In terms of Rule 48 of Public Procurement Rules, 2004, a Grievance Redressal Committee (GRC) is notified for the subject procurement and the notification copy is available on the procuring agency’s website and on the Authority’s website at (www.ppra.org.pk).
Works Directorate (Capital Development Authority), Deputy Director Works Division-I
Room No 26, Block No-III, CDA Main Secretariat, Sector G-7/4, Islamabad
+92-315-530-3631
ayazcda@yahoo.com
Sections of Prequalifica¬tion Documents
The following specific data for the Prequalification of Applicants shall complement, supplement, or amend the provisions in the Instructions to Applicants (ITA). Whenever there is a conflict, the provisions herein shall prevail over those in ITA.
| PDS Clause No. | ITA No. | Amendments of, and Supplements to, Clauses in the Instructions to Applicants |
A. General |
||
| 1. | 1.1 |
Identification Number of the Invitation for Prequalification: P119785 |
| 2. | 2.1 | The name of Procuring Agency is: Works Directorate (Capital Development Authority) The name of Project / Procurement is: Construction of New Islamabad Convention, Exhibition and Expo Centre, Islamabad |
| 3. | 4.2 | Maximum number of members in a Joint Venture (JV): 3 |
| 4. | 4.5 | A list of debarred firms and individuals is available on PPRA website: https://ppra.gov.pk |
B. Contents of the Prequalification Document |
||
| 5. | 7.1 | For clarification, the Applicant shall seek clarifications through: EPADS v2.0 |
| 6. | 7.1 & 8.2 | Information related to Prequalification shall be published on: EPADS v2.0 |
| 7. | 7.2 | Pre-Application Meeting: Clarification Date: Thursday, September 24, 2026 |
C. Preparation of Applications |
||
| 8. | 10.1 | This Prequalification Document has been issued in the language: English |
| 9. | 11.1(d) | Additional documents to be submitted through EPADS v2.0: No |
| 10. | 14.2 | Source for determining exchange rates: Not Applicable |
D. Submission of Applications |
||
| 11. | 16.1 | Deadline for Application Submission: Day: Friday Date: Friday, October 9, 2026 Time: 11:00 AM |
| 12. | 17.1 | Opening of Applications shall be conducted through: EPADS v2.0 Day: Friday Date: Friday, October 9, 2026 Time: 11:30 AM Virtual participation link: https://vendors.epads.gov.pk/ |
E. Procedures for Evaluation of Applications |
||
| 13. | 21.1 | Margin of Domestic Preference: Not Applicable (Applicable only if authorized in Procurement Plan) |
| 14. | 29.1 | Prequalification-related complaints / grievances shall be submitted in writing through: EPADS v2.0 A complaint may challenge:
|
| Bidder's Type | Required Registration |
|---|---|
|
Sole Proprietorship Partnership Firm Company (Private Limited) Company (Public Limited) State Owned Enterprise (Private Limited) State Owned Enterprise (Public Limited) |
NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) |
| Eligibility Criteria | Document |
|---|---|
| Duly licensed by the Pakistan Engineering Council (PEC) in the Category C-A and Relevant Specialization Codes CE-01, CE-02, CE-09, CE-10, , EE-01 to EE-06, EE11, ME-01, ME-02, ME-03, ME-04, BC-01, BC-03 & BC-04 The Bidder (Single Entity/ JV / Consortium) may fulfil all these specialized codes collectively. | Yes |
Quality Based Selection (QBS)
Weightage (Without Financial Criteria)
| Technical Evaluation % |
|---|
| 100 |
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 60 | |
| Specific Working Experience | ||
| Successfully Completed TWO (2) Construction Contracts of minimum value Rs.5.0 Billion or more (single Contract) in the last 10 years.
The bidder must upload Project Award Letter, Work Orders and Contract Agreement i/c completion Certificates.
The bidder must upload the joint venture agreement in case of projects is executed as a partner of joint venture clearly showing scope of works and percentage share of all partners of joint venture.
In case of foreign entity, the aforementioned documents and the translation of same in English language must be certified by the notary public or embassy of Pakistan in the country of foreign entity.
Note: In case the bidder is a Joint Venture, the working experience of all members combined shall be evaluated.
No marks in case the completed project is less than PKR 5 Billion. (Qualitative)(Doc Required) 02 Nos Completed Project (10) 01 No Completed Project (5) | 10 | |
| Successfully Completed Building project (RCC Structure) (Two Projects) of Contract value of PKR 5.0 Billion or more completed in the last 10-years.
The bidder must upload Project Award Letter, Work Orders and Contract Agreement i/c completion Certificates.
The bidder must upload the joint venture agreement in case of projects is executed as a partner of joint venture clearly showing scope of works and percentage share of all partners of joint venture.
In case of foreign entity, the aforementioned documents and the translation of same in English language must be certified by the notary public or embassy of Pakistan in the country of foreign entity.
Note: In case the bidder is a Joint Venture, the working experience of all members combined shall be evaluated.
No marks in case the completed project is less than PKR 5 Billion. (Qualitative)(Doc Required) 02 Nos Completed Project (20) 01 No Completed Project (10) | 20 | |
| One ongoing Building Projects of value PKR 5.0 Billion or above Note-1: In case the bidder is a Joint Venture, the working experience of all members combined shall be evaluated. In case the bidder is a Joint Venture, and one of the Joint Venture Members is a Foreign Company, the Foreign Company must independently meet the above requirements. If the Foreign Company cannot meet the requirement independently, the JV applicant shall be rendered ineligible. The bidder must upload Project Award Letter, Work Orders or Contract Agreement, and other documents necessary for confirming scope of works. The bidder must upload the joint venture agreement in case of projects is executed as a partner of joint venture clearly showing scope of works and percentage share of all partners of joint venture. In case of foreign entity, the aforementioned documents and the translation of same in English language must be certified by the notary public or embassy of Pakistan in the country of foreign entity. No marks in case of the ongoing work is less than PKR 5 Billion. (Qualitative)(Doc Required) | 10 | |
| Equipment Capabilities | ||
| Crane (02 Nos.) (Quantitative)(Doc Required) 02 nos. (4) 01 no. (2) | 4 | |
| Batching Plant (02 Nos.) (Qualitative)(Doc Required) 02 nos. (3) 01 no. (1) | 3 | |
| Transit Mixtures (04 Nos.) (Qualitative)(Doc Required) 04 nos. (2) 01 no. (1) | 2 | |
| Concrete Pump (Mobile) (02 Nos.) (Quantitative)(Doc Required) | 1 | |
| Scaffolding & Shuttering 50,000 Sft. (Quantitative)(Doc Required) | 3 | |
| Vibrators (05 Nos) (Quantitative)(Doc Required) | 1 | |
| Survey Equipment i/c Total Station (01 No.) (Quantitative)(Doc Required) | 1 | |
| Personal Capabilities | ||
| Project Manager (01 no.) MSc Civil with minimum 15yearsβ extensive experience of execution or design of Infrastructure, Building Works. (Quantitative)(Doc Required) | 3 | |
| Construction Managers (02 nos.) BSc Civil Engineering with minimum 15 yearsβ experience of execution of Infrastructure and Building Works. (Quantitative)(Doc Required) 02 Nos. (4) 01 No. (2) | 4 | |
| Mechanical Engineer (01 no.) BSc Mechanical Engineering with minimum 15 yearsβ experience of Infrastructure, Building Works. (Quantitative)(Doc Required) | 1 | |
| Electrical Engineer (02 Nos,) BSc Electrical Engineering with minimum 15 years experience of Infrastructure Building Works (Quantitative)(Doc Required) 02 Nos. (2) 01 No. (1) | 2 | |
| Interior Designer (01 No.) BE Architecture with minimum 10 yearsβ of Professional Experience of Interior Designing (Quantitative)(Doc Required) | 1 | |
| Contract Specialist (01 No.) BSc Civil Engineering with minimum 10 yearsβ experience in PEC/FIDIC based Contract (Quantitative)(Doc Required) | 1 | |
| Site Engineers (Civil) (02 Nos.) BSc Civil Engineering with minimum 8 yearsβ experience in Infrastructure & Building Works (Qualitative)(Doc Required) | 1 | |
| Site Engineers (E&M) (02 Nos. BSc Electrical Engineering with minimum 8 yearsβ field experience of Infrastructure & Building Works (Qualitative)(Doc Required) | 1 | |
| Site Surveyor (02 Nos.) DAE with 8 yearsβ field experience in Survey works including use of Total Station (Qualitative)(Doc Required) | 1 | |
| Financial Resources | ||
| Financial Resources (Working Capital + Contract/ Project Specific Bank Credit Line) The Joint Venture (must have
Financial Resources (Working Capital for last year + limit of Contract/Project Specific Bank Credit Line) of at least PKR 5.0
Billion or more. Note: In case the bidder is a Joint Venture, the financial resources of all members combined shall be
evaluated. (Quantitative)(Doc Required) Working Capital for last year + limit of Contract/Project Specific Bank Credit Line) are PKR 5.00 billion or more. (15) Working Capital for last year +limit of Contract/Project Specific Bank Credit Line) less than Rs. 5.00 Billion and more than Rs. 3.00 Billion (8) | 15 | |
| Average Annual Turnover in last 3 years, evaluated through the bidderβs, Audited financial statements for the last three (03) years. (Quantitative)(Doc Required) if the Average Annual Turnover for last three years is equal to or more than PKR 5.00 Billion (15) if the Average Annual Turnover for last three years is equal to or more than PKR 3.00 Billion but less than PKR 5.00 Billion (8) | 15 | |