In terms of Rule 48 of Public Procurement Rules, 2004, a Grievance Redressal Committee (GRC) is notified for the subject procurement and the notification copy is available on the procuring agency’s website and on the Authority’s website at (www.ppra.org.pk).
Cantonment Board Malir (Engineering Branch), Cantt Sub Engineer
Cantonment Board Office, Bostan Line Malir Cantt, Karachi
+92-334-606-5006
pa.cbmalir@gmail.com
Sections of Prequalifica¬tion Documents
The following specific data for the Prequalification of Applicants shall complement, supplement, or amend the provisions in the Instructions to Applicants (ITA). Whenever there is a conflict, the provisions herein shall prevail over those in ITA.
| PDS Clause No. | ITA No. | Amendments of, and Supplements to, Clauses in the Instructions to Applicants |
A. General |
||
| 1. | 1.1 |
Identification Number of the Invitation for Prequalification: P115888 |
| 2. | 2.1 | The name of Procuring Agency is: Cantonment Board Malir (Engineering Branch) The name of Project / Procurement is: Annual Repair/ Maintenance of Cantt Fund Buildings |
| 3. | 4.2 | Maximum number of members in a Joint Venture (JV): Nil |
| 4. | 4.5 | A list of debarred firms and individuals is available on PPRA website: https://ppra.gov.pk |
B. Contents of the Prequalification Document |
||
| 5. | 7.1 | For clarification, the Applicant shall seek clarifications through: EPADS v2.0 |
| 6. | 7.1 & 8.2 | Information related to Prequalification shall be published on: EPADS v2.0 |
| 7. | 7.2 | Pre-Application Meeting: Clarification Date: Wednesday, September 30, 2026 |
C. Preparation of Applications |
||
| 8. | 10.1 | This Prequalification Document has been issued in the language: English |
| 9. | 11.1(d) | Additional documents to be submitted through EPADS v2.0: No |
| 10. | 14.2 | Source for determining exchange rates: Not Applicable |
D. Submission of Applications |
||
| 11. | 16.1 | Deadline for Application Submission: Day: Wednesday Date: Wednesday, October 14, 2026 Time: 02:00 PM |
| 12. | 17.1 | Opening of Applications shall be conducted through: EPADS v2.0 Day: Wednesday Date: Wednesday, October 14, 2026 Time: 02:30 PM Virtual participation link: https://vendors.epads.gov.pk/ |
E. Procedures for Evaluation of Applications |
||
| 13. | 21.1 | Margin of Domestic Preference: Not Applicable (Applicable only if authorized in Procurement Plan) |
| 14. | 29.1 | Prequalification-related complaints / grievances shall be submitted in writing through: EPADS v2.0 A complaint may challenge:
|
| Bidder's Type | Required Registration |
|---|---|
|
Any |
NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) SECP PEC |
Quality Based Selection (QBS)
Weightage (With Financial Criteria)
| Technical Evaluation % | Financial Evaluation % |
|---|---|
| 70 | 30 |
| Technical Marks | 70 | |
|---|---|---|
| Passing Marks | 35 | |
| General Experience | ||
| Projects of similar nature and complexity Completed in last five years. No Marks are awarded for works less than specified limits. 12 Marks are given if thecontractor has completed at least 3 projects of similar nature in last five years. • For less than 3 projects completed use the following weightage. 12 x (A/3) • For more than 3 projects but less than 6 projects completed use the following weightage. 12+ (A/6) x 3 A = No of projects of similar nature Completed in last five years • Full Marks are given in case of 6 projects or more. (Quantitative)(Doc Required) | 15 | |
| Projects of similar nature and complexity in-hand during last three years. No Marks are awarded for works less than specified limits. 8 Marks are given if the contractor has 3 projects of similar nature inhand. • For less than 3 projects in hand use the following weightage. 8 x (A/3) • For more than 3 projects but less than 6 projects in-hand use the following weightage. 8+ (A/6) x 2 A = No of projects of similar nature Inhand during last three years • Full Marks are given in case of 6 projects or more. (Quantitative)(Doc Required) | 10 | |
| Electrical works carried out during last five years by the SubContractor/JV Partner. 4 Marks are given if the contractor has completed at least 3 projects of similar nature in last five years. • For less than 3 projects completed use the following weight age. 4 x (A/3) For more than 3 projects but less than 6 projects completed use the following weightage. 4+(A/6) x1 A = No of projects of similar nature Completed in last five years • Full Marks are given in case of 6 projects or more. (Quantitative)(Doc Required) | 5 | |
| PERSONNEL CAPABILITIES: B.Sc Engineers registered with Pakistan Engineering Council (PEC) Explanation for Marks Obtained Experience (3-Marks) : 3 Marks will be given if the individual experience of at least 4 no. of B.Sc Engineers (professional) is equal to 7 years or above. • For less than 4 no of B.Sc Engineers having individual experience of 7 years, marks will be given as per following formulas: = (A/4) * 3 A = No. of Engineers having individual experience of 7 years or above. Strength of Engineers (6 Marks) • 6 Marks will be given if the total no. of Engineers registered with PEC are 7 nos. or above. For less than 7 no of B.Sc Engineers registered with PEC marks will be given as per following formulas: = (A/7) * 6 A = No. of Engineers (Quantitative)(Doc Required) | 9 | |
| Associates Engineers (DAE) Explanation for Marks Obtained Experience (2-Marks) : • 2 Marks will be given if the individual experience of at least 4 no. of Associates Engineers (DAE) is equal to 5 years or above. • For less than 4 no of Associates Engineers (DAE) having individual experience of 5 years, marks will be given as per following formulas: = (A/4) * 2 A = No. of DAE Engineers. Strength of Associate Engineers (4 Marks) • 4 Marks will be given if the total no. of Associate Engineers (DAE) are 10 nos. or above. • For less than 10 no of Associate Engineers marks will be given as per following formulas: = (A/10) * 4 A = No. of Associate Engineers (Quantitative)(Doc Required) | 6 | |
| EQUIPMENT CAPABILITY: 05 marks shall be given for each single item. If the available quantity of each equipment is more than one full marks will be given. • Total Marks = (Marks Obtained/110) * 20 i. Batching Plant (30cuM/hr Cap.) ii. Concrete mixture machine one bag. Concrete Pump Crane Mobile (30 Ton Cap.) Scaffolding Pipe / Form Work Dumper Trucks Shovel/ Loader/ Backhoe Steel cutting & Bending Machine Concrete Transit Mixer (6 CuM / hr) Tractor Trolley / Bowzer Generator / Air Compressor Dozer / Grader / Roller (Quantitative)(Doc Required) | 20 | |
| Litigation History in which Decision has been given against the firm(s) In case the firm is involved in any litigation, no marks will be given and 5 points will be added in case affidavit of no litigation is attached. (Quantitative)(Doc Required) | 5 | |
| Financial Marks | 30 | |
| Financial Evaluation Criteria | ||
| Available Bank Credit Line 3 Marks are given if the available bank credit line limit is equal to 100 Million. • For limit less than 100 Million, use following weightage 3 x (A/100) • For the limit more than 10O million but less than 200 million use following weightage 3 + (A/200) x 2 A= Available Bank Credit Line Limit • Full Marks are given in case of limit is 200 million or more. (Quantitative)(Doc Required) | 5 | |
| Working Capital in last 3 years 3 Marks are given if the available average working capital for last three years is equal to 150 Million. • For the capital less than 150 million use following weightage 3 x (A/150) • For the capital more than 150 million but less than 200 million use following weightage 3+ (200/A) x 2 A= Average working capital in last three years. • Full Marks are given in case of limit is 2o00 million or more. (Quantitative) | 5 | |
| Registration with income tax department No points will be given if income tax certificate is not attached and 5 points will be added in case of valid certificate. (Quantitative) | 10 | |
| Copy of Valid electrical license from Sub-Contractor/ JV Partner No points will be given if license is not attached and 5 points will be added in case of valid license. (Quantitative) | 5 | |
| Blacklisting from any agency In case the firm is blacklisted, no Marks will be given and 5 points will be added in case affidavit by the company that it has not been black listed is attached. (Quantitative) | 5 | |