioned in the Technical Specifications, and, when no applicable standard is mentioned, the American Standards (such as ACI, IEEE, ASME, etc.) or the Pakistani standards such as PSQCA Such standards shall be the latest issued by the concerned institution.
7. Delivery/Location
7.1 The Goods shall be delivered to such locations as the Procuring Agency may approve and as specified in SCC.
8. Authorized Representatives / Authority of Member in charge
8.1 Any action required or permitted to be taken, and any document required or permitted to be executed, under this Contract by the Procuring Agency or the Bidder may be taken or executed by the officials specified in the SCC.
8. Effectiveness of Contract
8.1 This Contract shall come into effect on the date the Contract is signed by both parties and such other later date as may be stated in the SCC.
9. Commencement of the Contract
9.1 The Bidder shall confirm availability of Key Experts and begin carrying out the Services not later than the number of days after the Effective Date specified in the SCC.
10. Program
10.1 Before commencement of the Contract, the Bidder shall submit to the Procuring Agency for approval a Program showing the general methods, arrangements, order and timing for all activities. The Services shall be carried out in accordance with the approved Program as updated.
11. Starting Date/Expiration Date
11.1 The Bidder shall start carrying out the Services Five (05) days after the date the Contract becomes effective, or at such other date as may be specified in the SCC.
11.2 Unless terminated earlier pursuant to Clause GCC 16 hereof, this Contract shall expire at the end of such time period after the Effective Date as specified in the SCC.
12. Entire Agreement
12.1 This Contract contains all covenants, stipulations and provisions agreed by the Parties. No agent or representative of either Party has authority to make, and the Parties shall not be bound by or be liable for, any statement, representation, promise or agreement not set forth herein.
13. Modification
13.1 Any modification or variation of the terms and conditions of this Contract, including any modification or variation of the scope, may only be made by written agreement between the Parties. However, each Party shall give due consideration to any Bids for modification or variation made by the other Party.
13.2 In cases of any modifications or variations, the prior written consent of the Procuring Agency is required.
14. Force Majeure
14.1 Definition
For the purposes of this Contract, “Force Majeure” means an event which is beyond the reasonable control of a Party and which makes a Party’s performance of its obligations under the Contract impossible or so impractical as to be considered impossible under the circumstances.
14.2 No Breach of Contract
The failure of a Party to fulfill any of its obligations under the contract shall not be considered to be a breach of, or default under, this Contract in so far as such inability arises from an event of Force Majeure, provided that the Party affected by such an event (a) has taken all reasonable precautions, due care and reasonable alternative measures in order to carry out the terms and conditions of this Contract, and (b) has informed the other Party as soon as possible about the occurrence of such an event.
14.3 Extension of Time
Any period within which a Party shall, pursuant to this Contract, complete any action or task, shall be extended for a period equal to the time during which such Party was unable to perform such action as a result of Force Majeure. However, such period shall not exceed sixty (60) days.
14.4 Payments
During the period of their inability to perform the Services as a result of an event of Force Majeure, the Bidder shall be entitled to continue to be paid under the terms of this Contract, as well as to be reimbursed for additional costs reasonably and necessarily incurred by them during such period for the purposes of the Services and in reactivating the Service after the end of such period.
15. Termination
15.1 By the Procuring Agency
The Procuring Agency may terminate this Contract in case of the occurrence of any of the events specified in paragraphs (a) through (e) of this Clause. In such an occurrence the Procuring Agency shall give at least thirty (30) calendar days’ written notice of termination to the Bidder in case of the events referred to in (a) through (d); at least sixty (60) calendar days’ written notice in case of the event referred to in (e);
15.2 By the Bidder
The Bidder may terminate this Contract, by not less than thirty (30) calendar days’ written notice to the Procuring Agency, in case of the occurrence of any of the events specified in paragraphs (a) through (d) of this Clause.
16. General
16.1 Standard of Performance
16.2 Law Applicable to Goods
The Bidder shall deliver the goods in accordance with the Contract and in accordance with the Law of Pakistan and shall take all practicable steps to ensure that any of its Experts and Sub-Bidders, comply with the Applicable Law.
17. Conflict of Interests
17.1 Bidder Not to Benefit from Commissions and Discounts.
The remuneration of the Bidder shall constitute the Bidder’s sole remuneration in connection with this Contract or the Services, and the Bidder shall not accept for their own benefit any trade commission, discount, or similar payment in connection with activities pursuant to this Contract or to the Services or in the discharge of their obligations under the Contract, and the Bidder shall use their best efforts to ensure that the Personnel, any Subcontractors, and agents of either of them similarly shall not receive any such additional remuneration.
17.2 Bidder and Affiliates Not to be Otherwise Interested in Project
The Bidder agree that, during the term of this Contract and after its termination, the Bidder and its affiliates, as well as any Subcontractor and any of its affiliates, shall be disqualified from providing Goods for any project resulting from or closely related to the Services.
17.3 Prohibition of Conflicting Activities
Neither the Bidder nor its Subcontractors nor the Personnel shall engage, either directly or indirectly, in any of the following activities:
18. Confidentiality
18.1 Except with the prior written consent of the Procuring Agency, the Bidder and the Experts shall not at any time communicate to any person or entity any confidential information acquired in the course of the contract.
19. Insurance to be Taken Out by the Bidder
19.1 The Bidder(a) shall take out and maintain, and shall cause any Subcontractors to take out and maintain, at its (or the Subcontractors’, as the case may be) own cost but on terms and conditions approved by the Procuring Agency, insurance against the risks, loss or damage, and for the coverage, as shall be specified in the SCC; and (b) at the Procuring Agency’s request, shall provide evidence to the Procuring Agency showing that such insurance has been taken out and maintained and that the current premiums have been paid.
20. Bidder’s Actions Requiring Procuring Agency’s Prior Approval
20.1 The Bidder shall obtain the Procuring Agency’s prior approval in writing before taking any of the following actions:
(a) appointing such members of the Personnel not provided by the Bidder;
(b) changing the Program of activities; and
(c) any other action that may be specified in the SCC.
21. Reporting Obligations
21.1 The Bidder shall submit to the Procuring Agency the reports and documents in the numbers, and within the periods as prescribed by the Procuring Agency.
22. Liquidated Damages
22.1 If the Supplier fails to deliver any or all of the Goods or to perform the Services within the period(s) specified in the Contract, the Procuring Agency shall, without prejudice to its other remedies under the Contract, deduct from the Contract Price, as liquidated damages, a sum equivalent to the percentage specified in SCC of the delivered price of the delayed Goods or unperformed Services for each week or part thereof of delay until actual delivery or performance, up to a maximum deduction of the performance security (or guarantee) specified in SCC. Once the said maximum is reached, the Procuring Agency may consider termination of the Contract pursuant to GCC Clause 16.
22.2 Correction for Over-payment
If the Intended Completion Date is extended after liquidated damages have been paid, the Procuring Agency shall correct any overpayment of liquidated damages by the Bidder by adjusting the next payment certificate. The Bidder shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in SCC.
22.3 Lack of performance penalty
If the Bidder has not corrected a Defect within the time specified in the Procuring Agency’s notice, a penalty for Lack of performance will be paid by the Bidder. The amount to be paid will be calculated as a percentage of the cost of having the Defect corrected, assessed as specified in the SCC.
23. Performance Guarantee
23.1 The Performance Security (or Guarantee) shall be provided to the Procuring Agency no later than the date specified in the Letter of Acceptance and shall be issued in an amount and form acceptable to the Procuring Agency as specified in SCC, and denominated in the types and proportions of the currencies in which the Contract Price is payable as specified in the SCC.
23.2 Within Seven (07) days from the issuance of acceptance letter from the Procuring Agency, the successful Bidder shall furnish the Performance Guarantee in shape of ------- at the discretion of the PA in the amount specified in SCC. In case the amount of Bids security is equal or greater than
23.3 The proceeds of the Performance Guarantee shall be payable to the Procuring agency as compensation for any loss resulting from the Supplier’s failure to complete its obligations under the Contract.
23.4 The Performance Guarantee shall be denominated in the currency of the Contract, or in a freely convertible currency acceptable to the Procuring agency and shall be in the acceptable form as specified in SCC.
23.5 The Performance Guarantee will be discharged by the Procuring agency and returned to the Supplier not later than thirty (30) days following the date of completion of the Supplier’s performance obligations under the Contract, including any warranty obligations, unless otherwise specified in SCC.
23.6 The bid security of the successful bidder shall not be substituted with the Performance Guarantee.
24. Fraud and Corruption
24.1 The Procuring Agency requires the Supplier to disclose any commissions or fees that may have been paid or are to be paid to agents or any other party with respect to the Bidding process or execution of the Contract. The information disclosed must include at least the name and address of the agent or other party, the amount and currency, and the purpose of the commission, gratuity or fee.
25. Sustainable Procurement
25.1 The Bidder shall conform to the sustainable procurement contractual provisions, if and as specified in the SCC.
26. Description of Personnel
26.1 The titles, agreed job descriptions, minimum qualifications, and estimated periods of engagement in the carrying out of the Services of the Bidder’s Key Personnel. The Key Personnel listed by title as well as by name are hereby approved by the Procuring Agency.
27. Removal and/or Replacement of Personnel
27.1 Except as the Procuring Agency may otherwise agree, no changes shall be made in the Key Personnel. If, for any reason beyond the reasonable control of the Bidder, it becomes necessary to replace any of the Key Personnel, the Bidder shall provide as a replacement a person of equivalent or better qualifications.
27.2 If the Procuring Agency finds that any of the Personnel have (i) committed serious misconduct or have been charged with having committed a criminal action, or (ii) have reasonable cause to be dissatisfied with the performance of any of the Personnel, then the Bidder shall, at the Procuring Agency’s written request specifying the grounds thereof, provide as a replacement a person with qualifications and experience acceptable to the Procuring Agency.
27.3 The Bidder shall have no claim for additional costs arising out of or incidental to any removal and/or replacement of Personnel.
28. Assistance and Exemptions
28.1 The Procuring Agency shall use its best efforts to ensure that the Government shall provide the Bidder such assistance and exemptions as specified in the SCC.
29. Change in the Applicable Law
29.1 If, after the date of this Contract, there is any change in the Applicable Law with respect to taxes and duties which increases or decreases the cost of the related Services rendered by the Bidder, then the remuneration and reimbursable expenses otherwise payable to the Bidder under this Contract shall be increased or decreased accordingly by agreement between the Parties, and corresponding adjustments shall be made to the amounts referred in the SCC.
30. Services and Facilities
30.1 The Procuring Agency shall make available to the Bidder and the Experts, for the purposes of the Services and free of any charge, the services, facilities and property described , at the times and in the manner specified in the SCC or terms of reference.
30.2 In case that such services, facilities and property shall not be made available to the Bidder, the Parties shall agree on (i) any time extension that it may be appropriate to grant to the Bidder for the performance of the Services, (ii) the manner in which the Bidder shall procure any such services, facilities and property from other sources, and (iii) the additional payments, if any, to be made to the Bidder as a result thereof.
31. Contract Price
31.1 The price payable shall be in Pakistani Rupees unless otherwise specified in the SCC. Prices charged by the Supplier for Goods delivered under the Contract shall not vary from the prices quoted by the Supplier in its Bid.
32. Terms and Conditions of Payment
32.1 Payments will be made to the Bidder according to the payment schedule stated in the SCC and as per actual invoice submitted by the Bidder.
32.2 Unless otherwise stated in the SCC, the advance payment shall be made against the provision by the Bidder of a bank guarantee for the same amount, and shall be valid for the period stated in the SCC. Any other payment shall be made after the conditions listed in the SCC for such payment have been met, and the Bidder have submitted an invoice to the Procuring Agency specifying the amount due.
33. Currency of Payment
33.1 Any payment under this Contract shall be made in the currency(ies) specified in the SCC.
34. Identifying Defects
34.1 The principle and modalities of Inspection of the Goods by the Procuring Agency shall be as indicated in the SCC. The Procuring Agency shall check the Bidder’s performance and notify him of any Defects that are found. Such checking shall not affect the Bidder’s responsibilities. The Procuring Agency may instruct the Bidder to search for a Defect and to uncover and test any service that the Procuring Agency considers may have a Defect. Defect Liability Period is as defined in the SCC.
35. Correction of Defects, and
Lack of Performance Penalty
35.1 The Procuring Agency shall give notice to the Bidder of any Defects before the end of the Contract. The Defects liability period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice a Defect is given, the Bidder shall correct the notified Defect within the length of time specified by the Procuring Agency’s notice.
35.3 If the Bidder has not corrected a Defect within the time specified in the Procuring Agency’s notice, the Procuring Agency will assess the cost of having the Defect corrected, the Bidder will pay this amount, and a Penalty for Lack of Performance.
36. Taxes and Duties
36.1 A Supplier shall be entirely responsible for all taxes, duties, fees, etc., incurred until delivery of the contracted Goods to the Procuring Agency.
37. Alternate Dispute Resolution
37.1 Upon the commencement of the Procurement Contract, any disputes arising between the contracting parties shall be resolved in accordance with Rule 66 of the Public Procurement Rules, 2026.
37.2 The procuring agency may refer the matter to the Chief Justice Islamabad High Court or Managing Director PPRA or the Secretary Ministry of Law & Justice for appointment of Arbitrator.
37.3 The fee for the Arbitrator shall be specified in Pak Rupees as determined by the appointing authority which shall be borne and shared equally by the contracting parties.
38. Change Orders
The Procuring Agency may at any time, by a written order given to the Supplier, make changes within the general scope of the Contract in any one or more of the following:
a)Drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Agency;
b)The method of shipment or packing;
c)The place of delivery; and/or
d)The Services to be provided by the Supplier.
39. Contract Amendenments
39.1 Subject to GCC Clause 32, no variation in or modification of the terms of the Contract shall be made except by written amendment signed by the parties.
40. Sub-Contracts
40.1 The Supplier shall consult the Procuring Agency in the event of subcontracting under this contract if not already specified in the Bid. Subcontracting shall not alter the Supplier’s obligations.
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: Institute of Space Technology (Institute of Space Technology), Procurement Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
The Supplier is:
The title of the subject procurement is: Purchase of Lab Equipment for NCFA Department
Number of GC Clause 3
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 4
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 5
Notices:
The addresses for the notices are:
The Authority:
Institute of Space Technology (Institute of Space Technology), Procurement
Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
+92-301-509-8817
mgr.proc@ist.edu.pk
Contractor/ Bidder:
[Name, address and telephone number].
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 7.1
The Authorized Representatives are:
For the Procuring Agency:
Institute of Space Technology (Institute of Space Technology), Procurement
Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
+92-301-509-8817
mgr.proc@ist.edu.pk
For the Bidder:
Name: ………………………
Designation: ……………..
Address: ……………………………..
Number of GC Clause 8
Effectiveness of the contract
Number of GC Clause 9
Commencement of Contract:
Number of GC Clause 11.2
Expiration of Contract:
Number of GC Clause 15
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 17
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 22
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 0.06% to 10.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 23
Performance Guarantee:
Instrument of Performance Guarantee shall be in the Name of : Institute of Space Technology
The amount of performance guarantee shall be 10.00% of the contract price in acceptable form of Pay Order, Call at Deposit, Demand Draft
Number of GC Clause 32
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 33
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 34
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
For being Brand New, bearing relevant reference numbers of the equipment (Certificate from supplier)
For Physical Fitness having No Damages (Certificate from supplier)
For the Country of Origin as quoted by the Supplier (Certificate from manufacturer)
For conformance to specifications and performance parameters, through Prior to delivery inspection (Inspection Report by Procurement Committee / Inspection Team)
For successful operation at site after complete installation, testing and commissioning of the equipment (Installation, Testing and Commissioning Report by Procurement Committee / Inspection Team)
Copies of the Supplier’s invoice showing Goods’ description, quantity, unit price, and total amount;
Original and two copies of the usual transport document (for example, a negotiable bill of lading, a non-negotiable sea waybill, an inland waterway document, an air waybill, a railway consignment note, a road consignment note, or a multimodal transport document) which the buyer may require to take the goods;
Copies of the packing list identifying contents of each package;
Insurance Certificate;
Manufacturer’s or Supplier’s Valid Warranty Certificate;
Inspection Certificate issued by the Nominated Inspection Agency (if any), and the Supplier’s Factory Inspection Report;
Certificate of Origin.
The above documents would be required even if the equipment has already been imported and is available with the supplier ex-stock
Number of GC Clause 37
Following is the guidance for Dispute Resolution
(a) For Contracts to be entered with foreign Contractor/ Service Provider:
All disputes arising in connection with the present Contract shall be finally settled under the Rules of Conciliation and Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with said Rules.
(b) For Contracts to be entered with nationals of Pakistan:
i. If any dispute of any kind whatsoever shall arise between the Authority and the Bidder in connection with or arising out of the Contract, including without prejudice to the generality of foregoing, any question regarding its existence, validity, termination and the execution of the Contract – whether during developing phase or after their completion and whether before or after the termination, abandonment or breach of the Contract – the parties shall seek to resolve any such dispute or difference by mutual diligent negotiations in good faith within 14 (fourteen) days following a notice sent by one Party to the other Party in this regard.
ii. At future of negotiation the dispute shall be resolved through mediation and mediator shall be appointed with the mutual consent of the both parties.
iii. At the event of failure of mediation to resolve the dispute relating to this contract such dispute shall finally be resolved through binding Arbitration in accordance with GCC clause 38.
iv. The cost of the mediation and arbitration shall be shared by the parties in equal proportion however the both parties shall bear their own costs and lawyer’s fees regarding their own participation in the mediation and arbitration. However, the Arbitrator may make an award of costs upon the conclusion of the arbitration making any party to the dispute liable to pay the costs of another party to the dispute.
v. Arbitration proceedings as mentioned in the above clause regarding resolution of disputes may be commenced prior to, during or after completion of the contract.
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract unless they otherwise agree that the Authority shall pay the Bidder any monies due to the Bidder.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder who is a national of the Islamic Republic of Pakistan arising in connection with the present Contract shall be referred to adjudication or arbitration in accordance with the laws of the Islamic Republic of Pakistan including Arbitration Act 1940, however above provision shall prevail in referring the case to the Arbitrator.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place of arbitration shall be at Islamabad. The award of the arbitrator shall be final and shall be binding on the parties.
Date: [insert date (as day, month and year)]
Bid No.:P210297
Alternative No.: [insert identification No if this is a Bid for an alternative]
To: Institute of Space Technology (Institute of Space Technology), Procurement Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
Signed: [insert signature of person whose name and capacity are shown] In the capacity of
[insert legal capacity of person signing the Bid Securing Declaration]
Name: [insert complete name of person signing the Bid Securing Declaration]
Duly authorized to sign the Bid for and on behalf of: [insert complete name of Bidder]
Dated on day of , [insert date of signing]
Corporate Seal (where appropriate)
THIS AGREEMENT made the _____ day of __________ 20_____ between Institute of Space Technology (Institute of Space Technology), Procurement Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., Purchase of Lab Equipment for NCFA Department (P210297) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: Institute of Space Technology (Institute of Space Technology), Procurement Procurement Dept, Islamabad Expressway, Near CDA Toll Plaza., Islamabad Capital Territory
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}