In terms of Rules 48 of Public Procurement Rules, 2004 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager
State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
+92-300-937-6673
re.hyd@statelife.com.pk
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
|
BDS Clause Number |
ITB Number |
Amendments of, and Supplements to, Clauses in the Instruction to Bidders |
A. Introduction |
||
|
1 |
1.1 |
Name of Procuring Agency: State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)) The subject of procurement is: TENDER FOR UPGRADATION OF TOILET BLOCKS & PLUMBING SHAFT UNIT WORKS AT STATE LIFE BUILDING #3 THANDI SARAK HYDERABAD Expected commencement date: Thursday, December 3, 2026 |
|
2. |
2.1 |
Financial year for the operations of the Procuring Agency: 2026-27 Name and identification number of the Contract: P157800 |
| 3. | 3.1 | JV/Consortium or Association Allowed: No Number of JV/Consortium Members: Nil |
B. Bidding Documents |
||
|
4. |
6.2 & 6.4 |
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Saturday, October 31, 2026 |
| 5. | 7.2 |
Any addendum, in case issued, shall be published on State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)) website and on EPADS v2.0. |
C. Preparation of Bids |
||
| 6. |
8.1 |
List of documents required along with the bid: No |
| 7. | 9.1 |
The qualification criteria to establish the supply / production capability of the bidder. see Eligibility Criteria |
| 8. | 11.2 |
|
| 9. | 11.1 | Price schedule will be provided according to the format defined and acquired. see section price schedule. |
| 10. | 11.4 |
Specifications: see section of specifications. |
|
11. |
11.5 & 13.5 |
The price shall be Fixed. |
| 12. |
14.1 |
Currency of the Bids shall be : PKR |
| 13. |
16.1 |
The Bids/Bid Validity period shall be: 180 Days |
| 14. |
17.1 |
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6 |
| 15. | 17.2 |
The Bid Security shall be in the form of: Pay Order |
| 16. | 15.1 |
Alternative Bids to the requirements of the bidding documents will not be permitted. |
D. Submission of Bids |
||
|
17. |
18.1 & 21.1 |
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following; State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province). Bids that are not submitted on EPADS v2.0 shall be disqualified. The deadline for Bids submission is: Tuesday, November 3, 2026 11:00 AM |
E. Opening and Evaluation of Bids |
||
|
18. |
24.1 |
The Bids opening shall take place on EPADS v2.0. Day : Tuesday Date: November 03, 2026 Time : 11:30 AM |
|
19. |
30.2 |
Selection technique adopted will be: Least Cost Based Selection (LCBS) |
F. Award of Contract |
||
|
20. |
41.1 & 41.2 |
The Performance guarantee shall: 0%. The Performance Guarantee shall be acceptable in the form of: Nil |
| 21. | 45.1 |
Arbitrator shall be appointed by mutual consent of the both parties. |
G. Review of Procurement Decisions |
||
|
22. |
37 |
Grievance against this procurement shall be submitted online on EPADS v2.0. |
All Active Taxpayers shall be eligible to participate in the procurement process, unless expressly excluded or otherwise restricted under the Eligibility Criteria specified by the Procuring Agency.
| Required Registration |
|---|
| NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) PEC |
| Eligibility Criteria | Document |
|---|---|
| SRB REGISTRATION | Yes |
| a. Valid NTN registration. b. Valid SST / GST registration(As required) c. PEC registration in PEC-6 CIVIL or above category. d. Undertaking that participating firm / company is Not blacklisted by any of Provincial or Federal Government Department, Autonomous body or Private Sector Organization anywhere in Pakistan. | Yes |
Least Cost Based Selection (LCBS)
Weightage
| Technical Evaluation % |
|---|
| 100 |
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 60 | |
| Technical Evaluation Criteria | ||
| YEARS OF EXPERIENCE RELATED TO SUBJECT WORKS (PLEASE ATTACH EVIDENCE) • Up-to 4 years • 5 to 7 years • 8 to 10 years • 11 to 14 years • 15 years and more (Quantitative)(Doc Required) | 20 | |
| SIMILAR CONTRACT OF REPUTED/ RENOWNED FIRMS IN HAND (PLEASE ATTACH EVIDENCE) • Up-to 3 Contracts • 4 to 6 contracts • 7 to 9 contracts • More than 10 Contracts (Quantitative)(Doc Required) | 15 | |
| LIST OF CONTRACTS IN PROGRESS HAVINGVALUE ABOVE 1.0 MILLION (2.5 Marks each) (Quantitative)(Doc Required) | 10 | |
| TECHNICAL STAFF WITH RELATED EXPERIENCE RELATED TO THE DISCIPLINE Numbers of Staff: Up-to 3 3 to 5 >5 (Quantitative)(Doc Required) | 10 | |
| FINANCIAL STATUS OF THE FIRM The company should maintain minimum balance as follow at the last day of each month in their bank account during last two years • Up-to Rs. 01 million • 1 million to 3 million • >3 million or more (Quantitative)(Doc Required) | 15 | |
| TOTAL SIMILAR CONTRACTS EXECUTED BY THE FIRM DURING PAST 05 YEARS • 1 to 3 contractors • 4 to 10 contractors • 11 to 14 contractors • >15 contractors (Quantitative)(Doc Required) | 20 | |
| ISO 9000 CERTIFICATION FOR COMPNY (Quantitative)(Doc Required) | 5 | |
| ENLISTMENT WITH OTHERS FIRMS (01 MARKS/ ENLISTMENT (Quantitative)(Doc Required) | 5 | |
Lot Title : UPGRADATION OF TOILET BLOCKS & PLUMBING SHAFT UNIT WORKS AT STATE LIFE BUILDING #3 THANDI SARAK HYDERABAD
Bid Security : 200000 PKR
| Job | Delivery Schedule | Quantity |
|---|---|---|
| CIVIL WORKS |
Address: State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
Schedule: 80 Days
Quantity: 1/job
|
1/job |
| PLUMBING WORKS |
Address: State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
Schedule: 80 Days
Quantity: 1/job
|
1/job |
| ELECTRICAL WORKS |
Address: State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
Schedule: 80 Days
Quantity: 1/job
|
1/job |
No
Lot Title: UPGRADATION OF TOILET BLOCKS & PLUMBING SHAFT UNIT WORKS AT STATE LIFE BUILDING #3 THANDI SARAK HYDERABAD
Specifications / Requirements:
| Sr. No | Ref. No. | Description | Unit | Qty | Rate | Amount | |
|---|---|---|---|---|---|---|---|
| 1 | 1 | Dismantling, removing of existing hot & cold water supply lines including any structure as per site and as directed by the Engineer. Dismantled material shall be contractor's property | Rft | 833 | 89.25 | (Rupees Seventy four thousand three hundred forty five only) | 74345.25 |
| 2 | 2 | Dismantling, removing of existing hot & cold water supply lines including any structure as per site and as directed by the Engineer. Dismantled material shall be contractor's property | Rft | 1250 | 65.1 | (Rupees Eighty one thousand three hundred seventy five only) | 81375 |
| 3 | 3 | Dismantling, removing of existing firefighting water supply lines including any structure as per site and as directed by the Engineer. Dismantled material shall be contractor's property | Rft | 750 | 89.25 | (Rupees sixty six thousand nine hundred thirty eight only) | 66937.5 |
| 4 | 4 | Dismantling of Wooden shutters with frame of any thickness, tile floor including cleaning of floor/roof & Disposal of derbies Complete in all respect | SFT | 1428 | 52.5 | (Rupees Seventy four thousand nine hundred seventy only) | 74970 |
| 5 | 5 | Dismantling of existing clay bricks flooring at roof top floor as shown in the drawing/ as per site including disposal of surplus material and as directed by the Engineer. Dismantled material shall be contractor's property. | SFT | 5000 | 15.75 | (Rupees Seventy eight thousand seven hundred fifty only) | 78750 |
| 6 | 6 | Dismantling of existing stair case marble flooring & main entrance marble floor as shown in the drawing/ as per site including disposal of surplus material and as directed by the Engineer. Dismantled material shall be contractor's property. | SFT | 1250 | 63 | (Rupees Seventy eight thousand seven hundred fifty only) | 78750 |
| 7 | 7 | Dismantling and removal of existing exposed 6” diameter GI sewer pipes and associated shaft components, including safe disposal of debris. | Rft | 620 | 68.25 | (Rupees forty two lac three hundred fifteen only) | 42315 |
| 8 | 8 | Dismantling, removing of existing building lavatory blocks floor & wall tiles including disposal of debris materials to designated places/location as directed by the Engineer. All the dismantled materials shall be contractor's property and rate/price of dismantling work should include compensation of such items obtained by the Contractor from existing building. | Sft | 2626 | 442 | (Rupees One lac ten thousand two hundred ninety two only) | 110292 |
| 9 | 9 | Site Establishment and Safety Precautions, which includes mobilization, safety signage, barricading, access control, etc. | Job | 1 | 63000 | (Rupees Sixty three thousand only) | 63000 |
| 10 | 10 | Integration of Inspection Chambers in Shafts Constructing access chambers at floors or shaft locations for future maintenance. | No | 8 | 7875 | (Rupees Sixty three thousand only) | 63000 |
| 11 | 11 | Providing & fixing local Wall Tiles with border of floor tiles as including 1:4 rough plaster, stuck with base coat of approved Dry bond, grouting in matching color also includes removal of existing plaster etc. to accommodate new finishes, including all cuttings, grouting, and making all details complete in all respect as per drawings and Engineers instructions. | Sft | 5418 | 472.5 | (Rupees Two million five hundred sixty thousand and five only) | 2560005 |
| 12 | 12 | Providing/ Laying floor tiles for Washroom Flooring including 3" thick 1:4 cement sand mortar for surfacing, grouting with matching grout material of Stile, with proper slope of floor tiles towards floor trap, complete in all respect as per satisfaction of Engineer. Vendor has to arrange the required size floor tiles with laser cutting from supplier | Sft | 1344 | 336 | (Rupees Four lac fifty one thousand five hundred eighty four only) | 451584 |
| 13 | 13 | Waterproof Paint Application on Walls and Ceiling. Water-resistant emulsion will be used on internal surfaces of washrooms. | Sft | 1344 | 336 | (Rupees Three lac twenty four thousnd five hundred seventy six only) | 324576 |
| 14 | 14 | Retrofitting and Repair of Ceiling Surfaces. Chipping damaged plaster, drying, bonding, re-plastering and finishing ceiling surfaces | Sft | 640 | 262.5 | (Rupees One lac sixty eight thousand only) | 168000 |
| 15 | 15 | Supply, installation, Testing & Commissioning of PPR PN-20 cold/hot water pipes with molded fittings PN-25 as per DIN 16962, i/c pipe supports as indicated on the drawing, as per specifications & Engineers approval 32mm dia | Rft | 354 | 420 | (Rupees One lac sixty eight thousand only) | 148680 |
| 16 | 16 | Providing & fixing of brass (PPR coated) ball valves as indicated othe drawing & as specified in specifications 32 mm Dia | Nos | 8 | 5250 | (Rupees Fourty two thousand only) | 42000 |
| 17 | 17 | Providing, fixing, Testing & Commissioning of uPVC pipes & fittings as indicated on the drawing, as per specifications & Engineers approval & 6 dia | Rft | 254 | 577.5 | (RupeesOne lac fourty six thousand six hundred eighty five only) | 146685 |
| 18 | 18 | 4"DIA | Rft | 50 | 472.5 | (Rupees Twenty three thousand six hundred twenty five only) | 23625 |
| 19 | 19 | Providing and fixing European type ceramics ware coupled water closet, white / light color including 3 gallons cistern, P/s Trap, PVC flexible pipe connection, C.P tee stop cock with wall cups, "PORTA Brand" bacolite seat cover of best quality complete in all respect. | No | 16 | 31500 | (Rupees Five lac four thousand only) | 504000 |
| 20 | 20 | Providing and fitting Glazed earthen ware water closet, squatter type (Orissa pattern), combined with foot rest, Best Quality including ceramic Flushing tank Porta connected by concealed arrangement, tee stop cock for cistern water inlet and C.P connector with nuts and fitting, approved other ancillary material complete in all respect. | No | 24 | 13650 | (Rupees Three lac twenty seven thousand six hundred only) | 327600 |
| 21 | 21 | Installation of Wash Basins and Vanity Counters. Counters with stone/marble tops and basins with mixer taps. | No | 32 | 13650 | (Rupees Four lac thirty six thousand eight hundred only) | 436800 |
| 22 | 22 | Providing & fixing of PVC floor trap with multiple inlets & 4" dia outlet with S.S grating the approved design as per specifications | No | 32 | 1260 | (Rupees Fourty thousand three hundred twenty only) | 40320 |
| 23 | 23 | Provide and fix C.P Muslim Showers manufactured by Master/ Sonex orequivalent,complete with stop cock and controlled spray head. | No | 16 | 4200 | (Rupees Sixty seven thousand two hundred only) | 67200 |
| 24 | 24 | Replacement of Faucets and Taps (Manual + Sensor-based). Standard and sensor taps in selected locations | No | 100 | 3990 | (RupeesThree lac ninety nine thousand only) | 399000 |
| 25 | 25 | Installation of Water-Efficient Urinals with Optional Sensors. High-efficiency ceramic urinals with optional sensor flushing and partition panels. | No | 8 | 8925 | (Rupees Seventy one thousand four hundred only) | 71400 |
| 26 | 26 | Installation of Toilet Accessories. Soap dispensers, towel holders, tissue holders, grab bars, hooks, etc. | JOB | 16 | 36750 | (Rupees Five lac eighty eight thousand only) | 588000 |
| 27 | 27 | Supply, installation, testing, and commissioning of new 6” diameter uPVC sewer pipes, conforming to ASTM D3034 / ASTM F679 or equivalent approved ASTM standards for sewer applications. Re-routing of pipelines through designated internal ducts/shafts, including all required fittings, joints, supports, and access provisions. Construction of new shaft enclosures, including insulation, protective covering, surface finishing, and all incidental works necessary to complete the installation in accordance with specifications and to the satisfaction of the Engineer. | RFT | 620 | 651 | (Rupees Four lac three thousand six hundred twenty only) | 403620 |
| 28 | 28 | Circuit wiring from DB to switch board/dimmer including any wiring from switch board to switch board with 2x2.5 Sq.mm + ECC 1x2.5 Sqmm, 1-core PVC wires in 25mm dia of pvc conduit. | Nos | 3 | 13650 | (Rupees Fourty thousand nine hundred fifty only) | 40950 |
| 29 | 29 | Wiring for light point from switch board / Dimmer board to first light point with 1.5 Sq.mm common neutral of 1.5 Sq.mm and common ECC 1.5 Sq.mm + wires in 25mm dia exposed PVC conduit as shown on drawings. | Nos | 12 | 5565 | (RupeesSixty six thousand seven hundred eighty only) | 66780 |
| 30 | 30 | Same as above item but wiring from light point to point. Brand: Clipsal/Orange/Legrand Or Equivalent | Nos | 12 | 2940 | (Rupees thirty five thousand two hundred eighty only) | 35280 |
| 31 | 31 | Supply and installation of following 10 Amps, one-way gang type switches or 10/13/15/20 Amps socket outlets make including 16 SWG sheet steel back boxes recessed / surface on wall or as per design drawings. Brand: Clipsal/Orange/Legrand Or Equivalent | Nos | 16 | 4725 | (Rupees Seventy five thousand six hundred only) | 75600 |
| 32 | 32 | Supply Installation of the following lighting fixture complete with ballast, starter p.f.i capacitor and specified lamps.Supply of all the accessories required for the installation of Light Fixtures is included. Brand: Philips/Britlite/Fast/OSAKA Or Equivalent. | Nos | 16 | 4725 | (Rupees Seventy five thousand six hundred only) | 75600 |
| 33 | 33 | CEILING RECESSED / MOUNTED 45W LED 600MMX600MM PANEL LIGHT WITH CRI 90% COLOR TEMP 4000K/5000K OR AS | Nos | 64 | 11550 | (Rupees Seven lac thirty nine thousand two hundred only) | 739200 |
| 34 | 34 | SURFACE MOUNTED 12 W LED PACIFIC LIGHT WITH COLOR TEMP 4000K/5000K OR AS PER ARCHITECT. | Nos | 16 | 3675 | (Rupees Fifty eight thousand eight hundred only) | 58800 |
| 35 | 35 | Supply Installation Testing & Commissioning Exhaust Fan 12"x2" Complete in all respect GFC/PAK FAN/VOLDAM Or Equivalent | Nos | 16 | 7560 | (Rupees One lac twenty thousand nine hundred sixty only) | 120960 |
| GRAND TOTAL: | Rs 8,649,999.75 |
INSTRUCTIONS TO BIDDERS
A. GENERAL
IB.1 SCOPE OF BID
1.1 The Employer as defined in the Bidding Data hereinafter called “the Employer” wishes to receive bids for the works as described in these Bidding Documents, and summarized in the Bidding Data hereinafter referred to as the “Works”.
IB.2 SOURCE OF FUNDS
2.1 The Employer has arranged funds from its own sources.
IB.3 ELIGIBLE BIDDERS / MANDATORY REQUIREMENTS
3.1 This Invitation for Bids is open to all bidders meeting the following Mandatory requirements:
3.2 In case any of the mandatory documents mentioned above is not fulfilled by the bidder, their bid will be rejected. If at the time of submission of bid, the renewal of any above certificate is in process, the bidder must submit the proof of application submitted with concerned authority for renewal of certificate.
3.3 TECHNICAL EVALUATION CRITERIA.
Bid Evaluation Criteria attached as Appendix -F
IB.4 COST OF BIDDING
4.1The bidders shall bear all costs associated with the preparation and submission of their respective bids and the Employer will in no case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding process.
IB.5 SITE VISIT
5.1 The bidders are advised to visit and examine the Site of Works and its surroundings and obtain for themselves on their own responsibility all information that may be necessary for preparing the bid and entering into a contract for the Works. All cost in this respect shall be at the bidder’s own expense.
B. BIDDING DOCUMENTS
IB.6 CONTENTS OF BIDDING DOCUMENTS
6.1 The Bidding Documents, in addition to invitation for bids, are those stated below and should be read in conjunction with any Addenda issued in accordance with Clause IB.8.
1. Instructions to Bidders.
2. Bidding Data.
3. Form of Bid & Appendices to Bid.
Appendices to Bid comprise the following:
i. Schedule A: Contract Data.
ii. Schedule B: Schedule of Prices.
iii. Schedule C: Proposed Program of Works.
iv. Schedule D: Organization Chart for Supervisory Staff and Labor.
v. Schedule E: List of Major Equipment.
4. Conditions of Contract:
5. Standard Forms:
i. Performance Guarantee (As required)
ii. Form of Contract Agreement.
6. Specifications:
i. Special Provision.
ii. Technical Provision.
7. Drawings:
IB.7 CLARIFICATION OF BIDDING DOCUMENTS
7.1 Any prospective bidder requiring any clarification (s) in respect of the Bidding Documents may notify the Employer in writing at the Employer’s address indicated in the Invitation for Bids.
IB.8 AMENDMENT OF BIDDING DOCUMENTS
8.1 At any time prior to the deadline for submission of bids, the Employer may, for any reason, whether at his own initiative or in response to a clarification requested by a prospective bidder, modify the Bidding Documents by issuing addendum.
8.2 Any addendum thus issued shall be part of the Bidding Documents and shall be communicated in writing to all purchasers of the Bidding Documents.
C. PREPARATION OF BIDS
IB.9 LANGUAGE OF BID
9.1 The bid and all correspondence and documents related to the bid exchanged by a bidder and the Employer shall be in the bid language stipulated in the Bidding Data and Particular Conditions of Contract. Supporting documents and printed literature furnished by the bidders may be in any other language provided the same are accompanied by an accurate translation of the relevant parts in the bid language, in which case, for purposes of evaluation of the bid, the translation in bid language shall prevail.
IB.10 DOCUMENTS ACCOMPANYING THE BID
10.1 The bid prepared by the bidder shall comprise the following components:
a. Covering Letter
b. Form of Bid duly filled, signed and sealed.
c. Schedules (A to E) to Bid duly filled and initialed in accordance with the instructions contained therein & in accordance with Sub-Clause IB.16.3.
d. Bid Security furnished in accordance with Clause 1B.13.
10.2 Bids submitted by a joint venture of two (2) or more firms shall comply with the following requirements:
a. the bid and in case of a successful bid, the Form of Contract Agreement shall be signed so as to be legally binding on all partners;
b. one of the joint venture partners shall be nominated as being In-charge; and this authorization shall be evidenced by submitting a power of attorney signed by legally authorized signatories of all the joint venture partners;
a copy of the agreement entered into by the joint venture partners shall be submitted with the bid stating the conditions under which it will function, its period of duration, the persons authorized to represent and obligate it and which persons will be directly responsible for due performance of the Contract and can give valid receipts on behalf of the joint venture, the proportionate participation of the several firms forming the joint venture, and any other information necessary to permit a full appraisal of its functioning. No amendments / modifications whatsoever in the joint venture agreement shall be agreed to between the joint venture partners without prior written consent of the Employer.
IB.11 BID PRICES
11.1 Unless stated otherwise in the Bidding Documents, the Contract shall be for the whole of the Works as described in Sub-Clause 1.1 hereof, based on the unit rates and / or prices submitted by the bidder.
11.2 The bidders shall fill in rates and prices for all items of the Works described in the Bill of Quantities. Items against which no rate or price is entered by a bidder will not be paid for by the Employer when executed and shall be deemed covered by rates and prices for other items in the Bill of Quantities.
11.3 The unit rates and prices in the Schedule of Prices shall be quoted by the bidder in the currency as stipulated in Bidding Data.
IB.12 DOCUMENTS ESTABLISHING BIDDER’S ELIGIBILITY AND QUALIFICATIONS
12.1 Pursuant to Clause IB.6, the bidder shall furnish, as part of its bid, documents establishing the bidder’s eligibility to bid and its qualifications to perform the Contract if its bid is accepted.
12.2 Bidders must possess and provide evidence of its capability and the experience as stipulated in Bidding Data and in the Bidding Documents.
IB.13 BID SECURITY
13.1 Each bidder shall submit original Bid Securitas stipulated in the Bidding Data in Pak Rupees in the form of pay-order/demand draft before closing time of bid submission with Employer. Bid will be rejected if original bid security is not received by Employer before closing time.
13.2 Any E-bid not attached with Bid Security shall be rejected by the Employer as non-responsive.
13.3 The bid securities of unsuccessful bidders will be returned after award of Work to successful bidder.
13.4 The Bid Security of the successful bidder will be returned when the bidder has furnished the required performance guarantee and signed the Contract Agreement.
13.5 The Bid Security may be forfeited:
a. if the bidder withdraws his bid during the period of bid validity or
b. if the bidder does not accept the correction of his Bid Price pursuant to Sub-Clause 25.2hereof; or
c. In the case of successful bidder, if he fails within the specified time limit to:
i. Furnish the required performance guarantee.
ii. Sign the Contract Agreement in accordance with sub–clause IB.31.1.
IB.14 BID VALIDITY
14.1 Bids shall remain valid for the period stipulated in the Bidding Data after the Date of Bid Opening.
14.2 In exceptional circumstances, prior to expiry of the original bid validity period, the Employer may request that the bidders extend the period of validity for a specified additional period which shall in no case be more than the original bid validity period. The request and the responses thereto shall be made in writing.
A bidder may refuse the request without forfeiting his Bid Security. A bidder agreeing to the request will not be required or permitted to modify his bid.
IB.16 FORMAT AND SIGNING OF BID
16.1 Bidders are particularly directed that the amount entered on the Form of Bid shall be for performing the Contract strictly in accordance with the Bidding Documents.
16.2 All appendices / schedules to Bid are to be properly completed and signed.
16.3 No alteration is to be made in the Form of Bid nor in the Appendices thereto except in filling up the blanks as directed. If any such alterations be made or if these instructions be not fully complied with, the bid may be rejected.
16.4 Successful bidder shall prepare by filling out the forms completely and without alterations one (1) original copy, specified in the Bidding Data, of the documents comprising the bid as described in Clause IB.6 and submit it with Employer after letter of award.
16.5 The original and copy of the bid shall be typed or written in indelible ink and shall be signed by a person or persons duly authorized to sign on behalf of the bidder. All pages of the bid shall be initialed and stamped by the person or persons signing the bid.
B.18 DEADLINE FOR SUBMISSION OF BIDS.
18.1 The bids must be submitted electronically through E-Pads on or before the deadline stated in the bidding data / advertisement. Physical or manual submission of bids will not be accepted.
IB.19 LATE BIDS
19.1 E-Pads system will not accept late submission of bids. To avoid any problems / issues bids must be submitted on the system before closing time.
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
The Supplier is:
The title of the subject procurement is: TENDER FOR UPGRADATION OF TOILET BLOCKS & PLUMBING SHAFT UNIT WORKS AT STATE LIFE BUILDING #3 THANDI SARAK HYDERABAD
Number of GC Clause 2
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 3
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 4
Notices:
The addresses for the notices are:
Procuring Agency:
State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager
State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
+92-300-937-6673
re.hyd@statelife.com.pk
Contractor/ Bidder:
[Name, address and telephone number]
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 6.1
The Authorized Representatives are:
For the Procuring Agency:
State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager
State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
+92-300-937-6673
re.hyd@statelife.com.pk
For the Bidder:
Name: ………………………………………
Designation: ……………………..
Address: …………………………………………..
Number of GC Clause 7
Effectiveness of the contract
The Contractor/Bidder shall be effective within ….. days from the date of signature of the Contract by both parties
Number of GC Clause 8
Commencement of Contract:
The Contractor/Bidder shall provide Non-Consultancy Services from the effective date of contract.
Number of GC Clause 10.2
Expiration of Contract:
The time period shall be ……………………………
Number of GC Clause 14
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 16
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 20
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 10.00% to 0.10% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 21
Performance Guarantee:
The amount of performance guarantee shall be 0% of the contract price in acceptable form of Nil
Number of GC Clause 27
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 28
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 29
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
For being Brand New, bearing relevant reference numbers of the equipment (Certificate from supplier)
For Physical Fitness having No Damages (Certificate from supplier)
For the Country of Origin as quoted by the Supplier (Certificate from manufacturer)
For conformance to specifications and performance parameters, through Prior to delivery inspection (Inspection Report by Procurement Committee / Inspection Team)
For successful operation at site after complete installation, testing and commissioning of the equipment (Installation, Testing and Commissioning Report by Procurement Committee / Inspection Team)
Copies of the Supplier’s invoice showing Goods’ description, quantity, unit price, and total amount;
Original and two copies of the usual transport document (for example, a negotiable bill of lading, a non-negotiable sea waybill, an inland waterway document, an air waybill, a railway consignment note, a road consignment note, or a multimodal transport document) which the buyer may require to take the goods;
Copies of the packing list identifying contents of each package;
Insurance Certificate;
Manufacturer’s or Supplier’s Valid Warranty Certificate;
Inspection Certificate issued by the Nominated Inspection Agency (if any), and the Supplier’s Factory Inspection Report;
Certificate of Origin.
The above documents would be required even if the equipment has already been imported and is available with the supplier ex-stock
Number of GC Clause 31
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder shall be referred to arbitration under the laws of Pakistan including Arbitration Act 1940.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place shall be Islamabad. The award shall be final and binding.
Date: [insert date (as day, month and year)]
Bid No.:P157800
To: State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
THIS AGREEMENT made the _____ day of __________ 20_____ between State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., TENDER FOR UPGRADATION OF TOILET BLOCKS & PLUMBING SHAFT UNIT WORKS AT STATE LIFE BUILDING #3 THANDI SARAK HYDERABAD (P157800) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: State Life, Real Estate, Hyderabad (State Life Insurance Corporation of Pakistan (SLIC)), Manager State Life Building # 3, Thandi Sarak, Hyderabad, Hyderabad, Hyderabad (District), Hyderabad (Division), Sindh (Province).
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}