The following specific data for the procurement of works shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITBs). Whenever there is a conflict, the provisions herein shall prevail over those in ITBs.
ITB Number 1.1
Name of Procuring agency/Employer: NDMA (National Disaster Management Authority (NDMA))
The subject of procurement is: Ext of NGT - Construction of Cafeteria and Mosque
Period for completion of the works 60 Days
Commencement date execution of the works: 5 Days
Type of Procurement: Local
ITB Number 2.1
Financial year for the operations of the Procuring agency/Employer: 2026-27Name of Project [insert: name and summary description of the Project if any]
Name of financing institution: [insert: name if any]
Name and identification number of the Contract: P118789
ITB Number 3.1
JV/Consortium or Association Allowed: No
Maximum number of members in the joint venture shall be: Nil.
ITB Number 6.4
The Bidders may seek clarifications through EPADS v2.0: Last Clarification Date: Thursday, September 24, 2026
ITB Number 8.1
The Language of all correspondences and documents related to the Bid is: English
ITB Number 5.1 & 9.1
The following documents must be included to constitute the Bid
No
ITB Number 9.4 (b)
Other procurement specific documentation requirements are:
Annual Average Turnover Certificate Last 3 years (Rs. 1000 million & above)
Audited Financial Statement of last 3 years showing Annual Average Turnover of Rs. 1000 million & above.
Income Tax Returns for the last 3 years
PEC Registration Certificate of Category C-2 or Above
Minimum 8 years of experience in civil construction works (work award and completion certificates be attach)
An Affidavit on Rs. 100/- stamp paper duly attested by Notary Public, that the firm is not blacklisted by the government/ semi government department as per specimen attached.
An Affidavit on Rs. 100/- stamp paper duly attested by Notary Public, that the firm is not involved in any active legal disputes, corruption cases or blacklisting proceedings with government entities.
ITB Number 12.4
The Bid price will be/will not be subject to the price adjustment Nil.
ITB Number 12.6
The Bid price shall be adjusted in accordance with Schedule-A to Bid – “Schedule of Adjustment Data” if available.
ITB Number 13.1
Bidders to quote entirely in Pak rupees (PKR)
ITB Number 15.1
The Bid Validity period shall be 90 Days days.
ITB Number 16.1
The amount of Bid Security shall be (insert amount)
The currency of the Bid Security shall be: PKR.
ITB Number 16.2
The Bid Security shall be in the form of: Pay Order, Call at Deposit, Bank Guarantee
ITB Number 19.1
The deadline for Bid submission is: Friday, October 2, 2026 11:00 AM
Address for submission of Original Bid Security: Near ITP Office, Main Murree Road, Islamabad Capital Territory
ITB Number 21.1
The Bid opening shall take place at: EPADS v2.0
Day : Friday
Date: October 02, 2026
Time : 11:30 AM
ITB Number 27.1
The currency that shall be used for Bid evaluation and comparison purposes to convert all Bid prices expressed in various currencies is: PKR Only
The source of exchange rate shall be: Nil
The date of exchange rate shall be: Nil
ITB Number 28.2 & 28.5
Least Cost Based Selection (LCBS)
see Evaluation Criteria
ITB Number 29.1
Domestic preference to apply.
Domestic preference: No
Preference to domestic or national suppliers or contractors shall be provided in accordance with policies of the Federal Government and/or in accordance with the regulations issued by the Authority.
If Yes, The percentage for the domestic preference alongwith calculation formula is provided in the evaluation and qualification criteria.
ITB Number 32.2
Sub-contracting is allowed? : No
No % of the total value of the contract.
39.1 The Performance Security (or guarantee) shall be 0%
39.2 The Performance Security (or guarantee) shall be in the form of: Nil
| Bidder's Type | Required Registration |
|---|---|
| Sole Proprietorship Partnership Firm Company (Private Limited) Company (Public Limited) Company (Holding Company) Company (Limited by Guarantee) State Owned Enterprise (Private Limited) State Owned Enterprise (Public Limited) | NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) |
| Eligibility Criteria | Document |
|---|---|
| Annual Average Turnover Certificate Last 3 years (Rs. 1000 million & above) | Yes |
| Audited Financial Statement of last 3 years showing Annual Average Turnover of Rs. 1000 million & above. | Yes |
| Income Tax Returns for the last 3 years | Yes |
| PEC Registration Certificate of Category C-2 or Above | Yes |
| Minimum 8 years of experience in civil construction works | Yes |
| An Affidavit on Rs. 100/- stamp paper duly attested by Notary Public, that the firm is not blacklisted by the government/ semi government department as per specimen attached. | Yes |
| An Affidavit on Rs. 100/- stamp paper duly attested by Notary Public, that the firm is not involved in any active legal disputes, corruption cases or blacklisting proceedings with government entities. | Yes |
Least Cost Based Selection (LCBS)
Weightage
| Technical Evaluation % |
|---|
| 100 |
| Technical Marks | 70 | |
|---|---|---|
| Passing Marks | 49 | |
| Technical Evaluation Criteria | ||
| Firm Experience of civil work (Quantitative)(Doc Required) More than 25 Years (10) 21 to 25 Years (6) 15 to 20 Years (4) | 10 | |
| Similar Nature project Experience having accumulative worth of Rs. 1000 million or above in last 5 years (Quantitative)(Doc Required) Three or more similar projects Completed (10) Two Project (6) One Project (3) | 10 | |
| Key Personnel (Quantitative)(Doc Required) Key Personnel (10) Project Manager (4) Structural Engineer (3) Electrical Engineer (2) Mechanical Engineer (1) | 10 | |
| Construction Equipment (Quantitative)(Doc Required) Construction Equipment (All Type of Construction Equipment) (10) Batching Plant (4) Cranes (3) Excavator (2) Survey Equipment (1) | 10 | |
| Financial Capabilities (Quantitative)(Doc Required) Average Annual Turnover >= Rs. 1000 Million (10) Average Annual Turnover >= Rs800 Million (7) Average Annual Turnover >= Rs 600 Million (3) | 10 | |
| Work Plan & Methodology (Quantitative)(Doc Required) Work Plan & Methodology (10) Project Schedule (CPM / PERT) (6) Construction Methodology (4) | 10 | |
| Steel Structure Fabrication Facility (Quantitative)(Doc Required) Steel Structure Fabrication Facility (10) | 10 | |
Jobs Without Lots :
| Job | Delivery Schedule | Quantity | Bid Security |
|---|---|---|---|
| Ext of NGT - Construction of Cafeteria and Mosque | Address: Near ITP Office, Main Murree Road, Islamabad Capital TerritorySchedule: 49 DaysQuantity: 1/Qty |
1/Qty | 9600000 PKR |
Jobs Without Lots :
Job: Ext of NGT - Construction of Cafeteria and Mosque
Specifications / Requirements:
| Sr. No | Sr.No | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|---|
| 1 | 1 | Steel Structure | %No | |||
| 2 | 2 | Design, manufacturing, supply, and installation of Pre-Engineered Steel Shed including primary structural steel rafters, columns, connection plates, base plates, roof purlins, pre-painted roof sheets, trims, gutters, downtake pipes, cross wire bracing, anchor bolts, and all necessary hardware fixing screws. Item also includes 50mm thick EPS panels fixed to MS structural girts for First Floor external walls, joint sealing, and weather-proof exterior finish complete in all respects as per design | %Sft | 7869.48729 | ||
| 3 | 3 | Supply & Installation Mazzanine floor steel structure | %Sft | 5406.9330119 | ||
| 4 | 4 | Supply & Installation of Roof area only Glass Wool Insulation 100mm Thick with Mesh Density (10 – 12) Kg/m3. | %Sft | 6041.1958194 | ||
| 5 | 5 | Providing and fixing roof liner sheet made of precoated galvanized steel / aluminium-zinc alloy coated steel sheet, 0.5 mm thick , of approved make, colour, and shade, fixed to the underside of purlins using self-drilling/self-tapping screws with EPDM washers, complete with all accessories such as ridge fillers, trims, and sealants, as per the manufacturer’s specifications and drawings | %Sft | 6041.1958194 | ||
| 6 | 6 | Supply and Installation of Steel structure stair including railing with 12mm thk glass complete in all respects | %Job | 2 | ||
| 7 | 7 | Supply, fabrication and installation of MS/GI structural framework for façade shade comprising MS square/rectangular pipes and/or GI C-Channels of approved size and thickness, including all necessary brackets, cleats, gusset plates, anchor bolts, chemical anchors, nuts, washers and welding accessories. The structure shall be adequately braced and securely connected to the existing RCC columns and anchored with the brick masonry wall using suitable fastening arrangements. The scope includes cutting, fabrication, erection, alignment, welding, grinding, anti-rust primer and paint finish, complete in all respects as per approved drawings and site requirements. | %Ton | 1 | ||
| 8 | 8 | Civil/Archituctural Works | %No | |||
| 9 | 9 | Dismantling of Concrete and Site Clearance including the removal of surplus debris, unused material and by products as directed by the Engineer complete. | %Job | 1 | ||
| 10 | 10 | Excavation for foundation of columns, walls, etc. upto any depth and lead including back filling of excavated earth in foundation trenches and spreading the surplus earth in plinth area and/or depressions where required including making provision for shoring of loose soil if required and removal of excavated earth upto 5'-0" from edge of excavation complete as per drawing and as directed by the Consultants. | %Cft | 25549.7 | ||
| 11 | 11 | Providing Earth filling with off site material (brought from out side source)including compaction upto 95% in plinth, depression and where ever required laid in 12" layer well watered, consolidated and compacted with mechanical means complete as per drawing and as directed by the Consultants. | %Cft | 29194.672769568 | ||
| 12 | 12 | Providing C.C. 1:4:8 bed concrete using graded screened bajri 3/8" and down gauge as fine aggregate and stone ballast 1" to 2" size as coarse aggregate in foundation over well compacted earth including levelling and curing etc. complete as per drawing and as directed by the Consultants | %Cft | 4038.1268134623 | ||
| 13 | 13 | Providing Reinforced cement concrete 1:2:4 (mix design) using graded screened bajri 3/8" and down gauge as fine aggregate and crushed stone 3/4" and down gauge as coarse aggregate with machine mixing including the cost of form work and its removal, vibrating using mechanical vibrator, curing and cube testing etc. having min. works cube crushing strength of 3,000 psi after 28 days curing but excluding the cost of reinforcement bars complete as per drawing and as directed by the Consultants. | %Cft | 8802.3009139987 | ||
| 14 | 14 | Providing brick masonry using 9" x 4 1/2" x3" best approved quality burnt bricks the bricks used should be well-burnt without being vitrified and shall be uniform in colour, regular in shape and size with sharp and square corners and parallel faces, free from flaws and crackes, to be laid in mortar 1:4 with curing, scaffolding, racking out the joints, courses shall be kept in time plumb as per drawing, standard specificaiton and as directed by the Consultants Up To 12ft Height. | %Cft | 8827.324 | ||
| 15 | 15 | Providing fabrication and instllation in position 12mm of gypsum board sheet (gypsum board approved company) including cuttong of opening for lights ifixture/ diffusers with making of light pelmet fiber tape on joints icluding 3 coats of mat enamel paint fininsh pemerr coat filing if required with all other hardwares, wastage scaffolding, making access panel (where required)etc as per design & drawing complete. | %Sft | 12592.94171443 | ||
| 16 | 16 | Providing placing and installation of WPVC cladding on walls including preparation of all required arrangments and access work to be complete as per quality & interior finishes aspects in accordance with the specification complete in all respect. | %Sft | 1690 | ||
| 17 | 17 | Providing and fixing powder coated or anodized aluminum, glazed door of aluminum sections, tinted glass, rubber gaskets, double action floor mounted concealed type pivot hinge mechanism, hydraulic door closer, handles & locking arrangement, screws/expansion bolts and other aluminum accessories etc. complete in all respects as approved by the Engineer. | %Sft | 506 | ||
| 18 | 18 | Providing and fixing powder coated or anodized aluminum, glazed-window of aluminum sections, tinted glass, rubber gaskets latch lock arrangement, screws/expansion bolts and other aluminum accessories etc. complete in all respects as approved by the Engineer. | %Sft | 1960.2 | ||
| 19 | 19 | Providing and laying 1/2" thick cement sand plaster (1:4) to Internal Ceiling, Walls, Stairs, Columns, & etc making edges and corners, preparation of surface plaster with mesh, including finishing, scaffolding, curing and etc. Complete in all as per drawing & instruction of the Consultant. | %Sft | 19972.7 | ||
| 20 | 20 | Providing and applying 2 coats of Plastic Emulsion paint (Mat finish) of approved quality, color and shade (approved company) over 2 coats of Primer of approved manafacturer and quality on Ceiling, Columns, Walls, & etc including surface preparation, Wall putty filling, cutting, surfacing, scaffolding, scraping, sanding, & etc. Complete in all as per drawing & instruction of the Consultant. | %Sft | 23529.75459756 | ||
| 21 | 21 | Providing Reinforced steel bars using minimum Yield Strength of 60 KSI confirming to ASTM A-615, as per design including cutting, bending, binding and placing in position on c.c precast spacers and steel chairs, tying with binding wire 20 SWG complete with the cost of chairs, binding wire etc. complete as per drawing and as directed by the Consultants.(Rate should include the cost of westage of steel, also note that All Reinforcing steel shall be adequately protected from rust and corrosion before and during concreting) | %Ton | 33 | ||
| 22 | 22 | Providing and installation of locally produced Porcelain tiles on floor, Wall & skirting with cement motar 1:4 and complete with screening, grouting, filling, finishing and etc. complete in all respects, as per drawing & instruction of the consultant or Engineer. | %Sft | 15988.61971443 | ||
| 23 | 23 | Providing and fixing of Pre Polished Granite Sills / Thresholds under windows and doors respectively , of approved origin, color/shade / thickness fix with cement sand mortar | %Sft | 450 | ||
| 24 | 24 | Provide and install Aluminum Composite Panel overall 4mm thick with 0.5mm skin thickness with mineral-filled core of approved sample & metallic/solid colour of approved shades including making grooves, champhered edges, joint details, sealant, backing rod, fixing & framing system, protection of panels, etc. all as per manufacturer's specifications and instructions, fixing arrangement, etc. complete in all respect as per drawings & specifications. | %Sft | 16279.4828 | ||
| 25 | 25 | Supply & Installation of 19mm Thick Tempered Toughened Glass for open-to-sky area, including glass panels, approved supporting structure/frame, SS/aluminium fittings, clamps, brackets, fixing accessories, sealants, edge finishing, cutting, drilling, lifting and installation, complete in all respects. | %Sft | 1086 | ||
| 26 | 26 | Supply & Installation of 3'-0" High Glass Railing System, comprising approved thickness toughened/tempered glass panels, SS/aluminium posts, handrail, base channels, brackets, clamps, fittings, anchors, sealants and all necessary accessories, including fixing, alignment and finishing, complete in all respects | %Sft | 360 | ||
| 27 | 27 | Matel Framing With Gypsum Board Cladding on both side and Rock Wool Insulation | %Sft | 1419 | ||
| 28 | 28 | Providing and fixing cleared toughened glass partition,10mm thick, fixed with LGS Stud framing including harware complete in all aspectsa | %Sft | 1419 | ||
| 29 | 29 | Providing and making at site Plinth Protection around the building area 3'-0'' wide comprising of brick masonry, back filling, compaction, pcc 1:2:4 complete in all respects. | %CFT | 3717 | ||
| 30 | 30 | Providing and Fixing of Cementious Tile/chemical tile of Different sizes at plinth protection Comprising cement Sand Mortor complete in all respects. | %Sft | 1416 | ||
| 31 | 31 | Plumbing Works (1 nos of washroom with all accessories.Pipe for inlet/outlet and connection with service water tank included; internal suigas connectivity for any kitchen; conclealed service water tank included; suigas submeter, | %No | 8 | ||
| 32 | 32 | Installation of Blind Curtain Providing placing and installation of Blind curtain including preparation of all required arrangments and access work to be complete as per quality & interior finishes aspects in accordance with the specification complete in all respect | %Sft | 1300 | ||
| 33 | 33 | Supply and installation of premium-grade uPVC toilet/washroom door, comprising a rigid uPVC frame. Door to include solid uPVC panels for high durability in wet areas Complete in all aspects | %Sft | 160 | ||
| 34 | 34 | Providing and laying 6" Gravel Fill Material of approved quality and size in foundation including Compaction, complete in all respects. | %CFT | 3934.743645 | ||
| 35 | 35 | Supply of Aluminium Fixed Curtain Wall, Premium Quality, of Anodized Aluminium extruded section size, colour and texture as specified, including fixing on concrete, wood or steel frames, complete with all necessary fittings incl 6mm double glazed glass all as specified. | %Sft | 923.4 | ||
| 36 | 36 | Providing and installation of 8" dia bore l 120 ft deep along with 1.5hp submersible pump | %Job | 1 | ||
| 37 | 37 | Providing, installation, testing, commissioning of Water pressure booster pumps for water supply (One operation and one standby). Pumps shall be complete with electric drive motor, operate at 230 volts, single phase 50 hertz including electric power supply wiring conduiting, earthing etc. complete in all respects as per specification | %Job | 1 | ||
| 38 | 38 | Supply, Installation, Testing & Commissioning of Complete Plumbing Piping System for kitchen and washroom areas, including internal and external PPRC, UPVC and Other pipes of approved sizes and specifications for cold & hot water supply, soil, waste, Vent and drainage lines, complete with all necessary fittings, elbows, tees, reducers, unions, valves, traps, clamps, supports, sleeves, connections, jointing materials and accessories, including chasing, fixing, testing and making good, complete in all respects as per approved drawings and Engineer’s instructions. | %Job | 1 | ||
| 39 | 39 | Providing and Installation of Rain Water pipe Dia 6'' with calmps and all other nessary hardware | %RFT | 500 | ||
| 40 | 40 | “Supply, installation, testing and commissioning of electric geyser,(25L) complete with all accessories, inlet/outlet connections, safety valve, thermostat, pressure release system, and necessary fittings, including all civil and electrical works to make the unit fully operational. | %NO | 3 | ||
| 41 | 41 | Supply and installation of Hand dryer complete in all aspect | %No | 8 | ||
| 42 | 42 | Road Works | %No | |||
| 43 | 43 | Earthwork in Excavation / Filling to Sub-Grade Level, Dressing to Design Line(Road) | %Cft | 12600 | ||
| 44 | 44 | Preparation, Dressing, Levelling and Compaction of Existing Soil/Subgrade to the required line | %Sft | 12600 | ||
| 45 | 45 | Sub-Base Course (Granular Material), 12" Compacted Thickness | %Cft | 12600 | ||
| 46 | 46 | Base Course (Crushed Stone / WBM Grade), 6" Compacted Thickness | %Cft | 6300 | ||
| 47 | 47 | Prime Coat (MC-30 Cutback Bitumen) @ 0.10 Ltr/Sft | %Sft | 12600 | ||
| 48 | 48 | Asphalt Wearing Course (HMA), 2" Compacted Thickness | %Sft | 12600 | ||
| 49 | 49 | Road Shoulders (Compacted Gravel Material), 2ft Width, Both Sides | %CFT | 1400 | ||
| 50 | 50 | Precast PCC Kerb-stone, size 300 x 300 x 150 mm including setting, jointing and pointing in CM 1:4 all as specified. | %RFT | 1400 | ||
| 51 | 51 | Kerb Stone Reflective Paint (Yellow & Black, Traffic/Tactile) | %RFT | 1400 | ||
| 52 | 52 | Road Marking - Edge Line, Thermoplastic Paint, Both Sides | %RFT | 1400 | ||
| 53 | 53 | Road Marking - Center Line, Thermoplastic Paint (Reflective) | %RFT | 700 | ||
| 54 | 54 | Road / Traffic Signage (Cautionary, Mandatory & Informatory Boards) | %No | 10 | ||
| 55 | 55 | Side Drains (RCC / Masonry, Covered), Both Sides | %RFT | 1400 | ||
| 56 | 56 | MODULAR KITCHEN | %N0 | |||
| 57 | 57 | Supply and installation of wall-mounted cabinets in approved white finish, complete with carcass, shutters, hinges, handles and all necessary hardware, for approx. | %Rm. | 5 | ||
| 58 | 58 | Supply and installation of wall-mounted cabinets in approved black finish, complete with carcass, shutters, hinges, handles and all necessary hardware, | %Rm. | 5 | ||
| 59 | 59 | Supply and installation of base cabinets with drawers in approved black finish, complete with carcass, drawer channels, handles and all necessary hardware | %Rm. | 3 | ||
| 60 | 60 | Supply and installation of upper glass-front display cabinets, complete with carcass, glass shutters, hinges, handles and all necessary hardware. | %Rm. | 3 | ||
| 61 | 61 | Supply and installation of stainless-steel open shelving, complete with supports, brackets, fixings and all necessary accessories. | %Rm. | 5 | ||
| 62 | 62 | Supply and installation of built-in side-by-side inverter refrigerator, complete with all necessary fittings, connections and accessories. | %No | 1 | ||
| 63 | 63 | Supply and installation of 4-burner built-in gas cooktop, complete with burners, controls, gas connection fittings and accessories. | %No | 1 | ||
| 64 | 64 | Supply and installation of 60L built-in electric oven, complete with controls, electrical connections, fittings and accessories. | %No | 1 | ||
| 65 | 65 | Supply and installation of 30L built-in microwave oven, complete with electrical connection, mounting and necessary accessories. | %No | 1 | ||
| 66 | 66 | Supply and installation of built-in dishwasher, 13-place setting capacity, complete with water, drainage and electrical connections and accessories. | %No | 1 | ||
| 67 | 67 | Supply and installation of chimney-style range hood/exhaust, complete with ducting, filters, controls, electrical connection and accessories. | %No | 1 | ||
| 68 | 68 | Supply and installation of single-bowl stainless-steel kitchen sink, complete with waste outlet, strainer, sealant and all necessary accessories. | %No | 1 | ||
| 69 | 69 | Supply and installation of chrome-finish touch/pull-out kitchen faucet, complete with flexible connections, fittings and accessories. | %No | 1 | ||
| 70 | 70 | Supply and installation of waste pipe connections and traps, complete with fittings, joints, supports and accessories. | %Job | 1 | ||
| 71 | 71 | Supply and installation of copper/PPR water supply lines, complete with fittings, joints, valves, supports and necessary accessories. | %Job | 1 | ||
| 72 | 72 | Day Care Room | %No | |||
| 73 | 73 | Low-height wooden beds Kids Toddler Beds | %No | 4 | ||
| 74 | 74 | Bed Side Cabinets / Tables(Small bedside storage units / drawers between beds) | %No | 3 | ||
| 75 | 75 | Mattress & Bedding Set(Custom kids mattresses with fitted sheets & pillows) | %Sets | 4 | ||
| 76 | 76 | Modern Shell Chairs(Green Molded Eames-style chairs with wooden/wire legs) | %No | 2 | ||
| 77 | 77 | Study Counter / Bench(Wall-mounted continuous study counter/desk (White finish) | %Job | 1 | ||
| 78 | 78 | Low Soft Seating Bench / Sofa(Soft modular kids bench/sofa (Blue colour)) | %No. | 1 | ||
| 79 | 79 | Low Soft Single Armchairs(Soft padded kids single lounge seats (Pink/Yellow)) | %No. | 2 | ||
| 80 | 80 | Hexagonal Modular Stools/Ottomans | %No. | 5 | ||
| 81 | 81 | Square Soft Storage Poufs(Modular square foam cubes / ottomans (Green & Yellow)) | %No. | 3 | ||
| 82 | 82 | Children’s Chairs / Stools(Small black metal frame activity chairs) | %No. | 2 | ||
| 83 | 83 | Open Storage Rack System(Multi-tier white floor-to-ceiling metal frame open shelving unit) | %Job | 1 | ||
| 84 | 84 | Woven Storage Baskets(Brown/tan woven storage boxes for top shelves) | %No | 6 | ||
| 85 | 85 | Patterned Storage Bins(Decorative storage boxes/bins with printed numbers) | %No | 4 | ||
| 86 | 86 | Illusion / Feature Wall Wallpaper(Full height cartoon character/cat pattern wall wallpaper) | %Job | 1 | ||
| 87 | 87 | Framed Wall Art (Small), White framed character / animal artwork prints | %No | 14 | ||
| 88 | 88 | Framed / Canvas Artwork (Medium) Large kids artwork prints / drawing displays | %No | 2 | ||
| 89 | 89 | Kids Wooden Rocking Horse,Wooden rocking horse toy unit | %No | 1 | ||
| 90 | 90 | Wall-Mounted Large Whiteboard | %No | 1 | ||
| 91 | 91 | Standing Art Easel Board | %No | 1 | ||
| 92 | 92 | Wooden Display Rack / Grids(Wall-mounted wooden grid organizer rack) | %Job | 1 | ||
| 93 | 93 | Interlocking Foam Play Mat(Multi-color square EVA interlocking foam play tiles) | %Set | 1 | ||
| 94 | 94 | Multi-Color Floor Mat / Carpet(Bright colorful play area floor mat / runner) | %Set | 1 | ||
| 95 | 95 | Rainbow Circular Area Rug, Circular multi-colored rainbow pattern carpet / rug | %No | 1 | ||
| 96 | 96 | Vinyl / Wooden Laminate Flooring, Wooden textured finish flooring / floor tiles | %Room | 1 | ||
| 97 | 97 | Furniture | %No | |||
| 98 | 98 | Round Table for Mess | %No | 32 | ||
| 99 | 99 | Sitting Chairs Around round Table | %No | 192 | ||
| 100 | 100 | SECTION - A WIRING / WIRING ACCESSORIES Supply, installation, testing and commissioning of following items including all material, conduits, tools, labor & accessories required for the completion of work as per description & drawings. Complete in all respects. As shown on drawings. | %No | |||
| 101 | 101 | Circuit wiring from DB to switch board including any wiring from switch board to switch board with 3x1C-2.5 Sq.mm Cu/PVC/PVC wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 12 | ||
| 102 | 102 | Wiring for light point from switch board to first light point with 3x1C-2.5 Sq.mm Cu/PVC/PVC in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 39 | ||
| 103 | 103 | Same as above item but wiring from light point to point. | %No | 6 | ||
| 104 | 104 | Circuit wiring from DB to first point with 3x1C-2.5 Sq.mm Cu/PVC/PVC wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 22 | ||
| 105 | 105 | Same as above item but wiring from light point to point. | %No | 270 | ||
| 106 | 106 | Wiring for 13A/15A Switch Socket units (RAW Power) from DB to first outlet with following size of wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. 3x1C-4 Sq.mm, Cu/PVC/PVC | %No | 12 | ||
| 107 | 107 | Same as above item, but wiring from outlet to outlet. | %No | 40 | ||
| 108 | 108 | Wiring of 20A DP Round Switch (For Hand Dryer) from DB to first outlet with following size of wires in 25mm dia PVC conduit as shown on drawings. | %No | |||
| 109 | 109 | 3x1C-4 Sq.mm, Cu/PVC/PVC | %No | 4 | ||
| 110 | 110 | Wiring of 20A DP Isolator for Electric Water Heater from DB to Isolator with 3x1C-4 Sq.mm Cu/PVC/PVC size of wires in 25mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 8 | ||
| 111 | 111 | Wiring of 20A DP Isolator for HVAC Indoor Units / Transfer / Sump Pumps from DB to Isolator with 3x1C-4 Sq.mm Cu/PVC/PVC size of wires in 25mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 10 | ||
| 112 | 112 | Wiring of 40A TP Isolator from DB to Isolator with 4C-6 Sq.mm + ECC 1C-6 Sq.mm Cu/PVC CABLE size of wires in 38mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 6 | ||
| 113 | 113 | Wiring of 32A 5-Pin Industrial Socket from DB with 4C-6 Sq.mm + ECC 1C-6 Sq.mm Cu/PVC size of wires in 38mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 3 | ||
| 114 | 114 | SECTION - B CABLE CONTAINMENT Supply & Installation of following sizes of PVC/UPVC Conduits including all accessories such as bends, sockets, j-boxes, flexible conduits, metal saddles e.t.c for Main / Sub Main Power, Telephone & Data Cables, concealed / surface on wall as per design drawings. Provide MS Pull boxes where ever required. | %No | |||
| 115 | 115 | 25 mm dia PVC Conduit | %Rm. | 200 | ||
| 116 | 116 | 32 mm dia PVC Conduit | %Rm. | 50 | ||
| 117 | 117 | 50 mm dia PVC Conduit (Class-D) | %Rm. | 50 | ||
| 118 | 118 | Supply and installation of following M.S Pull Boxes for data / voice / power / UPS circuits, recessed on wall or column as per design drawings. Complete in all respect. | %No | |||
| 119 | 119 | 200mm×200mm×62mm | %No | 5 | ||
| 120 | 120 | Supply & installation of following sizes of GI/M.S Powder Coated Perforated 16 SWG Cable tray with 18 SWG cover duly Painted with anti corrosive paint after degreesing, derusting, phosphating and antirust primer including all installation accessories such as rovel bolts e.t.c. Complete in all respects. | %No | |||
| 121 | 121 | 200 mm x 100 mm | %Rm. | 25 | ||
| 122 | 122 | SECTION - C SWITCHES & SOCKETS Supply & installation of following 10 Amps switches or 10/13/15/20 Amps socket outlets make including 16 SWG sheet steel back boxes recessed / surface on wall or as per design drawings. | %No | |||
| 123 | 123 | 10A, 220V Three Gang Switch Unit | %No | 9 | ||
| 124 | 124 | 10A, 220V Four Gang Switch Unit | %No | 3 | ||
| 125 | 125 | 10A, 220V One Gang Dimmer Unit | %No | 4 | ||
| 126 | 126 | 13A, International Switch Socket unit (For Raw Power) | %No | 25 | ||
| 127 | 127 | 15A, 3 Pin Round Switch Socket unit (For Raw Power) | %No | 6 | ||
| 128 | 128 | 20A DP Switch with Neon Indication Light (For Hand Dryer) | %No | 8 | ||
| 129 | 129 | 20A DP Isolator for Electric Heaters | %No | 8 | ||
| 130 | 130 | 20A DP Isolator for HVAC Indoor Units / Transfer Pumps / Sump Pumps | %No | 10 | ||
| 131 | 131 | 40A TP Isolator for HVAC Floor Standing Units | %No | 6 | ||
| 132 | 132 | 32A 5-Pin Industrial Socket with Plug | %No | 3 | ||
| 133 | 133 | SECTION - D MAIN / SUB-MAIN CABLES Supply, Installation, testing and commissioning of following sizes of Main / Sub main Cables in already installed cable tray, conduit etc. Including all accessories, lugs, glands etc. complete in all respect as shown on drawing. | %No | |||
| 134 | 134 | From Utility Supply to Main Panel 4C-50 Sqmm CU/PVC/PVC + 1C-25 Sqmm CU/PVC | %Rm. | 25 | ||
| 135 | 135 | From Main Panel to LPDB 4C-35 Sqmm CU/PVC/PVC + 1C-16 Sqmm CU/PVC | %Rm. | 25 | ||
| 136 | 136 | From Main Panel to DB-UPS 4C- 4 Sqmm CU/PVC/PVC + 1C- 4 Sqmm CU/PVC | %Rm. | 25 | ||
| 137 | 137 | From Main Panel to DB-KITCHEN 4C-10 Sqmm CU/PVC/PVC + 1C-10 Sqmm CU/PVC | %Rm. | 35 | ||
| 138 | 138 | From Main Panel to DB-EXTERNAL 4C- 6 Sqmm CU/PVC/PVC + 1C- 6 Sqmm CU/PVC | %Rm. | 35 | ||
| 139 | 139 | From Main Panel to DB-AC 4C- 25 Sqmm CU/PVC/PVC + 1C- 16 Sqmm CU/PVC | %Rm. | 35 | ||
| 140 | 140 | SECTION - E LV PANELS & DISTRIBUTION BOARDS Supply & installation, testing & commissioning of following Low Voltage Panels made with 14 SWG and Distribution Boards as shown on drawing made with 16 SWG sheet steel housing including all installation accessories such as Rowel bolt etc. Refer SLD and General Notes. | %No | |||
| 141 | 141 | MAIN PANEL | %No | 1 | ||
| 142 | 142 | LPDB | %No | 1 | ||
| 143 | 143 | DB-UPS-1F | %No | 1 | ||
| 144 | 144 | DB-AC | %No | 1 | ||
| 145 | 145 | DB-EXTERNAL | %No | 1 | ||
| 146 | 146 | DB-KITCHEN | %No | 1 | ||
| 147 | 147 | SECTION - F LIGHTING FIXTURES & AIR CONDITIONING - INDOOR LIGHTS | %No | |||
| 148 | 148 | Supply, installation, testing and commissioning of 100mm wide recessed linear LED light, complete with aluminium profile, opal diffuser, LED module, driver, mounting accessories and connections; 4000K, CRI ≥80, PF >0.90, 1,500–2,000 lm/m. Complete in all respects. (For Sitting area Outer Octgon) | %Rmtr. | 145.69439533778 | ||
| 149 | 149 | Supply, installation, testing and commissioning of 15W recessed LED downlight, complete with LED module, trim, driver, mounting accessories and connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. (For Sitting area Outer Octgon) | %No | 36 | ||
| 150 | 150 | Supply, installation, testing and commissioning of 10W recessed LED downlight, complete with LED module, trim, driver, mounting accessories and connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. (For the Rest Room) | %No | 8 | ||
| 151 | 151 | Supply, installation, testing and commissioning of 20W recessed LED downlight, complete with LED module, trim, driver, mounting accessories and connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. (For Others Areas) | %No | 10 | ||
| 152 | 152 | Supply, installation, testing and commissioning of concealed LED strip light 15W/Mtr., complete with aluminium profile, diffuser, LED strip, driver, connectors and accessories; 4000K, CRI ≥80, suitable for continuous architectural/cove lighting. Complete in all respects. (For Inner Octagon & Kitchen counter/worktop under the wall cabinets) | %Rmtr. | 248 | ||
| 153 | 153 | Supply, installation, testing and commissioning of sleek wall-mounted cylindrical LED light, approximately 2'-0" long, complete with LED module, housing, diffuser, driver, mounting accessories and electrical connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. | %No | 24 | ||
| 154 | 154 | Supply, installation, testing and commissioning of 2'-0" long slim wall-mounted LED mirror light, complete with LED module, diffuser, driver, mounting accessories and electrical connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. | %No | 8 | ||
| 155 | 155 | Supply, installation, testing and commissioning of wall-mounted LED Emergency Exit Sign, complete with green illuminated exit signage, 8W LED light source, battery backup, housing, mounting accessories and necessary electrical connections; suitable for emergency/escape route indication. Complete in all respects. | %No | 5 | ||
| 156 | 156 | SECTION - F LIGHTING FIXTURES & AIR CONDITIONING - OUTDOOR LIGHTS | %No | |||
| 157 | 157 | Supply, installation, testing and commissioning of 20W recessed LED downlight, complete with LED module, trim, driver, mounting accessories and connections; 4000K, CRI ≥80, PF >0.90. Complete in all respects. (For Outer premisses) | %No | 36 | ||
| 158 | 158 | Supply, installation, testing and commissioning of LED Flood Light Fixture, complete with LED light source, housing, driver, mounting bracket, accessories and necessary electrical connections; 80W, weatherproof, IP65, 3000K, CRI >80, PF >0.90, suitable for external architectural/landscape illumination, or as approved by the Architect. Complete in all respects. | %No | 6 | ||
| 159 | 159 | Supply, installation, testing and commissioning of LED Garden Spike Light, complete with weather-resistant aluminium body, adjustable spotlight head, ground spike, LED light source, integral driver and all necessary mounting and electrical accessories; 12W, IP65, 3000K, CRI >80, PF >0.90, suitable for planter and landscape illumination. Complete in all respects as approved by the Architect. | %No | 15 | ||
| 160 | 160 | Supply, installation, testing and commissioning of decorative LED Bollard Light, complete with corrosion-resistant M.S./aluminium body, suitable LED light source, integral driver, base plate, anchor bolts and all necessary mounting and electrical accessories; 20W, IP65, 3000K, CRI >80, PF >0.90, suitable for external pathway/landscape lighting. Complete in all respects as approved by the Architect. | %No | 8 | ||
| 161 | 161 | AIR VENTILATION | %No | |||
| 162 | 162 | Supply, installation, testing and commissioning of 2'-0" × 2'-0" recessed ceiling-mounted fan, complete with fan motor, grille, mounting frame, regulator/controller and necessary electrical accessories; 230V, 50Hz, energy-efficient and low-noise type, or as approved by the Architect. Complete in all respects. | %No | 4 | ||
| 163 | 163 | Supply, installation, testing and commissioning of wall-mounted exhaust fan, complete with fan motor, protective grille, backdraft shutter, mounting accessories and necessary electrical connections; suitable for washroom ventilation, 230V, 50Hz, low-noise type, or as approved by the Architect. Complete in all respects. | %No | 8 | ||
| 164 | 164 | Supply, installation, testing and commissioning of inline duct-mounted exhaust fan, complete with fan motor, casing, mounting brackets, flexible connectors, backdraft damper, suitable duct connections and necessary electrical accessories; 300W, 230V, 50Hz, approximately 900 CFM capacity, low-noise type, suitable for kitchen exhaust ventilation and connection to exhaust ductwork. Complete in all respects as approved by the Architect. | %No | 1 | ||
| 165 | 165 | Supply, installation, testing and commissioning of 4-Ton floor-standing split air-conditioning unit, complete with indoor and outdoor units, compressor, refrigerant piping, control system, drain piping, necessary supports, insulation, electrical connections and all accessories; 230V, 50Hz, energy-efficient type, suitable for the required cooling capacity, or as approved by the Architect. Complete in all respects. | %No | 6 | ||
| 166 | 166 | Supply, installation, testing and commissioning of 2-Ton wall-mounted split air-conditioning unit, complete with indoor and outdoor units, compressor, refrigerant piping, drain piping, insulation, remote control, electrical connections and all necessary accessories; 230V, 50Hz, energy-efficient type, or as approved by the Architect. Complete in all respects. | %No | 4 | ||
| 167 | 167 | SECTION - G ADDRESSABLE FIRE ALARM SYSTEM Supply, Installation, testing & commissioning of following items for Addressable Fire Alarm System comprising of following equipments including all accessories required for the completion of the system in all respects | %No | |||
| 168 | 168 | Addressable Fire Alarm Control Panel of 2-Loop, having maximum of 200 devices per loop. The FACP shall be self powered with built in 12V batteries for 24 Hrs backup with charging unit. It can be programmed using Windows based software for peripheral devices like display unit, printers etc. | %No | 1 | ||
| 169 | 169 | Addressable Smoke Detectors incorporating an LED indication located in labyrinth with in the housing of the detector. Sensing of the detector shall be adjustable via software between 0-90 seconds. The detector shall have built in short circuit isolators on both inputs. | %No | 24 | ||
| 170 | 170 | Addressable Heat Detectors incorporating an LED indication located in labyrinth with in the housing of the detector. Sensing of the detector shall be adjustable via software between 0-90 seconds. The detector shall have built in short circuit isolators on both inputs. | %No | 9 | ||
| 171 | 171 | Addressable Break Glass Type Manual Call Point having a built in short circuit isolator and built in microprocessor to ensure a response time of max 1 second. It also incorporates an indication LED, flashed after pressing the button to acknowledge the activation and a key operation facility for testing purposes. | %No | 4 | ||
| 172 | 172 | Addressable Type Indoor Loop Powered electronic sounder with flasher and minimum sound out put 100 dB at 1 meter with frequencies for variety of sounds as required. Souder shall be loop wired and loop signaled, built in short circuit isolator, configured via software. | %No | 4 | ||
| 173 | 173 | Supply & wiring for whole Fire Alarm System using 2C, 1.5 Sq.mm Fire Resistant Shielded Cable (Fire Rating for 2 hours) in 25mm dia PVC conduit from fire alarm control panel to all sensors & devices including all installation accessories. Complete in all respects. Cable should comply below standard: 180 minutes Fire retardant, Low Smoke, Zero Halogen cable BS 6387 LPCB | %Rm. | 492 | ||
| 174 | 174 | SECTION - H EARTHING / GROUNDING SYSTEM Supply, installation, testing and commissioning of following items for Earthing / Grounding System of other systems including all material, boring, labor, tools, transportation, accessories etc. Complete in all respects with detailed test reports. | %No | |||
| 175 | 175 | Chemical Enhanced Earth using 17.2 mm dia 3m copper cladded rod including 4" dia, 11' deep boring and back filled with chemical to enhance conductivity. Complete with termination clamps, and heavy duty Earthing Pit with cover as per details given in drawings. (GCEM Chemical to be Used) | %No | 2 | ||
| 176 | 176 | Earth Connecting Point (ECP) or Equipotential bar made with 200 mm wide, 50mm high and 5mm thick tin plated Copper, as shown in drawings. Bar shall be provided with holes suitable for installation of 4 No. 70 sqmm bare copper conductor. Note: ECP shall be enclosed in appropriate size of powder coated metal enclosure with front accessible cover. | %No | 2 | ||
| 177 | 177 | Stranded bare copper conductors of following sizes in appropriate size of PVC/UPVC conduit laid in floor/raft from Earth Station to ECP to as shown in drawings. Complete in all respects including termination at ECP. | %No | |||
| 178 | 178 | 1C, 70 Sq.mm Bare Copper Conductor | %Rm. | 65 | ||
| 179 | 179 | Supply, installation, testing and commissioning of following size of Single core PVC Cables from ECP to several equipments as per details given in schematic drawings, including all material, labor, tools, transportation, accessories etc. Complete in all respects with detailed test reports. | %No | |||
| 180 | 180 | 1C, 70 Sq.mm Cu/PVC (Green) | %Rm. | 40 | ||
| 181 | 181 | 1C, 16 Sq.mm Cu/PVC (Green) | %Rm. | 80 | ||
| 182 | 182 | HVAC-85 TONNAGE CAPACITY | %No | |||
| 183 | 183 | Supply, installation, testing and commissioning of complete VRF Air Conditioning System, comprising all outdoor and indoor units (cassette, ducted and fresh air units), refrigerant copper piping with closed-cell insulation, Y-branches, isolation valves, additional refrigerant charging, factory-fabricated G.I. ducting with insulation, supply/return air grilles, diffusers, jet nozzles, fresh air louvers, UPVC condensate drain piping with insulation, cable trays, control wiring, flexible duct connectors, hangers, supports, accessories, fittings and all associated mechanical, electrical and control works. The scope shall include fabrication, fixing, alignment, supports, sealing, testing, balancing, commissioning, shop drawings, as-built drawings and all labor, materials, equipment, tools and incidentals required to complete the HVAC system in all respects as per approved drawings, project specifications, manufacturer's recommendations and the Engineer's instructions. | %JOB | 1 | ||
| 184 | 184 | IT WORKS | %No | |||
| 185 | 185 | 85" LED | %No | 4 | ||
| 186 | 186 | 65" LED | %No | 1 | ||
| 187 | 187 | 24-Port Managed POE Ethernet Switch S5735-L24P4XE-A-V2 | %No | 1 | ||
| 188 | 188 | SFPs (LC) 1 km, Single Mode, dual 10G Gigabit Industrial grade | %Pairs | 2 | ||
| 189 | 189 | 24 Port Patch Panel | %No | 1 | ||
| 190 | 190 | Cable Organizer | %No | 1 | ||
| 191 | 191 | WIFI Access Points Indoor Tplink EAP 660 | %No | 3 | ||
| 192 | 192 | Fiber Optic Cable 12-core Single mode with Digging and laying (End to End Connectivity) | %Mtr | 100 | ||
| 193 | 193 | 12-Port ODF for Patching of Fiber Optic with Splicing | %No | 1 | ||
| 194 | 194 | Fiber Patch Cords 3m Single mode (LC-LC) | %No | 5 | ||
| 195 | 195 | Ethernet Patch Cords 1m | %No | 10 | ||
| 196 | 196 | Ethernet Patch Cords 3m | %No | 10 | ||
| 197 | 197 | Ethernet I/O (Faceplate with Box) | %No | 5 | ||
| 198 | 198 | 4 Port Rack mounted PDUs with loop cables | %No | 1 | ||
| 199 | 199 | UTP CAT6 (305 Meter) Roll | %Roll | 2 | ||
| 200 | 200 | UPS 2KVA | %No | 1 | ||
| 201 | 201 | 9U Cabinet | %No | 1 | ||
| 202 | 202 | IP-Phone | %No | 2 | ||
| 203 | 203 | 8 MP Fixed Bullet Camera | %No | 8 | ||
| 204 | 204 | 8 Channel NVR with 5 TB HDD | %No | 1 | ||
| 205 | 205 | NDMA MOSQUE | %No | |||
| 206 | 206 | Steel Structure | %No | |||
| 207 | 207 | Design, Manufacturing and Supply of Pre engineered Steel Shed having including, primary structural steel rafters, columns, Connection plates, Base plates, Roof Purlins, Pre-painted roof sheet, Trims, gutters, Down take Pipes and cross wire bracing, anchor bolts for anchorage and Other Necessary hardware fixing screws complete in all respects. | %Sft | 6515 | ||
| 208 | 208 | Supply & Installation Mazzanine floor steel structure | %Sft | 5667 | ||
| 209 | 209 | Supply & Installation of Roof area only Glass Wool Insulation 100mm Thick with Mesh Density (10 – 12) Kg/m3. | %Sft | 6515 | ||
| 210 | 210 | Supply and Installation of Steel structure stair including railing with 12mm thk glass complete in all respects | %Job | 1 | ||
| 211 | 211 | Providing, fabricating, and installing Fibreglass main dome structure with green weather-resistant polyurethane paint finish, including structural steel support base, waterproofing treatment, flashing, and decorative MS/Brass crescent finial at top, complete in all respects. | %Job | 1 | ||
| 212 | 212 | Civil/Archituctural Works | %No | |||
| 213 | 213 | Dismantling of Existing Structure and Site Clearance including the removal of surplus debris, unused material and by products as directed by the Engineer complete. | %Job | 1 | ||
| 214 | 214 | Excavation for foundation of columns, walls, etc. upto any depth and lead including back filling of excavated earth in foundation trenches and spreading the surplus earth in plinth area and/or depressions where required including making provision for shoring of loose soil if required and removal of excavated earth upto 5'-0" from edge of excavation complete as per drawing and as directed by the Consultants. | %Cft | 25879.85 | ||
| 215 | 215 | Providing Earth filling with off site material (brought from out side source)including compaction upto 95% in plinth, depression and where ever required laid in 12" layer well watered, consolidated and compacted with mechanical means complete as per drawing and as directed by the Consultants. | %Cft | 31042.68825 | ||
| 216 | 216 | Providing C.C. 1:4:8 bed concrete using graded screened bajri 3/8" and down gauge as fine aggregate and stone ballast 1" to 2" size as coarse aggregate in foundation over well compacted earth including levelling and curing etc. complete as per drawing and as directed by the Consultants | %Cft | 3930.273375 | ||
| 217 | 217 | Providing Reinforced cement concrete 1:2:4 (mix design) using graded screened bajri 3/8" and down gauge as fine aggregate and crushed stone 3/4" and down gauge as coarse aggregate with machine mixing including the cost of form work and its removal, vibrating using mechanical vibrator, curing and cube testing etc. having min. works cube crushing strength of 3,000 psi after 28 days curing but excluding the cost of reinforcement bars complete as per drawing and as directed by the Consultants. | %Cft | 8936.8965 | ||
| 218 | 218 | Providing brick masonry using 9" x 4 1/2" x3" best approved quality burnt bricks the bricks used should be well-burnt without being vitrified and shall be uniform in colour, regular in shape and size with sharp and square corners and parallel faces, free from flaws and crackes, to be laid in mortar 1:4 with curing, scaffolding, racking out the joints, courses shall be kept in time plumb as per drawing, standard specificaiton and as directed by the Consultants Up To 12ft Height. | %Cft | 11542.904625 | ||
| 219 | 219 | Providing fabrication and instllation in position 12mm of gypsum board sheet (gypsum board approved company) including cuttong of opening for lights ifixture/ diffusers with making of light pelmet fiber tape on joints icluding 3 coats of mat enamel paint fininsh pemerr coat filing if required with all other hardwares, wastage scaffolding, making access panel (where required)etc as per design & drawing complete. | %Sft | 12791.1 | ||
| 220 | 220 | Providing & Fixing of Decorative wooden Cladding following coved ceiling geometry fixed to ceiling frame | %Sft | 440 | ||
| 221 | 221 | Supply, fabrication and installation of decorative architectural cladding over steel columns in mosque, comprising concealed GI/MS supporting framework, approved wood/bronze-finish decorative panels with vertical fluted/ribbed profiles, top and bottom capping, trims, brackets, fasteners, sealant and all necessary fixing accessories, including cutting, fabrication, alignment, finishing and complete installation as per approved architectural design, sample and dimensions, complete in all respects. | %Nos | 8 | ||
| 222 | 222 | Supply and installation of high-quality mosque Prayer carpet, with Islamic geometric medallion pattern, with suitable underlay, dense pile masjid-grade, wall-to-wall fitted with edge binding | %Sft | 13578.6 | ||
| 223 | 223 | Design, supply, fabrication and installation of an aesthetically designed mosque Mihrab feature wall, comprising decorative architectural wall cladding with premium-quality stone/marble/wood-finish panels, ornamental profiles, recessed and raised features, decorative borders, Islamic geometric elements and approved calligraphy, including concealed supporting framework, backing, trims, mouldings, fixing accessories, surface finishing, polishing and all necessary works, complete in all respects as per approved architectural design, shop drawings, material samples and specifications. | %Nos | 1 | ||
| 224 | 224 | Providing, fabricating, and fixing decorative interior pointed-arch CNC laser-cut Islamic geometric Jali window panels, including dark-finished hardwood/HDF border frame, HDF/WPC lattice screen, frosted acrylic backing diffuser sheet, PU satin finish paint, concealed fasteners, and silicone joint sealing complete. | %Sft | 1100 | ||
| 225 | 225 | Providing, fabricating, and fixing main entrance porch and to cover Rain water pipe,portal frame featuring arched opening, decorative white CNC laser-cut geometric Jali side panels of approved design, border trim mouldings, and weather-proof exterior coat finish, complete as per drawings and Engineer's instructions. | %Sft | 1340 | ||
| 226 | 226 | Supply & Installation of Multi-tier crystal/acrylic strand chandelier, decorative centrepiece fixture, tiered drum design, complete with chain suspension, driver & LED lamping | %Nos | 1 | ||
| 227 | 227 | Providing and fixing powder coated or anodized aluminum, glazed door of aluminum sections, tinted glass, rubber gaskets, double action floor mounted concealed type pivot hinge mechanism, hydraulic door closer, handles & locking arrangement, screws/expansion bolts and other aluminum accessories etc. complete in all respects as approved by the Engineer. | %Sft | 105.6 | ||
| 228 | 228 | Providing and laying 1/2" thick cement sand plaster (1:4) to Internal Ceiling, Walls, Stairs, Columns, & etc making edges and corners, preparation of surface plaster with mesh, including finishing, scaffolding, curing and etc. Complete in all as per drawing & instruction of the Consultant. | %Sft | 24815.7 | ||
| 229 | 229 | Providing and applying exterior wall finish system on cement-sand plaster, grooved channel details, weather-resistant primer, and two coats of premium exterior-grade acrylic emulsion weather-shield paint in approved dual-tone grey/white shade, complete as per site requirements. | %Sft | 9536.1 | ||
| 230 | 230 | Providing and applying 2 coats of Plastic Emulsion paint (Mat finish) of approved quality, color and shade (approved company) over 2 coats of Primer of approved manafacturer and quality on Ceiling, Columns, Walls, & etc including surface preparation, Wall putty filling, cutting, surfacing, scaffolding, scraping, sanding, & etc. Complete in all as per drawing & instruction of the Consultant. | %Sft | 11699.325 | ||
| 231 | 231 | Providing and installing decorative outdoor /composite pergola canopy of Approved metarial consisting of main support beams and cross rafters, treated with anti-termite sealant and exterior weather-resistant paint, complete. | %Rft | 350 | ||
| 232 | 232 | Providing Reinforced steel bars using minimum Yield Strength of 60 KSI confirming to ASTM A-615, as per design including cutting, bending, binding and placing in position on c.c precast spacers and steel chairs, tying with binding wire 20 SWG complete with the cost of chairs, binding wire etc. complete as per drawing and as directed by the Consultants.(Rate should include the cost of westage of steel, also note that All Reinforcing steel shall be adequately protected from rust and corrosion before and during concreting) | %Ton | 34 | ||
| 233 | 233 | Providing and installation of locally produced Porcelain tiles on floor, Wall & skirting with cement motar 1:4 and complete with screening, grouting, filling, finishing and etc. complete in all respects, as per drawing & instruction of the consultant or Engineer. | %Sft | 15022.14525 | ||
| 234 | 234 | Providing and fixing complete flooring and Wall Cladding in ablution area (including main floor area, Wall area, space beneath seating blocks, and drainage channels) using approved quality of Approved thickness Travertine Marble slabs in vein-cut pattern, laid over concrete substrate with polymer-modified high-bond waterproof adhesive, jointed and pointed with matching non-shrink epoxy grout, complete with edge chamfering, drain cut-outs, surface waterproofing, anti-slip sealing treatment, silicon joint sealing, and cleaning complete as per architectural drawings, site specifications, and instructions of the Engineer-in-Charge. | %Sft | 1250 | ||
| 235 | 235 | Providing and fixing of Pre Polished Granite Sills / Thresholds under windows and doors respectively , of approved origin, color/shade / thickness fix with cement sand mortar | %Sft | 450 | ||
| 236 | 236 | Supply & Installation of 3'-0" High Glass Railing System, comprising approved thickness toughened/tempered glass panels, SS/aluminium posts, handrail, base channels, brackets, clamps, fittings, anchors, sealants and all necessary accessories, including fixing, alignment and finishing, complete in all respects | %Sft | 330 | ||
| 237 | 237 | Providing and making at site Plinth Protection around the building area 3'-0'' wide comprising of brick masonry, back filling, compaction, pcc 1:2:4 complete in all respects. | %CFT | 2772 | ||
| 238 | 238 | Providing and Fixing of Cementious Tile/chemical tile of Different sizes at plinth protection Comprising cement Sand Mortor complete in all respects. | %Sft | 924 | ||
| 239 | 239 | Plumbing Works (1 nos of washroom with all accessories.Pipe for inlet/outlet and connection with service water tank included; internal suigas connectivity for any kitchen; conclealed service water tank included; suigas submeter, | %No | 5 | ||
| 240 | 240 | Installation of Blind Curtain Providing placing and installation of Blind curtain including preparation of all required arrangments and access work to be complete as per quality & interior finishes aspects in accordance with the specification complete in all respect | %Sft | 1879.5 | ||
| 241 | 241 | Supply and installation of premium-grade uPVC toilet/washroom door, comprising a rigid uPVC frame. Door to include solid uPVC panels for high durability in wet areas Complete in all aspects | %Sft | 100 | ||
| 242 | 242 | Providing and laying 6" Gravel Fill Material of approved quality and size in foundation including Compaction, complete in all respects. | %CFT | 3420.375 | ||
| 243 | 243 | Supply of Aluminium Fixed Curtain Wall, Premium Quality, of Anodized Aluminium extruded section size, colour and texture as specified, including fixing on concrete, wood or steel frames, complete with all necessary fittings incl 6mm double glazed glass all as specified. | %Sft | 2257.5 | ||
| 244 | 244 | Providing and installation of 8" dia bore l 120 ft deep along with 1.5hp submersible pump | %Job | 1 | ||
| 245 | 245 | Providing, installation, testing, commissioning of Water pressure booster pumps for water supply (One operation and one standby). Pumps shall be complete with electric drive motor, operate at 230 volts, single phase 50 hertz including electric power supply wiring conduiting, earthing etc. complete in all respects as per specification | %Job | 1 | ||
| 246 | 246 | Supply, Installation, Testing & Commissioning of Complete Plumbing Piping System for Ablution and washroom areas, including internal and external PPRC, UPVC and Other pipes of approved sizes and specifications for cold & hot water supply, soil, waste, Vent and drainage lines, complete with all necessary fittings, elbows, tees, reducers, unions, valves, traps, clamps, supports, sleeves, connections, jointing materials and accessories, including chasing, fixing, testing and making good, complete in all respects as per approved drawings and Engineer’s instructions. | %Job | 1 | ||
| 247 | 247 | Providing and Installation of Rain Water pipe Dia 6'' with calmps and all other nessary hardware | %RFT | 500 | ||
| 248 | 248 | Supply, installation, testing and commissioning of 150-Liter electric storage water heater (geyser) for mosque ablution area, complete with heating element, thermostat, temperature and pressure safety valve, inlet/ outlet connections, isolation valves, flexible connections, supports, thermal insulation, and all necessary plumbing and electrical accessories, including labour, testing and commissioning, complete in all respects. | %NO | 1 | ||
| 249 | 249 | Supply & Fixing of Wall-mounted ablution tap fitting with concealed angle valve, chrome-plated brass, complete in all aspects. | %No | 14 | ||
| 250 | 250 | Concealed PPR water supply piping to each tap point, including tee-offs from main riser, pressure tested. | %Point | 14 | ||
| 251 | 251 | Supply, installation, testing and commissioning of stainless steel drinking water cooler, complete with cooling system, storage tank, drinking taps, inlet/outlet connections, drain and all necessary fittings and accessories, complete in all respects. | %No | 1 | ||
| 252 | 252 | Supply and installation of water-absorbent carpet/mat for ablution area, complete in all aspects | %Rft | 60 | ||
| 253 | 253 | Supply & installation of digital mosque prayer time display with LED screen, controller, power supply and accessories, complete. | %No | 2 | ||
| 254 | 254 | Supply & installation of wall-mounted analog clock with complete mechanism, battery and mounting accessories. | %No | 2 | ||
| 255 | 255 | Road Works | %No | |||
| 256 | 256 | Earthwork in Excavation / Filling to Sub-Grade Level, Dressing to Design Line(Road) | %Cft | 4200 | ||
| 257 | 257 | Preparation, Dressing, Levelling and Compaction of Existing Soil/Subgrade to the required line | %Sft | 4200 | ||
| 258 | 258 | Providing P C.C. 1:4:8 bed concrete using graded screened bajri 3/8" and down gauge as fine aggregate and stone ballast 1" to 2" size as coarse aggregate for road tuff paver over well compacted earth including levelling and curing etc. complete as per drawing and as directed by the Consultants | %Cft | 924 | ||
| 259 | 259 | Provide and lay 80mm thick 6000 psi cube strength precast Paver Concrete sand bed, Including the cost of 3" thick approved quality graded aggregate subgrade must be well compacted upto 98% compaction. | %SFT | 4000 | ||
| 260 | 260 | Side Drains (RCC / Masonry, Covered), Both Sides | %RFT | 350 | ||
| 261 | 261 | Horticulture/ Landscapting | %No | |||
| 262 | 262 | Earthwork in Excavation / Filling, Dressing to Design Line | %CFT | 6500 | ||
| 263 | 263 | Supply & Installation of 12ft high Ornamental Palm Trees (Field Transplant incl. Staking & Initial Care) | %Nos | 7 | ||
| 264 | 264 | Turfing / Lawn Development (Grass Turf incl. Soil Preparation, sweet soil and Grass instl) | %SFT | 5500 | ||
| 265 | 265 | Furniture | %No | |||
| 266 | 266 | Providing, fabricating, and fixing wooden open-pigeonhole shoe rack unit for mosque entrance area, constructed using approved gauge High-Density Fiberboard (HDF) / commercial plywood with approved laminate/veneer finish on all exposed surfaces, featuring multiple open cubicle compartments of uniform size as per site layout, complete with PVC edge banding tape on all open edges, internal joinery, rawl plugs, concealed wall anchorage, hardware, and surface finishing, all complete. | %No | 1 | ||
| 267 | 267 | SECTION - A WIRING / WIRING ACCESSORIES Supply, installation, testing and commissioning of following items including all material, conduits, tools, labor & accessories required for the completion of work as per description & drawings. Complete in all respects. As shown on drawings. Note: 1) The cost of wiring items shall includes Imported Polycarbonate Connectors (as approved by the consultant) and High Quality flexible conduit on each light point. 2) The circuit wire will drop in flexible conduit 3)Insulation,resistance (Megger) Test of each circuit to be done by contractor. 4)The surface conduiting shall be done in decorative / aesthetic manner wherever applicable. 5)Wherever the circuits are running in cable tray, it will enter / leave tray using proper glands / Junction boxes (IP44). The cost of all such accessories to be included in wiring cost. 6) All electrical circuits and power outlets shall be numbered (i.e. circuit number and distribution board number) and the circuit schedule of the distribution board must accurately reflect the installation. The load across all phases must be balanced 7). Color Code Phase: - 3 Phases (Red) with proper phase tagging - Neutral (black) - Earth (green/green-yellow) - Control wiring (Orange or red) | %No | |||
| 268 | 268 | Circuit wiring from DB to switch board including any wiring from switch board to switch board with 3x1C-1.5 Sq.mm Cu/PVC/PVC wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 8 | ||
| 269 | 269 | Wiring for light point from switch board to first light point with 3x1C-1.5 Sq.mm Cu/PVC/PVC in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 15 | ||
| 270 | 270 | Same as above item but wiring from light point to point. | %No | 30 | ||
| 271 | 271 | Circuit wiring from DB to first point with 3x1C-1.5 Sq.mm Cu/PVC/PVC wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | 5 | ||
| 272 | 272 | Same as above item but wiring from light point to point. | %No | 20 | ||
| 273 | 273 | Wiring for 13A/15A Switch Socket units (RAW Power) from DB to first outlet with following size of wires in 25mm dia PVC Conduit / Cable Tray as shown in drawings. | %No | |||
| 274 | 274 | 3x1C-2.5 Sq.mm, Cu/PVC/PVC | %No | 12 | ||
| 275 | 275 | Same as above item, but wiring from outlet to outlet. | %No | 40 | ||
| 276 | 276 | Wiring For Chandelier from DB to first outlet with following size of wires in 25mm dia PVC conduit as shown on drawings. | %No | |||
| 277 | 277 | 3C-2.5 Sq.mm, Cu/PVC/PVC | %No | 1 | ||
| 278 | 278 | Wiring of 20A DP Isolator for Electric Geyser from DB to Isolator with 3C-2.5 Sq.mm Cu/PVC/PVC size of wires in 25mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 1 | ||
| 279 | 279 | Wiring of 20A TP Isolator for Pump DB to Isolator with 4C-4 Sq.mm Cu/PVC/PVC + ECC 1C-4 Sq.mm Cu./PVC CABLE size of wires in 32mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 1 | ||
| 280 | 280 | Wiring of 20A TP Isolator for HVAC Indoor Units from DB to Isolator with 4C-4 Sq.mm + ECC 1C-4 Sq.mm Cu/PVC CABLE size of wires in 38mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 4 | ||
| 281 | 281 | Wiring of 20A 3-Pin Industrial Socket for Comm. Racks from DB with 3 x 4 Sqmm Cu/PVC size of wires in 25mm dia PVC conduit / Cable Tray as shown on drawings. | %No | 1 | ||
| 282 | 282 | SECTION - B CABLE CONTAINMENT Supply & Installation of following sizes of PVC/UPVC Conduits including all accessories such as bends, sockets, j-boxes, flexible conduits, metal saddles e.t.c for Main / Sub Main Power, Telephone & Data Cables, concealed / surface on wall as per design drawings. Provide MS Pull boxes where ever required. | %No | |||
| 283 | 283 | 25 mm dia PVC Conduit | %Rm. | 20 | ||
| 284 | 284 | 32 mm dia PVC Conduit | %Rm. | 20 | ||
| 285 | 285 | 50 mm dia PVC Conduit (Class-D) | %Rm. | 20 | ||
| 286 | 286 | Supply and installation of following M.S Pull Boxes for data / voice / power / UPS circuits, recessed on wall or column as per design drawings. Complete in all respect. | %No | |||
| 287 | 287 | 200mm×200mm×62mm | %No | 2 | ||
| 288 | 288 | Making of Man Hole, finished with plaster & covered with heavy duty G.I cover with anti-rust paint. (For M.V/ L.V Cables whereever required as mentioned in drawings) | %No | |||
| 289 | 289 | 900mm x 900mm x 1200mm RCC Man Hole | %No | 1 | ||
| 290 | 290 | SECTION - C SWITCHES & SOCKETS | %No | |||
| 291 | 291 | Supply & installation of following 10 Amps switches or 10/13/15/20 Amps socket outlets make including 16 SWG sheet steel back boxes recessed / surface on wall or as per design drawings. | %No | |||
| 292 | 292 | 10A, 220V Three Gang Switch Unit | %No | 12 | ||
| 293 | 293 | 10A, 220V Four Gang Switch Unit | %No | 8 | ||
| 294 | 294 | 13A switched twin socket outlet, BS 1363 type, flush mounted, complete with box and accessories | %No | 20 | ||
| 295 | 295 | Dedicated 13A switched socket outlet for miscellaneous equipment | %No | 8 | ||
| 296 | 296 | 13A socket outlet for cleaning/maintenance purposes | %No | 4 | ||
| 297 | 297 | 13A socket outlet for Imam/office/administrative use | %No | 4 | ||
| 298 | 298 | 20A DP geyser isolator | %No | 1 | ||
| 299 | 299 | 20A TP Isolator for water pump | %No | 1 | ||
| 300 | 300 | 20A TP Isolator for HVAC floor standing unit | %No | 4 | ||
| 301 | 301 | 20A 3-Pin Industrial Socket with Plug for Communication Racks & UPS | %No | 2 | ||
| 302 | 302 | SECTION - D MAIN / SUB-MAIN CABLES | %No | |||
| 303 | 303 | Supply, Installation, testing and commissioning of following sizes of Main / Sub main Cables in already installed cable tray, conduit etc. Including all accessories, lugs, glands etc. complete in all respect as shown on drawing. | %No | |||
| 304 | 304 | From Utility Supply to Main Panel 4C-25 Sqmm CU/PVC/PVC + 1C-16 Sqmm CU/PVC | %Rm. | 25 | ||
| 305 | 305 | From Main Panel to DB-AC 4C-6 Sqmm CU/PVC/PVC + 1C-6 Sqmm CU/PVC | %Rm. | 15 | ||
| 306 | 306 | From Main Panel to LPDB-GF 4C- 16 Sqmm CU/PVC/PVC + 1C- 16 Sqmm CU/PVC | %Rm. | 15 | ||
| 307 | 307 | From Main Panel to LPDB-FF 4C- 16 Sqmm CU/PVC/PVC + 1C- 16 Sqmm CU/PVC | %Rm. | 30 | ||
| 308 | 308 | From Main Panel to DB-EXTERNAL 4C- 10 Sqmm CU/PVC/PVC + 1C- 10 Sqmm CU/PVC | %Rm. | 30 | ||
| 309 | 309 | SECTION - E LV PANELS & DISTRIBUTION BOARDS Supply & installation, testing & commissioning of following Low Voltage Panels made with 14 SWG and Distribution Boards as shown on drawing made with 16 SWG sheet steel housing including all installation accessories such as Rowel bolt etc. All the Panels and DB's should also be "Weather Proof", with anti-corrosive paint and zinc oxide/epoxy layers for derusting and degreasing. It should also include a warranty of 10 years for its anti-corrosive primer/coating. Complete in all respects. Refer SLD and General Notes. | %No | |||
| 310 | 310 | MAIN PANEL | %No | 1 | ||
| 311 | 311 | LPDB-GF | %No | 1 | ||
| 312 | 312 | LPDB-1F | %No | 1 | ||
| 313 | 313 | DB-AC | %No | 1 | ||
| 314 | 314 | DB-EXTERNAL | %No | 1 | ||
| 315 | 315 | TP Box 80A | %No | 1 | ||
| 316 | 316 | SECTION - F FIXTURES - Indoor Lights Supply, installation, testing and commissioning of complete lighting installation comprising LED luminaires, recessed/surface-mounted fittings, architectural lighting, LED strip lighting, chandelier points, pathway lighting, emergency lighting and exit signage, including all required wiring, conduits, junction boxes, drivers, supports, connectors, terminations, switching accessories and other necessary accessories, complete in all respects. | %No | |||
| 317 | 317 | 18W, 6" recessed LED downlight, 4000K, CRI ≥80, PF ≥0.90, complete with driver and accessories | %No | 48 | ||
| 318 | 318 | LED architectural/cove spot light, 7–10W, 3000/4000K, complete with driver and accessories | %No | 16 | ||
| 319 | 319 | LED strip light, 10–12W/m, 3000K, complete with diffuser, driver and accessories | %Rmtr. | 50 | ||
| 320 | 320 | 12W, 4–5" recessed LED downlight for covered pathways, 4000K | %No | 24 | ||
| 321 | 321 | LED downward/pathway light, 5–7W, IP65, 3000K, complete with accessories | %No | 16 | ||
| 322 | 322 | LED emergency light, minimum 3-hour battery backup | %No | 8 | ||
| 323 | 323 | LED illuminated exit sign, complete with battery backup and accessories | %No | 4 | ||
| 324 | 324 | CEILING FANS Supply, installation, testing and commissioning of ceiling fan installation including ceiling fans, regulators/controllers, suspension rods, canopies, supports, wiring connections and all necessary accessories, complete in all respects. | %No | |||
| 325 | 325 | 56" ceiling fan, 230V, approximately 70–90W, complete with regulator/controller, suspension rod, canopy and accessories | %No | 32 | ||
| 326 | 326 | WASHROOM ELECTRICAL INSTALLATION Supply, installation, testing and commissioning of complete electrical installation for washrooms including lighting, exhaust fans, geyser power points, isolators, wiring, conduits, switches, protective devices and all necessary accessories, complete in all respects. | %No | |||
| 327 | 327 | 12–15W LED recessed/surface-mounted washroom light, 4000K | %No | 6 | ||
| 328 | 328 | 8–10" exhaust fan, 230V | %No | 6 | ||
| 329 | 329 | SECTION - G PA-SYSTEM Supply, installation, testing and commissioning of complete 100V line public address and mosque sound system comprising indoor ceiling speakers, outdoor weatherproof horn speakers for Azan, mixer amplifier, microphones, speaker cabling, zone controls, equipment rack and all required accessories, including wiring, termination, testing and commissioning, complete in all respects. | %No | |||
| 330 | 330 | 100V line ceiling speaker, 6–8", approximately 10W, suitable for indoor mosque PA system | %No | 12 | ||
| 331 | 331 | 100V line outdoor horn speaker, 15/20W, weatherproof IP65 or better, complete with bracket | %No | 4 | ||
| 332 | 332 | 240W, 100V line mixer amplifier, with microphone/auxiliary inputs and minimum 3-zone arrangement | %No | 1 | ||
| 333 | 333 | Wired microphone for Imam/Khateeb | %No | 1 | ||
| 334 | 334 | Wireless handheld microphone system | %No | 1 | ||
| 335 | 335 | PA speaker cable, 2C × 1.5 mm² Cu, including conduit and accessories | %Rmtr. | 480 | ||
| 336 | 336 | Audio/microphone cable including conduit and accessories | %Rmtr. | 30 | ||
| 337 | 337 | 9U wall-mounted equipment rack | %No | 1 | ||
| 338 | 338 | Rack-mounted PDU | %No | 1 | ||
| 339 | 339 | 1 kVA UPS with standard short-duration backup for PA equipment | %No | 1 | ||
| 340 | 340 | SECTION - H EARTHING / GROUNDING SYSTEM Supply, installation, testing and commissioning of following items for Earthing / Grounding System of other systems including all material, boring, labor, tools, transportation, accessories etc. Complete in all respects with detailed test reports. | %No | |||
| 341 | 341 | Chemical Enhanced Earth using 17.2 mm dia 3m copper cladded rod including 4" dia, 11' deep boring and back filled with chemical to enhance conductivity. Complete with termination clamps, and heavy duty Earthing Pit with cover as per details given in drawings. (GCEM Chemical to be Used) | %No | 1 | ||
| 342 | 342 | Earth Connecting Point (ECP) or Equipotential bar made with 200 mm wide, 50mm high and 5mm thick tin plated Copper, as shown in drawings. Bar shall be provided with holes suitable for installation of 4 No. 70 sqmm bare copper conductor. Note: ECP shall be enclosed in appropriate size of powder coated metal enclosure with front accessible cover. | %No | 2 | ||
| 343 | 343 | Stranded bare copper conductors of following sizes in appropriate size of PVC/UPVC conduit laid in floor/raft from Earth Station to ECP to as shown in drawings. Complete in all respects including termination at ECP. | %No | |||
| 344 | 344 | 1C, 70 Sq.mm Bare Copper Conductor | %Rm. | 50 | ||
| 345 | 345 | Supply, installation, testing and commissioning of following size of Single core PVC Cables from ECP to several equipments as per details given in schematic drawings, including all material, labor, tools, transportation, accessories etc. Complete in all respects with detailed test reports. | %No | |||
| 346 | 346 | 1C, 70 Sq.mm Cu/PVC (Green) | %Rm. | 30 | ||
| 347 | 347 | 1C, 16 Sq.mm Cu/PVC (Green) | %Rm. | 30 | ||
| 348 | 348 | HVAC-75 TONNAGE CAPACITY | %No | |||
| 349 | 349 | Supply, installation, testing and commissioning of complete VRF Air Conditioning System, comprising all outdoor and indoor units (cassette, ducted and fresh air units), refrigerant copper piping with closed-cell insulation, Y-branches, isolation valves, additional refrigerant charging, factory-fabricated G.I. ducting with insulation, supply/return air grilles, diffusers, jet nozzles, fresh air louvers, UPVC condensate drain piping with insulation, cable trays, control wiring, flexible duct connectors, hangers, supports, accessories, fittings and all associated mechanical, electrical and control works. The scope shall include fabrication, fixing, alignment, supports, sealing, testing, balancing, commissioning, shop drawings, as-built drawings and all labor, materials, equipment, tools and incidentals required to complete the HVAC system in all respects as per approved drawings, project specifications, manufacturer's recommendations and the Engineer's instructions. | %JOB | 1 | ||
| 350 | TOTAL AMOUNT | 480000000 | ||||
| GRAND TOTAL: | Rs 480,000,000.00 |
The project shall comprise the following major components:
a. Construction of state-of-the-art Pre-Engineered Steel Building (PEB) structures and allied civil works for:
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
Red Book:
© FIDIC 2017. All rights reserved.
The Conditions of Contract are the “General Conditions” which form part of the “Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer (“Red book”) Second edition 2017” published by the Federation Internationale Des Ingenieurs – Conseils (FIDIC) and the following “Particular Conditions” which shall complement the General Conditions of the Contract.
The successful Bidder, upon contract award, shall be required to furnish two (02) copies of aforementioned “General Conditions” for incorporation in the Works Contract.
International Federation of Consulting Engineers (FIDIC) FIDIC
Bookshop – Box- 311 – CH – 1215 Geneva 15, Switzerland
Fax: +41 22 799 49 054
Telephone: +41 22 568 0500
E-mail: fidic@fidic.org
Website: www.fidic.org
FIDIC code: ISBN13: 978-2-88432-084-9
Particular Conditions
(Mandatory Provisions not to be amended/substituted)
The Particular Conditions (PCC) complement the General Conditions (GCC) to specify dates, contractual requirements, and special circumstances related to the Works. The PCC consists of two parts, Part A - Contract Data and Part B - Special Provisions. The provisions to be found in the Special Provisions (Particular Conditions - Part B) take precedence over the equivalent provisions found under the same Sub-Clause number(s) in the General Conditions, and the provisions of the Contract Data (Particular Conditions - Part A) take precedence over the Special Provisions (Particular Conditions - Part B).
Sub-Clause 1.1.27
Defects Notification Period (DNP): 365 Days
Sub-Clause 1.1.31
Employer's name & address: NDMA (National Disaster Management Authority (NDMA)), Director Near ITP Office, Main Murree Road, Islamabad Capital Territory
Sub-Clause 1.1.35
Engineer's name & address: Junaid Khalid
NDMA HQ Islamabad
Sub-Clause 1.1.84
Time for Completion: 60 days for whole of the works
Sub-Clause 1.3 (a)(ii)
Agreed method of electronic transmission: Not Agreed
Sub-Clause 1.3 (d)
Address of Empoyer for Communications: Near ITP Office, Main Murree Road, Islamabad Capital Territory
Address of Engineer for Communications:
NDMA HQ Islamabad
Sub-Clause 1.4
Contract shall be governed by the law of: Islamic Republic of Pakistan
Ruling language: English
Language for communications: English
Sub-Clause 2.1
After receiving the Letter of Acceptance, the Contractor shall be given right of access to all or part of the Site within: 5 days after Commencement Date
Sub-Clause 2.4
Employer’s financial arrangements:
NDMF
Sub-Clause 3.2 (e)(ii)
Engineer’s Duties and Authority: Variation resulting in an increase of the Accepted Contract Amount in excess ofone percent (1%)subject to accumulative Variations not exceeding five percent (5%)of the Accepted Contract Amount
Sub-Clause 4.2
Performance Security (as percentage of the Accepted Contract Amount in Currencies): 0%
Form of Performance Guarantee: Nil
Sub-Clause 4.2.1
List of Insurance Companies:
Any A+/AA rating insurance companies
Sub-Clause 4.7.2
period for notification of errors in the items of reference: Twenty Eight (28) days
Sub-Clause 4.19
Period of payment for temporary utilities: Each Month
Sub-Clause 5.1 (a)
Maximum allowable accumulated value of work subcontracted (as a percentage of the Accepted Contract Amount): Nil %
Sub-Clause 5.1 (b)
Parts of the Works for which subcontracting is not permitted: Nil
Sub-Clause 6.5
Normal working hours on the Site: 12
Sub-Clause 8.3
Number of additional paper copies of programmes: 1
Sub-Clause 8.8 & 14.15(b)
Delay Damages payable for each day of delay 0.20% of the Accepted Contract Amountfor delay in completion of whole of the Works
Sub-Clause 8.8
Maximum amount of Delay Damages 10.00 % of the Accepted Contract Amount
Sub-Clause 8.14
Applicability of Incentives for Early Completion No
Sub-Clause 12.3
Percentage profit (Not more than 10%): Nil
Sub-Clause 13.4.(b)(ii)
Percentage rate to be applied to Provisional Sums for overhead charges and profit: Twenty Five percent (25%)
Sub-Clause 14.2
Total Advance Payment: Fifteen percent (15%) of the Accepted Contract Amount excluding Provisional Sums payable in the currencies and proportions in which the Accepted Contract Amount is payable
Sub-Clause 14.2.1
Advance Payment Insurance Allowed
Sub-Clause 14.2.3
Percentage deductions for the repayment of the Advance Payment: Deduction shall be made at the amortization rate of 17.5 % of the value of the Works executed of each IPC as provided in paragraph (i) of Sub-Clause GCC 14.3, starting from 2nd IPC provided that the advance payment shall be completely repaid prior to the time when 90% of the Accepted Contract Amount less Provisional Sums has been certified for payment. It may be more than 17.5% in the last instalment to ensure full repayment.
Sub-Clause 14.3
Period of payment One Month
Sub-Clause 14.3(b)
Number of additional paper copies of Statements: 1
Sub-Clause 14.3 (iii)
Percentage of retention: Seven percent (7%)
Sub-Clause 14.3 (iii)
Limit of Retention Money (as a percentage of the Accepted Contract Amount): Five percent (5%)
Sub-Clause 14.5(b)(i)
Plant and Materials for payment when shipped: Plant and Materials under Bill of “Imported Plant and Materials”
Sub-Clause 14.5(c)(i)
Plant and Materials for payment when delivered to the Site: Plant and Non Perishable Materials
Sub-Clause 14.6.2
Minimum amount of Interim Payment Certificate (IPC): Yes
The Minimum Amount IPC is 20000000
[Employer to give value not exceeding one fifth of the average expected value of Interim Payment Certificate]
Sub-Clause 14.7(a)
Period of payment of Advance Payment to the Contractor: 14 days
Sub-Clause 14.7b(i)
Period for the Employer to make interim payments to the Contractor under Sub-Clause 14.6: 28 days
Sub-Clause 14.7b(ii)
Period for the Employer to make interim payments to the Contractor under Sub-Clause 14.13 (Final Payment): 28 days
Sub-Clause 14.7(c)
Period for the Employer to make final payment to the Contractor: 30 days
Sub-Clause 14.8
Financing charges for delayed payment Local Currency (PKR):
6-Month KIBOR (Offer) +3% per annum.
Foreign Currency:
USD
6-Month SOFR (Secured Overnight Financing Rate for USD) +1% per annum.
EURO
6-Month EURIBOR (EURO Interbank Offered Rate for EURO) +1% per annum.
Others
Appropriate rates +1% (for other foreign currencies, Ref. Schedule-A, A-4 to Bid).
Sub-Clause 14.11.1(b)
Number of additional paper copies of draft Final Statements: 1
[insert number of copies say six (06)]
Sub-Clause 14.15
Currencies of payment of Contract Price: as stated in the Table Schedule of Adjustment Data of Schedule A (if Given)
Sub-Clause 14.15(a)(i)
Proportions or amounts of Local and Foreign currencies: as stated in the Table Schedule of Adjustment Data of Schedule A (if Given)
Sub-Clause 14.15(c)
Currencies and proportions for payment of Delay Damages: as stated in the Table Schedule of Adjustment Data of Schedule A (if Given)
Sub-Clause 14.15(f)
rates of exchange: as stated in the Table IV of Schedule A (If Given)
Sub-Clause 17.2(d)
Forces of nature, the risks of which are allocated to the Contractor: Nil
Sub-Clause 19.1
Permitted deductible limits:
i) insurance required for the Works: Ten percent (10%) of loss amount on each & every loss
ii) insurance required for Goods: Nil
iii) insurance required for liability for breach of professional duty: Nil
iv) insurance required against liability for fitness for purpose (if any is required): Nil
v) insurance required for injury to persons and damage to property: Nil
vi) insurance required for injury to employees: Nil
vii) other insurances required by Laws and by local practice : Nil
Periods for submission of insurance:
a) evidence of insurance: Not later than the Commencement Date
b) relevant policies: Within twenty eight (28) day from the Commencement Date
Sub-Clause 19.2.1(b)
Additional amount to be insured (as a percentage of the replacement value): 15% of the replacement value (Accepted Contract Amount)
Sub-Clause 19.2.2
Extent of insurance required for Goods: From Ex-Works (i.e., works, factory, warehouse, etc) to delivery at the Site
Amount of insurance required for Goods: Full replacement value
Sub-Clause 19.2.3(a)
Amount of insurance required for liability for breach of professional duty: Full replacement value of the Works to be designed by the Contractor
Sub-Clause 19.2.3(b)
Insurance required against liability for fitness for purpose: Yes
Sub-Clause 19.2.3
Period of insurance required for liability for breach of professional duty: Until the date of issuance of Performance Certificate
Sub-Clause 19.2.4
Amount of insurance required for injury to persons and damage to property: Injury to person and Fatal case:
in accordance with Workmen Compensation Act
Damage to Property: The Amount of Insurance Required for Person Injury is 30000
The Amount of Insurance Required for Damage to Property is 100000 as per his assessment of the adjoining property(ies) other than the Works]
without limit to the number of incidents
Sub-Clause 19.2.6
Other insurances required by Laws and by local practice: All insurances as applicable, to the extent of execution of the project, under Federal and Provincial laws of Islamic Republic of Pakistan
Sub-Clause 21.1
Time for appointment of the DAAB: Within 28 days from the Commencement Date.
In case the Accepted Contract Amount is lesser than PKR one (01) billion, appointment of the DAAB shall be made when Dispute arises between the Parties.
Sub-Clause 21.1
The DAAB shall comprise 1
[insert either “a sole Member” or “Three Members”]
[For a Contract estimated to cost above PKR 2.5billion, the DAAB shall comprise of three members. For a Contract estimated to cost between PKR1billion and PKR2.5billion, the DAAB may comprise of three members or a sole member. For a Contract estimated to cost less than PKR1billion, a sole member is recommended.]
Sub-Clause 21.1
List of proposed members of DAAB
- proposed by Employer
Atif Majeed
Sub-Clause 21.2
Appointing entity (official) for DAAB members Managing Director Public Procurement Regulatory Authority (PPRA) or Chairman Pakistan Engineering Council (PEC) from the list of PEC approved arbitrators published at its website
Sub-Clause 21.6
Rules of Arbitration: PEC Rules of Conciliation and Arbitration or Pakistan Arbitration Act of 1940, if the former is inactive.
The place of Arbitration shall be in the Employer’s country: Pakistan
[Insert name of city]
PartB - Special Provisions
1.1 Definitions
1.1.76 “Specification”
Following is added at the end:
“and consists of two parts i.e.,
i) “Part A - Specific Provisions”; and
ii) “Part B - Technical Provisions”.”
1.2 Interpretation
“and” is deleted from the end of sub-paragraph (i) and added at the end of sub-paragraph (j).
Sub-paragraph (k) is added:
“(k) The word “tender” is synonymous with “bid” the word tenderer with “bidder”, the words “tender documents” with “bidding documents” and “Schedule of Prices” with “Bill of Quantities”, as applicable.”
1.5 Priority of Documents The documents listed at (a) through (k) of this Sub-Clause are deleted and substituted with the following:
(a) the Contract Agreement;
(b) the Letter of Acceptance;
(c) the Letter of Bid;
(d) the Particular Conditions Part A - Contract Data;
(e) the Particular Conditions Part B - SpecialProvisions;
(f) the General Conditions;
(g) the Specification Part A - SpecificProvisions;
(h) the Specification Part B- Technical Provisions;
(i) the Drawings;
(j) the completed Schedules to Bid includingBillof Quantities;
(k) the JV Undertaking (if the Contractor is a JV); and
(l) any other documents forming part of the Contract.
The addenda/corrigenda, if any, shall be deemed to have been incorporated at the appropriate places in the documents forming the Contract.
1.6 Contract Agreement
In the last line of the 1st paragraph the text “shall be borne by the Employer” is substituted by “shall be reimbursed by the Employer to the Contractor”.
3.1 The Engineer
In sub-paragraph (a) the text “as defined in the Pakistan Engineering Council Act, 1975 (Act No.V of 1976)” are added after the words “professional engineer”.
3.2 Engineer’s Duties and Authority
The Engineer shall obtain the consent in writing of the Employer before taking action under the following Sub-Clauses of these Conditions:
(a) Consenting to the subcontracting of any part of the Works under Sub-Clause 5.1 [Subcontractors]
(b) Any action under Sub-Clauses 8.9 [Employer’s Suspension] and 8.12 [Prolonged Suspension]
(c) Issuance of “Taking Over Certificate” under Sub-Clause 10.1 [Taking Over the Works and Sections].
(d) Issuing the “Performance Certificate” under Sub-Clause 11.9 [Performance Certificate].
(e) Sub-Clause 13.1 [Right to Vary]: instructing a Variation, except;
(i) in an emergency situation as determined by the Engineer, or
(ii) if such a Variation would increase the Accepted Contract Amount by less than the percentage specified in the Contract Data.
(f) Sub-Clause 13.3 [Variation Procedure]: approving a proposal for Variation submitted by the Contractor in accordance with Sub-Clause 13.3.2 [Variation by Request for Proposal] or 13.2 [Value Engineering].
(g) Certifying release of second half of the Retention Money under Sub-Clause 14.9 [Release of Retention Money].
(h) Issuing Final Payment Certificate under Sub-Clause 14.13 [Issue of FPC].
(i)
*[insert Sub-Clause number (not Sub-Clause 3.7 [Agreement or Determination]
Any such requirement shall not be applied to any action by the Engineer under Sub-Clause 3.7 [Agreement or Determination], as stated in Sub-Clause 3.2 [Engineer’s Duties and Authority] of the General Conditions.
Notwithstanding the obligation, as set out above, to obtain approval, if, in the opinion of the Engineer, an emergency occurs affecting the safety of life or of the Works or of adjoining property, he may, without relieving the Contractor of any of his duties and responsibility under the Contract, instruct the Contractor to execute all such work or to do all such things as may, in the opinion of the Engineer, be necessary to abate or reduce the risk. The Contractor shall forthwith comply, despite the absence of approval of the Employer, with any such instruction of the Engineer. The Engineer shall determine an addition to the Contract Price, in respect of such instruction, in accordance with Clause 13 and shall notify the Contractor accordingly, with a copy to the Employer.
Following is added after the words “the Employer’s consent is required” in 4th paragraph:
“stating that the Employer’s consent has been obtained for that specified authority”
4.2 Performance Security
4.2.1 Contractor’s Obligations
The entity issuing the Performance Security and its form shall be as under:
The Performance Security shall be, at the option of the Contractor,issuedin the prescribed form included in the Bidding Documents,by(a) a Scheduled Bank in Pakistan or (b) a foreign bank duly counter-guaranteed by a Scheduled Bank in Pakistan or (c)an Insurance Companylisted in the Contract Data and rated by PACRA/VIS ofratingas provided in Table below:
Accepted Contract Amount (In Eq. PKR million) Minimum Rating of Insurance Companies
Up to 1000 A (+)
1001 to no limit AA
In case of Joint Venture, the Performance Security shall be in the name of the Joint Venture or in the name of Lead/either firm of the JV or in ratio of shares of the individual JV partners.
Following paragraph is added at the end of this Sub-Clause:
“The amount of Performance Security shall be reducedto 50%following issue of the Taking-Over Certificate for the whole of the Works under Clause 10 of Conditions of Contract.”
4.3 Contractor’s Representative
In second paragraphthe text “professional engineer as defined in the Pakistan Engineering Council Act, 1975 (Act No. V of 1976) (having temporary licence in case of foreign engineer under Section 12 of the Pakistan Engineering Council Act, 1975 (Act No. V of 1976)” are added after the words “qualified, experienced”.
In the 3rd paragraph the words “28 days” are substituted by “14 days”. In 2nd line of 4thparagraph the text “or appoint a replacement” is substituted by “except appointment of a suitable temporary replacement is deployed at the Site”
4.4 Contractor’s Documents
4.4.2 As-Built Records
First paragraph is deleted and the text in the last paragraph is substituted with the following:
“The Contractor shall furnish to the Engineer 6 copies, one reproducible and one electronic copy(provided the Engineer has made available to the Contractor editable form of the Drawings)of all Drawings amended to conform to the Works as built.In case the Engineer does not make available to the Contractor editable form of the Drawings, the Contractor shall furnish to the Engineer as-built data for incorporation in the Drawings. Upon receipt of PDF versions of the as-built drawings prepared by the Engineer, the Contractor shall furnish to the Engineer 6copies and one reproducible of these Drawings.
The price of such Drawings shall be deemed to be included in the Contract Price.”
Following Sub-Clause is added:
4.4.4 ShopDrawings
The Contractor shall submit to the Engineer for review 3 copies of all shop and erection drawings applicable to this Contract as per provision of relevant Sub-Clause of the Contract.
Review and approval by the Engineer shall not exceed 21 days and be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory and the Engineer’s review or approval shall not relieve the Contractor of any of his responsibilities under the Contract.
4.8 Health and Safety Obligations
The following text is added at the end ofthis Sub-Clause:
In the event of work being carried out outside the normal working hours and in the event of work being carried out at night, the Contractor shall at his own cost, provide and maintain such good and sufficient light as will enable the work to proceed satisfactorily and without danger. The approaches to the Site and the Works where the night work is being carried out shall be sufficiently lighted. All arrangement adopted for such lighting shall be to the satisfaction of the Engineer.
4.20 Progress Reports
At the end of sub-paragraph (g) the word “and” is deleted and at the end of sub-paragraph (h) the full stop (.) is replaced with “;”, and the following new sub-paragraphs are added as:
(i) planned programme for the execution of the Works for next 56 days to enable the Engineer to determine its programme of inspection and testing;
(j) monthly summery of daily job record indicating weather conditions, deployment of Contractor’s Equipment, labour employment, local material procurement and material import, if any; and
(k) salient contractual and project information.
5.1 Subcontractors
Add the following text at the end of paragraph (ii):
“underSchedule to Bid”
The following is added at the end of the last paragraph of Sub-Clause 5.1:
“All subcontracts relating to the Works shall include provisions which entitle the Employer to require the subcontract to be assigned to the Employer under sub-paragraph (a) of Sub-Clause 15.2.3 [After Termination].
The Contractor shall give reasonable opportunity to contractors from Islamic Republic of Pakistan for subcontracts for the Works, and endeavour to employ such contractors as Subcontractors.”
5.2 Nominated Subcontractors
5.2.2 Objection to Nomination
In sub-paragraph (c), “and” is deleted from the end of (i);
“.” at the end of (ii) is replaced with: “, and”.
The following is then added as (iii):
“(iii) be paid only if and when the Contractor has received from the Employer payments for sums due under the Subcontract referred to under Sub-Clause 5.2.3 [Payment to nominated Subcontractors].”
6.1 Engagement of Staff and Labour
The following paragraph is added at the end of the Sub-Clause:
“The Contractor shall, to the extent practicable and reasonable, employ staff (not less than 50%) and labour (not less than 85%) with appropriate qualifications and experience from sources within the Islamic Republic of Pakistan.”
6.7 Health and Safety of Personnel
The existing text is substituted with the following:
“In order to provide for the safety, health and welfare of persons, and for prevention of damage of any kind, all operations for the purposes of or in connection with the Contract shall be carried out in compliance with the Safety Requirements of the Government of Pakistan with such modifications thereto as the Engineer may authorize or direct and the Contractor shall take or cause to be taken such further measures and comply with such further requirements as the Engineer may determine to be reasonably necessary for such purpose. The Contractor shall also provide all other medical services and appoint a health and safety officer at Site if stated in the Specifications. In case of any fatality or serious accident, the Contractor shall, in addition, notify the Engineer immediately by the quickest available means.”
6.8 Contractor’s Superintendence
Insert at the end of sub-paragraph (a) of this Sub-Clause:
"or, if not, the Contractor shall make competent interpreters available during all working hours, in a number sufficient for those persons to properly perform their superintendence duties"
The following text is added at the end of this Sub-Clause:
“The Contractor’s authorized representative and his other engineers working at site shall possess valid registration with the Pakistan Engineering Council.
The Contractor’s authorized representative at Site shall be authorized to exercise adequate administrative and financial powers on behalf of the Contractor so as to achieve completion of the Works as per the Contract.”
6.12 Key Personnel
The following is inserted at the end of the last paragraph:
“If any of the Key Personnel are not fluent in this language, the Contractor shall make competent interpreters available during all working hours in a number deemed sufficient by the Engineer.”
The following Sub-Clauses 6.13 to 6.26 are added at the end of Sub-Clause 6.12:
6.13 Foreign Personnel
The Contractor may bring in to the Country any foreign personnel who are necessary for the execution of the Works to the extent allowed by the applicable Laws. The Contractor shall ensure that these personnel are provided with the required residence visas and work permits. The Employer will, if requested by the Contractor, use all reasonable endeavours in a timely and expeditious manner to assist the Contractor in obtaining any local, state, national, or government permission required for bringing in the Contractor’s personnel.
The Contractor shall be responsible for the return of these personnel to the place where they were recruited or to their domicile. In the event of the death in the Country of any of these personnel or members of their families, the Contractor shall similarly be responsible for making the appropriate arrangements for their return or burial.
6.14 Supply of Foodstuffs
The Contractor shall arrange for the provision of a sufficient supply of suitable food as may be stated in the Specification at reasonable prices for the Contractor’s Personnel for the purposes of or in connection with the Contract.
6.15 Supply of Water
The Contractor shall, having regard to local conditions, provide on the Site an adequate supply of drinking and other water for the use of the Contractor’s Personnel.
6.16 Measures against Insect and Pest Nuisance
The Contractor shall at all times take the necessary precautions to protect the Contractor’s Personnel employed on the Site from insect and pest nuisance, and to reduce the danger to their health. The Contractor shall comply with all the regulations of the local health authorities, including use of appropriate insecticide.
6.17 Alcoholic Liquor or Drugs
The Contractor shall not, otherwise than in accordance with the Laws of the Country, import, sell, give, barter or otherwise dispose of any alcoholic liquor or drugs, or permit or allow importation, sale, gift, barter or disposal thereto by Contractor’s Personnel.
6.18 Arms and Ammunition
The Contractor shall not give, barter, or otherwise dispose of, to any person, any arms or ammunition of any kind, or allow Contractor’s Personnel to do so.
6.19 Festivals and Religious Customs
The Contractor shall respect the Country’s recognized festivals, days of rest and religious or other customs.
6.20 Funeral Arrangements
The Contractor shall be responsible, to the extent required by local regulations, for making any funeral arrangements for any of its local employees who may die while engaged upon the Works.
6.21 Forced Labour
The Contractor, including its Subcontractors, shall not employ or engage forced labour which consists of any work or service, not voluntarily performed, that is exacted from an individual under threat of force or penalty, and includes any kind of involuntary or compulsory labour, such as indentured labour, bonded labour or similar labour-contracting arrangements.
6.22 Child Labour
The Contractor, including its Subcontractors, shall not employ or engage child labour in accordance with relevant law(s) in force in Islamic Republic of Pakistan.
6.23 Employment Records of Workers
The Contractor shall keep complete and accurate records of the employment of labour at the Site. The records shall include the names, ages, genders, hours worked and wages paid to all workers. These records shall be summarized on a monthly basis and submitted to the Engineer. These records shall be included in the details to be submitted by the Contractor under Sub-Clause 6.10 [Contractor’s Records].
6.24 Workers’ Organizations
The Contractor shall comply with the relevant labour laws of Pakistan which recognize workers’ rights to form and to join workers’ organizations/Trade Union of their choosing and to bargain collectively without interference.
6.25 Non-Discrimination and Equal Opportunity
The Contractor shall not make decisions relating to the employment or treatment of Contractor’s Personnel on the basis of personal characteristics unrelated to inherent job requirements. The Contractor shall base the employment of Contractor’s Personnel on the principle of equal opportunity and fair treatment, and shall not discriminate with respect to any aspects of the employment relationship, including recruitment and hiring, compensation (including wages and benefits), working conditions and terms of employment, access to training, job assignment, promotion, termination of employment or retirement, and disciplinary practices.
Special measures of protection or assistance to remedy past discrimination or selection for a particular job based on the inherent requirements of the job shall not be deemed discrimination. The Contractor shall provide protection and assistance as necessary to ensure nondiscrimination and equal opportunity, including for specific groups such as women, persons with disabilities, migrant workers and children (of working age in accordance with Sub-Clause 6.22).
6.26 Epidemics
In the event of any out-break of illness of epidemic nature, the Contractor shall comply with and carry out such regulations, orders and requirements as may be made by the Government or the local medical or sanitary authorities for the purpose of overcoming the same.
7.7 Ownership of Plant and Materials
The following is added before the first paragraph:
“Except as otherwise provided in the Contract,”
The following is added at the end of the Sub-Clause:
"No Plant and/or Materials that is the property of the Employer shallbe removed from the Site. If it becomes necessary to:
(i) remove any item of such Plant from the Site for the purposesof repair, the Contractor shall give a Notice, with reasons, tothe Engineer requesting consent to remove the defective ordamaged item off the Site. This Notice shall clearly identifythe item of defective or damaged Plant, and shall give detailsof: the defect or damage to be repaired; the place to whichdefective or damaged item of Plant is to be taken for repair;the transportation to be used (and insurance cover for suchtransportation); the proposed inspections and testing off theSite; and the planned duration required before the repaireditem of Plant shall be returned to the Site. The Contractorshall also provide any further details that the Employer mayreasonably require; or
(ii) replace any item(s) of such Plant and/or Materials, theContractor shall give a Notice, with reasons, to the Engineerclearly identifying the item(s) of Plant and/or Materials to bereplaced, and giving details of the due date of delivery tothe Site of the replacement item(s).
Where any item of Plant and/or Materials has become the propertyof the Employer under this Sub-Clause before it has been deliveredto the Site, the Contractor shall ensure that such an item is notmoved except for its delivery to the Site.
The Contractor shall indemnify and hold the Employer harmlessagainst and from the consequences of any defect in title orencumbrance or charge (except any reasonable restrictionarising from the intellectual property rights of the manufacturer orproducer) on any item of Plant and/or Materials that has becomethe property of the Employer under this Sub-Clause."
The following Sub-Clause7.9 is added after Sub Clause 7.8:
7.9 Use of Pakistani Materials and Services
The Contractor shall, so far as may be consistent with the Contract, make the maximum use of materials, supplies, plant and equipment indigenous to or produced or fabricated in Pakistan and services available in Pakistan provided such materials, supplies, plant, equipment and services shall be of required standard.
8.1 Commencement of Works
The following is added before the first paragraph:
“After signing of the Contract Agreement by both Parties,” and thereafter the word “The” is replaced with the word “the”.
8.5 Extension of Time for Completion
The following is added after paragraph (c):
“for last five years”.
The following Sub-Clause 8.14 is added after Sub-Clause 8.13:
8.14 Incentives For Early Completion
If Contract Data does not state applicability of incentives for early completion, this Sub-Clause shall not apply.
The Contractor shall be entitled subject to Sub-Clause 20.2 [Claims for Payment and/or EOT] to bonus payment if the Works and/or each Section is completed earlier than the Time for Completion for the Works or Section (as the case may be). The amount of bonus for early completion of the Works and/or each Section shall be upto a limit and at a rate to 50% of the relevant limit and rate of delay damages prescribed in Contract Data and shall be paid for every day which shall elapse between the relevant Date of Completion of the Works or Section and the relevant Time for Completion.
For the purposes of calculating any bonus payment, the applicableTime for Completion stated in the Contract Data is fixed and noadjustments of this time by reason of granting an EOT will beallowed.
The following Sub-Clause 11.12 is added after Sub-Clause 11.11:
11.12 Supervisory Assistance During DNP
If provided under the Schedule of Prices, the Contractor shall provide supervisory assistance to the Employer during the DNP for the Works. Such supervisory assistance shall be as described in the Specification for the purpose of supporting the Employer's operation and maintenance of the Plant for the period specified in the Schedule of Prices after the Date of Completion.
12.2 Method of Measurement
The following paragraph is added at the end of the Sub-Clause:
“Summary of measured quantity for payment shall be delineated item-wise under four headsnamely; “Schedule of Prices Quantity”, “Quantity Executed To-date”, “Quantity Certified Previously” and “Net Quantity Executed under this Certificate”.
12.3 Valuation of the Works
The following text is added at the end of fifth paragraph of the Sub-Clause:
“Sum of overhead charges and profit for sub-paragraph (a) shall be Twenty Five percent (25%)”.
13.4 Provisional Sums
The following paragraph is inserted as the penultimate paragraph:
“The Provisional Sum shall be used to cover the Employer’s share of the DAAB members’ fees and expenses, in accordance with Clause 21. No prior instruction of the Engineer shall be required with respect to the work of the DAAB. The Contractor shall submit the DAAB members’ invoices and the satisfactory evidence of having paid 100% of such invoices as part of the substantiation of those Statements submitted under Sub-Clause 14.3.
13.6 Adjustments for Changes in Laws
The following paragraphsare added at the end of the Sub-Clause:
“Notwithstanding the foregoing, the Contractor shall not be entitled to an extension of time if the relevant delay has already been taken into account in the determination of a previous extension of time and such Cost shall not be separately paid if the same shall already have been taken into account in the indexing of any inputs to the Table of Adjustment Data in accordance with the provisions of Sub-Clause 13.7 [Adjustments for Changes in Cost].”
14.1 The Contract Price
The following is added at the end of the Sub-Clause:
“Notwithstanding the provisions of subparagraph (b), Contractor's Equipment, including essential spare parts, imported by the Contractor for the sole purpose of executing the Contract shall be temporarily exempt from the payment of import duties and taxes upon initial importation, provided the Contractor shall post with the customs authorities at the port of entry an approved re-export bond or bank guarantee, valid until the Time for Completion plus six months, in an amount equal to the full import duties and taxes which would be payable on the assessed imported value of such Contractor's Equipment and spare parts, and callable in the event the Contractor's Equipment is not re-exported from the Country on completion of the Contract. A copy of the bond or bank guarantee endorsed by the customs authorities shall be provided by the Contractor to the Employer upon the importation of individual items of Contractor's Equipment and spare parts. Upon re-export of individual items of Contractor's Equipment or spare parts, or upon the completion of the Contract, the Contractor shall prepare, for approval by the customs authorities, an assessment of the residual value of the Contractor's Equipment and spare part to be re-exported, based on the depreciation scale(s) and other criteria used by the customs authorities for such purposes under the provisions of the applicable Laws. Import duties and taxes shall be due and payable to the customs authorities by the Contractor on (a) the difference between the initial imported value and the residual value of the Contractor's Equipment and spare parts to re-exported; and (b) on the initial imported value of the Contractor's Equipment and spare parts remaining in the Country after completion of the Contract. Upon payment of such dues within 28 days of being invoiced, the bond or bank guarantee shall be reduced or released accordingly; otherwise the security shall be called in the full amount remaining.”
[The Employer may change or delete this Sub-Clause as per Project requirements]
14.2 Advance Payment
14.2.1 Advance Payment Guarantee
The entity issuing the Advance PaymentGuaranteeand its form shall be as under:
The Advance PaymentGuarantee shall be in the form of Guarantee issued by (a) a Scheduled Bank in Pakistan or (b) a foreign bank duly counter-guaranteed by a Scheduled Bank in Pakistanor (c)an Insurance Companylisted in the Contract Data and rated by PACRA/VIS ofrating as provided in Table below:
Accepted Contract Amount (In Eq. million PKR) Minimum Rating of Insurance Companies
Up to 1000 A (+)
1001 to no limit AA
In case of Joint Venture, the Advance PaymentGuarantee(s)shall be in the name of the Joint Venture or in the name of Lead/either firm of the JV or in ratio of shares of the individual JV partners.
14.6 Issue of IPC
14.6.1 The IPC
In the first line of the 1st paragraph the words “28 days” are substituted by “14 days”.
14.7 Payment
The words “or through crossed cheque in favour of the Contractor or JV partners. The Payment to JV partners shall be made at the request of the Joint Ventures in the ratio of their shares specified by them” are added at the end of the Sub-Clause.
14.8 Delayed Payment
In the first paragraph, third line, the words “compounded monthly” are deleted.
The text of 2nd paragraph is deleted and substituted with the following:
“The Employer shall pay to the Contractor compensation at the rate stated in the Contract Data.”
14.9 Release of Retention Money
The following is added at the end of Sub-Clause 14.9:
“Unless otherwise stated in the Contract, when the Taking-Over Certificate has been issued for the Works and the first half of the Retention Money has been certified for payment by the Engineer, the Contractor shall be entitled to substitute a guarantee, in the form annexed to the Particular Conditions or in another form approved by the Employer and issued by a schedule bank selected by the Contractor, for the second half of the Retention Money. The Contractor shall ensure that the guarantee is in the amounts and currencies of the second half of the Retention Money and is valid and enforceable until the Contractor has executed and completed the Works and remedied any defects, as specified for the Performance Security. On receipt by the Employer of the required guarantee, the Engineer shall certify, and the Employer shall pay the second half of the Retention Money. The release of the second half of the Retention Money against a guarantee shall then be in lieu of the release after the latest of the expiry dates of the Defects Notification Periods. The Employer shall return the guarantee to the Contractor within 21 days after receiving a copy of the Performance Certificate.
If the Performance Security required under Sub-Clause 4.2 is in the form of a demand guarantee, and the amount guaranteed under them when the Taking-Over Certificate is issued is more than half of the Retention Money, then the Retention Money guarantee will not be required. If the amount guaranteed under the Performance Security when the Taking-Over Certificate is issued is less than half of the Retention Money, the Retention Money guarantee will only be required for the difference between half of the Retention Money and the amount guaranteed under the Performance Security.
15.2 Termination for Contractor’s Default
15.2.1 Notice
Following text is added at the end of sub-paragraph (h) of this Sub-Clause:
“For the purposes of this Contract, corrupt and fraudulent practices have been defined in Public Procurement Rules 2004.”
15.2.3 After Termination
The word “and” at the end of sub-paragraph (ii) of paragraph (b) is deleted the following paragraph is added after sub-paragraph (iii):
“(iv) all Employer-Supplied Materials and/or Employer's Equipment madeavailable to the Contractor in accordance with Sub-Clause 2.6 [Employer-Supplied Materials and Employer's Equipment], and”
15.4 Payment after Termination
The following text is added at the end of this Sub-Clause:
“The Employer shall be entitled to sell any of the Contractor’s Equipment, Temporary Works and unused materials and apply the proceeds of sale towards payment of any debt due from the Contractor to the Employer under this Clause including any outstanding payments to the Subcontractors.
16.2 Termination by Contractor
16.2.1 Notice
The sub-paragraph (j) is deleted in its entirety.
At the end of sub-paragraph (i) “; or” is replaced with “.” and at the end of sub-paragraph (h) “;” is replaced with “; or”.
In sub-paragraph (f) “84 days” are replaced with “180 days” and text “for reasons not attributable to the Contractor” is added at the end.
16.3 Contractor’s Obligations After Termination
Sub-paragraph (c) is deleted and replaced with:
"(c) deliver to the Engineer all Employer-Supplied Materials and/orEmployer's Equipment made available to the Contractor in accordance with Sub-Clause 2.6 [Employer-Supplied Materials and Employer’s Equipment]; and
(d) remove all other Goods from the Site, except as necessary for safety,and leave the Site."
17.1 Responsibility for Care of the Works
After the two instances of “Goods” in the last paragraph, the words “Employer-Supplied Materials and/orEmployer's Equipment” are added.
The following Sub-Clause 17.7 is added after Sub-Clause 17.6:
17.7 Use of Employer’s Accommodation/Facilities
The Contractor shall take full responsibility for the care of the items of the Employer’s facilities and/or accommodation, if any, as detailed in the Specification, from the date of use and/or occupation by the Contractor until the date on which such use and/or occupation is re-vested in the Employer.
If any loss or damage happens to any of the above items during a time while the Contractor is responsible for its care, arising from any cause other than a cause for which the Employer is responsible or liable, the Contractor shall promptly rectify the loss or damage at the Contractor’s risk and cost.
18.1 Exceptional Events
The words “or disorder” are replaced with “disorder or sabotage” in sub-paragraph (c) of the Clause.
18.4 Consequences of an Exceptional Event
The following is added at the end of sub-paragraph (b) after deleting the “.”:
“, including the costs of rectifying or replacing the Works and/or Goods damaged or destroyed by Exceptional Events, to the extent they are not indemnified through the insurance policy referred to in Sub-Clause 19.2 [Insurance to be provided by the Contractor].”
18.5 Optional Termination
In sub-paragraph (c), the words “and necessarily” areadded after the words “was reasonably”.
19.1 General Requirements
Following text is added at the end of first paragraph:
“The Contractor shall immediately after the date of the Letter of Acceptance submit the draft of insurance policies for the Employer’s consent.”
Following text is added at the end of third paragraph:
“The Contractor shall, within the respective periods stated in the Contract Data submit to the Engineer and the Employer a) evidence that the insurances described in this Clause have been effected, and b) copies of policies of the insurances described in Sub-Clauses 19.2.1, 19.2.4 and 19.2.5.”
19.2 Insurance to be provided by the Contractor
19.2.5 Injury to employees
The words “sickness, disease” are deleted in the third line of first paragraph.
The following Sub-Clause is added after Sub-Clause 19.2.6:
19.2.7 Insurance Company
“The Contractor shall be obliged to place all insurances described in this Clause with insurers listed in the Contract Data and rated byPACRA/VISofrating as provided in Table below:
Accepted Contract Amount (In Eq. million PKR) Minimum Rating of Insurance Companies
Up to 1000 A (+)
1001 to no limit AA
21.6 Arbitration
The word “international” is deleted in the sixth line of first paragraph. The text of sub-paragraph (a) is substituted with the following:
“the Dispute shall be finally settled under the Rules of Arbitration, specified in the Contract Data;”
The following Clauses are added after Clause 21
22 Custom Duty
[Employer may incorporate provisions where applicable. However, in order to make the bid more balanced, the payment of Customs Duties should be the responsibility of the Employer.]
23 Taxes
The Contractor, Subcontractors and their employees shall be liable to pay income tax, withholding tax, super tax and other taxes on income arising out of the Contract. The rates and prices as stated in the contract shall be deemed to cover all such taxes.
24 Integrity Part
If it is found and established at any stage that the Contractor or any of his Subcontractors, agents or servants have violated or involved in violation of the Integrity Pact signed by the Contractor then the Employer shall be entitled to :
(a) recover from the Contractor an amount equivalent to ten times the sum of any commission, gratification, bribe, finder’s fee or kickback given by the Contractor or any of his Subcontractors, agent or servants;
(b) terminate the Contract; and
(c) recover from the Contractor any loss or damage to the Employer as a result of such termination or of any other corrupt business practices of the Contractor or any of his Subcontractors, agent or servants.
The termination under sub-paragraph(b) of this Sub-Clause shall proceed in the manner prescribed under Sub-Clause 15.1 to 15.4 and the payment under Sub-Clause 15.4 shall be made after having deducted the amounts due to the Employer under sub-paragraph(a) and (c) of this Sub-Clause.
Appendix General Conditions of Dispute Avoidance/Adjudication Agreement
12 Disputes Under DAAB Agreement
In the first paragraph, third, fourth and fifth line, the text “under the Rules of Arbitration of the International Chamber of Commerce 2017……………shall apply” is substituted with “under the Arbitration Act 1940 by sole arbitrator appointed by the Managing Director Public Procurement Regulatory Authority or Chairman Pakistan Engineering Council.”
Date:
No.:
Alternative No.: P118789
To: NDMA (National Disaster Management Authority (NDMA)), Director Near ITP Office, Main Murree Road, Islamabad Capital Territory
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid-Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
(a) have withdrawn our Bid during the period of Bid validity specified in the Letter of Bid; or
(b) having been notified of the acceptance of our Bid by the Procuring agency/Employer during the period of Bid validity, (i) fail or refuse to sign the Contract; or (ii) fail or refuse to furnish the Performance Security (or guarantee), if required, in accordance with the ITB.
We understand this Bid Securing Declaration shall expire if we are not the successful Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight days after the expiration of our Bid.
Name of the Bidder*
Name of the person duly authorized to sign the Bid on behalf of the Bidder** _______
Title of the person signing the Bid ______________________
Signature of the person named above ______________________
Date signed ________________________________ day of ___________________, _____
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder attached to the Bid
[Note: In case of a Joint Venture, the Bid-Securing Declaration must be in the name of all members to the Joint Venture that submits the Bid.]
THIS CONTRACT AGREEMENT (hereinafter called the “Agreement”) made on the _________ day of __________ (month) 20_____ between NDMA (National Disaster Management Authority (NDMA)), Director Near ITP Office, Main Murree Road, Islamabad Capital Territory (hereinafter called the “Employer”) of the one part and __________________________________________________ (hereinafter called the “Contractor”) of the other part.
WHEREAS the Employer is desirous that certain Works, viz., Ext of NGT - Construction of Cafeteria and Mosque (P118789) should be executed by the Contractor and has accepted a Bid by the Contractor for the execution and completion of such Works and the remedying of any defects therein.
NOW this Agreement witnessed as follows:
1. In this Agreement words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents, in the order of priority, after incorporating addenda, if any, except those parts relating to Instructions to Bidders shall be deemed to form and be read and construed as part of this Agreement:
a) This Contract Agreement;
b) The Letter of Acceptance;
c) The Letter of Bid;
d) The Particular Conditions Part A - Contract Data;
e) The Particular Conditions Part B - SpecialProvisions;
f) The General Conditions;
g) The Specifications Part A - SpecificProvisions;
h) The Specifications Part B- Technical Provisions;
i) The Drawings;
j) The Completed Schedules to Bid including Schedule of Prices;
k) the JV Undertaking (if the Contractor is a JV); and
l) [Employer to insert any other documents forming part of the Contract]
The addenda/corrigenda,if any, (Excluding part relating to Instructions to Bidders alongwith Bidding Data) shall be deemed to have been incorporated at the appropriate places in the “Documents forming the Contract”.
3. In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the Contractor hereby covenants with the Employer to execute and complete the Works and remedy defects therein in conformity and in all respects with the provisions of the Contract.
4. The Employer hereby covenants to pay the Contractor, in consideration of the execution and completion of the Works as per provisions of the Contract, the Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the Contract.
IN WITNESS WHEREOF the parties hereto have caused this Agreement to be executed on the day, month and year first before written in accordance with their respective laws.
Signature of the Contactor Signature of Employer
(Seal) (Seal)
Signed, Sealed and Delivered in the presence of:
Witness Witness
(Name, Title and Address) (Name, Title and Address)
[All italicised text and any text within square brackets (except sub-clause headings) in this form of agreement is for use in preparing the form and should be deleted from the final product].
Name and details of the Contract Ext of NGT - Construction of Cafeteria and Mosque
______________________________________________________________________________
This Agreement made the ______day of ______ [month], _____ [year], between
Name and contact details of the Employer NDMA (National Disaster Management Authority (NDMA)), Director
Near ITP Office, Main Murree Road, Islamabad Capital Territory
+92-333-921-6192
latifndma@gmail.com
Name and contact details of the Contractor _____________________________________ (name)
____________________________________ (address)
__________________________________ (telephone)
___________________(email / other contact details);
Name and contact details of the DAAB Member _____________________________________ (name)
____________________________________ (address)
__________________________________ (telephone)
___________________(email / other contact details);
Whereas:
A. the Employer and the Contractor have entered (or intend to enter) into the Contract;
B. under the Contract, the “DAAB” or “Dispute Avoidance/Adjudication Board” means the sole member or three members (as stated in the Contract Data of the Contract) so named in the Contract, or appointed under Sub-Clause 21.1 [Constitution of the DAAB] or Sub-Clause 21.2 [Failure to Appoint DAAB Members] of the Conditions of Contract;
C. the Employer and the Contractor desire jointly to appoint the above-named DAAB Member to act on the DAAB as:
a. the sole member of the DAAB, and where this is the case, all references to the “Other Members” do not apply; or
b. one of three members / chairman [delete the one which is not applicable] of the DAAB and, where this is the case, the other two persons are:
____________________________ (name) _________________________ (name)
___________________________ (address) _______________________ (address)
_____________________________(telephone) ______________________(telephone)
______________(email/ other contact details) _______ (email/other contact details)
the “Other Members”; and
D. the DAAB Member accepts this appointment.
The Employer, Contractor and DAAB Member jointly agree as follows:
1. The conditions of this DAAB Agreement comprise:
(a) Clause 21 [Disputes and Arbitration] of the Conditions of Contract, and any other provisions of the Contract that are applicable to the DAAB’s Activities; and
(b) the “General Conditions of Dispute Avoidance/Adjudication Agreement”, which is appended to the General Conditions of the “Conditions of Contract for Construction” Second Edition 2017 published by FIDIC (“GCs”), as amended and/or added to by the following provisions.
2. [Details of amendments to the GCs, if any. For example:
In the procedural rules annexed to the GCs, Rule _ is deleted and replaced by: “ … “]
3. The DAAB Member shall be paid in accordance with Clause 9 of the GCs. The currency of payment shall be ________.
In respect of Sub-Clauses 9.1 and 9.2 of the GCs, the amounts of the DAAB Member’s monthly fee and daily fee shall be:
monthly fee___________________ per month, and
daily fee of____________________ per day
(or as otherwise set under Sub-Clause 9.3 of the GCs).
4. In consideration of the above fees, and other payments to be made to the DAAB Member in accordance with the GCs, the DAAB Member undertakes to act as DAAB Member in accordance with the terms of this DAAB Agreement.
5. The Employer and the Contractor shall be jointly and severally liable for the DAAB Member’s fees and other payments to be made to the DAAB Member in accordance with the GCs.
6. This DAAB Agreement shall be governed by the law of _____________ (if not stated, the law that governs the Contract under Sub-Clause 1.4 of the Conditions of Contract).
SIGNED by:_______________ SIGNED by:_______________ SIGNED by:_______________
Print name:_________________ Print name:_________________ DAAB Member
Title: _____________________ Title:______________________ Title:______________________
for and on behalf of the
Employer for and on behalf of the
Contractor
in the presence of in the presence of in the presence of
Witness:___________________ Witness:___________________ Witness:___________________
Name:_____________________ Name:_____________________ Name:_____________________
Address:___________________ Address:___________________ Address:___________________
__________________________ __________________________ __________________________
Date:______________________ Date:______________________ Date:______________________
Guarantee No._________________________________________ Date _________________
WHEREAS _____________________________________ (hereinafter called the 'Employer')
has entered into a Contract for __________________________________________________
(Particulars of Contract)
with ____________________________________________ (hereinafter called the "Contractor').
AND WHEREAS, the Employer has agreed to advance to the Contractor, at the Contractor's request, an amount of Pak Rupees ___________________________________ (PKR _________ ) which amount shall be advanced to the Contractor as per provisions of the Contract.
AND WHEREAS, the Employer has asked the Contractor to furnish Guarantee to secure the mobilization advance for the performance of his obligations under the said Contract.
AND WHEREAS, ____________________________________________________________
(hereinafter called the “Guarantor”) at the request of the Contractor and in consideration of theEmployer agreeing to make the above advance to the Contractor, has agreed to furnish the said Guarantee.
NOW, THEREFORE, the Guarantor hereby guarantees that the Contractor shall use the advance for the purpose of above mentioned Contract and if he fails and commits default in fulfilment of any of his obligations for which the advance payment is made, the Guarantor shall be liable to the Employer for payment not exceeding the aforementioned amount.
Notice in writing of any default,on the part of the Contractor, of which the Employer at his discretion of making decision, shall be given by the Employer to the Guarantor, and on such first written demand, payment shall be made by the Guarantor of all sums then due under this Guarantee without any reference to the Contractor and without any objection.
This Guarantee shall remain in force until the advance is fully adjusted against payments from the Interim Payment Certificates of the Contractor or until _________________________whichever is earlier. (Date)
The Guarantor's liability under this Guarantee shall not in any case exceed the sum of
PKR ______________________ (PakRupees ________________________________________________).
This Guarantee shall remain valid up to the aforesaid date and shall be null and void after the aforesaid date or earlier if the advance made to the Contractor is fully adjusted against paymentsfrom Interim Payment Certificates of the Contractor provided that the Guarantor
agrees that the aforesaid period of validity shall be deemed to be extended if on the above mentioned date the advance payment is not fully adjusted.
Guarantor
(Scheduled Bank/ Insurance Company)
Signature ________________________________________________
Name ________________________________________________
Title ________________________________________________
WITNESS:
1. ________________________________________________
________________________________________________
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ________________________________________________
________________________________________________
Name, Title & Address
________________________________ [Guarantor letterhead or SWIFT identifier code]
Beneficiary: ___________________ [Insert name and Address of Employer]
Date: ________________[Insert date of issue]
RETENTION MONEY GUARANTEE No.: [Insert guarantee reference number]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that ________________ [insert name of Contractor, which in the case of a joint venture shall be the name of the joint venture] (hereinafter called "the Contractor") has entered into Contract No. _____________ [insert reference number of the contract] dated ____________ with the Employer, for the execution of _____________________ [insert name of contract and brief description of Works] (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, the Employer retains moneys up to the limit set forth in the Contract (“the Retention Money”), and that when the Taking-Over Certificate has been issued under the Contract and the first half of the Retention Money has been certified for payment, payment of [insert the second half of the Retention Money orifthe amount guaranteed under the Performance Guarantee when the Taking-Over Certificate is issued is less than half of the Retention Money, the difference between half of the Retention Money and the amount guaranteed under the Performance Security and, if required, the ES Performance Security] is to be made against a Retention Money guarantee.
At the request of the Applicant, we, as Guarantor, hereby irrevocably undertake to pay the Beneficiary any sum or sums not exceeding in total an amount of ___________ [insert amount in figures] () [amount in words] upon receipt by us of the Employer’s complying demand supported by the Beneficiary’s statement, whether in the demand itself or in a separate signed document accompanying or identifying the demand, stating that the Applicant is in breach of its obligation(s) under the Contract, without your needing to prove or show grounds for your demand or the sum specified therein.
A demand under this guarantee may be presented as from the presentation to the Guarantor of a certificate from the Employer’s bank stating that the second half of the Retention Money as referred to above has been credited to the contractor on its account number ___________ at _________________ [insert name and address of Contractor’s bank].
This guarantee shall expire no later than the …. day of ……, 2…, and any demand for payment under it must be received by us at the office indicated above on or before that date.
____________________
[signature(s)]
Note: All italicized text (including footnotes) is for use in preparing this form and shall be deleted from the final product.
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
Name of Employer: ……………… Name of Bidder/Contractor: ……………
Signature: …………………… Signature: …………………………….
[Seal] [Seal]
Guarantee No.___________________
Executed on ____________________
Expiry date _____________________
Name of Guarantor with address: _________________________________________________________________________________________________________________________________
Name of Principal (Contractor) with address:___________________________________________________________________________________________________________________________
Penal Sum of Security (express in words and figures) ____________________________________________________________________________________________________________________
Letter of Acceptance No. _____________________________________Dated __________________
KNOW ALL MEN BY THESE PRESENTS, that in pursuance of the terms of the Bidding Documents and above said Letter of Acceptance (hereinafter called the Documents) and at the request of the said Principal we, the Guarantor above named, are held and firmly bound unto the NDMA (National Disaster Management Authority (NDMA)), Director Near ITP Office, Main Murree Road, Islamabad Capital Territory (hereinafter called the Employer) in the penal sum of the amount stated above for the payment of which sum well and truly to be made to the said Employer, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has accepted the Employer's above said Letter of Acceptance for _____________________________________ ________________________________
(Name of Contract) for the Ext of NGT - Construction of Cafeteria and Mosque (P118789)
______________________________________________ (Name of Project).
NOW THEREFORE, if the Principal (Contractor) shall well and truly perform and fulfill all the undertakings, covenants, terms and conditions of the said Documents during the original terms of the said Documents and any extensions thereof that may be granted by the Employer, with or without notice to the Guarantor, which notice is, hereby, waived and shall also well and truly perform and fulfill all the undertakings, covenants terms and conditions of the Contract and of any and all modifications of said Documents that may hereafter be made, notice of which modifications to the Guarantor being hereby waived, then, this obligation to be void; otherwise to remain in full force and virtue till all requirements of Clause11, Defects After Taking Over, of Conditions of Contract are fulfilled.
Our total liability under this Guarantee is limited to the sum stated above and it is a condition of any liability attaching to us under this Guarantee that the claim for payment in writing shall be received by us within the validity period of this Guarantee, failing which we shall be discharged of our liability, if any, under this Guarantee.
We, _________________________________________________ (the Guarantor), waiving all objections and defense under the Contract, do hereby irrevocably and independently guarantee to pay to the Employer without delay upon the Employer's first written demand without cavil or arguments and without requiring the Employer to prove or to show grounds or reasons for such demand any sum or sums up to the amount stated above, against the Employer's written declaration that the Principal has refused or failed to perform the obligations under the Contract which payment will be effected by the Guarantor to Employer’s designated Bank & Account Number.
PROVIDED ALSO THAT the Employer shall decide, whether the Principal (Contractor) has duly performed his obligations under the Contract or has defaulted in fulfilling said obligations and the Guarantor shall pay without objection any sum or sums up to the amount stated above upon first written demand from the Employer forthwith and without any reference to the Principal or any other person.
IN WITNESS WHEREOF, the above-bounden Guarantor has executed this Instrument under its seal on the date indicated above, the name and corporate seal of the Guarantor being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
Guarantor
(Schedule Bank/ Insurance Company)
Signature: _________________________________________________
Name: _________________________________________________
Title: _________________________________________________
Corporate Guarantor (Seal)
WITNESS:
1.
_________________________________________________
_________________________________________________
2.
_________________________________________________
_________________________________________________
Name, Title & Address