In terms of Rules 65 of Public Procurement Rules, 2026 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer
132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
+92-370-180-0277
pdgscfesco@gmail.com
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
|
BDS Clause Number |
ITB Number |
Amendments of, and Supplements to, Clauses in the Instruction to Bidders |
A. Introduction |
||
|
1 |
1.1 |
Name of Procuring Agency:Â Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)) The subject of procurement is:Â Tender No.58 for Special Repair of C-1 Flat situated at 132KV Grid Station Agriculture University Colony FESCO Faisalabad Expected commencement date: Thursday, December 31, 2026 |
|
2. |
2.1 |
Financial year for the operations of the Procuring Agency:Â 2026-27 Name and identification number of the Contract: P192228Â |
| 3. | 3.1 | JV/Consortium or Association Allowed: Yes Number of JV/Consortium Members: 5 |
B. Bidding Documents |
||
|
4. |
6.2 & 6.4 |
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Tuesday, November 24, 2026 |
| 5. | 7.2 |
Any addendum, in case issued, shall be published on Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)) website and on EPADS v2.0. |
C. Preparation of Bids |
||
| 6. |
8.1 |
List of documents required along with the bid:
 |
| 7. | 9.1 |
The qualification criteria to establish the supply / production capability of the bidder. see Eligibility Criteria |
| 8. | 11.2Â |
|
| 9. | 11.1 | Price schedule will be provided according to the format defined and acquired. see section price schedule. |
| 10. | 11.4 |
 Specifications: see section of specifications. |
|
11. |
11.5 & 13.5 |
The price shall be Fixed. |
| 12. |
14.1 |
Currency of the Bids shall be : PKR |
| 13. |
16.1 |
The Bids/Bid Validity period shall be: 150 Days |
| 14. |
17.1Â |
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6 |
| 15. | 17.2 |
The Bid Security shall be in the form of: Pay Order, Banker's Cheque, Call at Deposit, Demand Draft  |
| 16. | 15.1 |
Alternative Bids to the requirements of the bidding documents will not be permitted. |
D. Submission of Bids |
||
|
17. |
18.1 & 21.1 |
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following; 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province). Bids that are not submitted on EPADS v2.0 shall be disqualified. The deadline for Bids submission is: Friday, November 27, 2026 11:30 AM |
E. Opening and Evaluation of Bids |
||
|
18. |
24.1 |
The Bids opening shall take place on EPADS v2.0. Day : Friday Date:Â November 27, 2026 Time : 01:30 PM |
|
19. |
30.2 |
Selection technique adopted will be: Least Cost Based Selection (LCBS) |
F. Award of Contract |
||
|
20. |
41.1 & 41.2 |
The Performance guarantee shall: 10.00%. The Performance Guarantee shall be acceptable in the form of:Â Pay Order, Banker's Cheque, Call at Deposit, Demand Draft |
| 21. | 45.1 |
Arbitrator shall be appointed by mutual consent of the both parties. |
G. Review of Procurement Decisions |
||
|
22. |
37 |
Grievance against this procurement shall be submitted online on EPADS v2.0. |
All Active Taxpayers shall be eligible to participate in the procurement process, unless expressly excluded or otherwise restricted under the Eligibility Criteria specified by the Procuring Agency.
| Required Registration |
|---|
| NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) Punjab (PRA) PEC |
| Eligibility Criteria | Document |
|---|---|
| Complete Bidding Documents Generated by PPRA Upload after proper filling bid price with stamp & signed. | Yes |
| Completed Technical & Financial documents uploaded proper stamp & signed. | Yes |
| Uploaded remaining documents technical and financial if required. | Yes |
Least Cost Based Selection (LCBS)
Jobs Without Lots :
| Job | Delivery Schedule | Quantity | Bid Security |
|---|---|---|---|
| Special Repair of C-1 Flat situated at 132KV Grid Station Agriculture University FESCO Faisalabad | Address: 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province). Schedule: 30 Days Quantity: 1/job |
1/job | 57636 PKR |
No
Jobs Without Lots :
Job: Special Repair of C-1 Flat situated at 132KV Grid Station Agriculture University FESCO Faisalabad
Specifications / Requirements:
| Sr. No | Ref. No. | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|---|
| 1 | 1 | Petty repairs to small rooms below 10.75 Sq.CSR 20-22/178 | Each | 3 | 319.71 | 959.13 |
| 2 | 2 | Petty repairs to main rooms above 10.75 Sq.CSR 20-22/177 | Each | 3 | 646.78 | 1940.34 |
| 3 | 3 | Petty repairs to verandah CSR 20-22/179 | Each | 2 | 646.78 | 1293.56 |
| 4 | 4 | Removing cement plaster.CSR 3-4/39 | Sqm | 74.04 | 43.05 | 3187.422 |
| 5 | 5 | Dismantling cement concrete CSR 3-1/11 | Cum | 1.55 | 3870.63 | 5999.4765 |
| 6 | 6 | Cement concrete plain including placing, compacting, finishing and curing complete (including screening and washing of stone aggregate) without shuttering. CSR 5-1/2 b | Cum | 1.55 | 11037.67 | 17108.3885 |
| 7 | 7 | Distempering one Coat over and I/C cost of priming coat CSR-10-2/16-a | sqm | 450 | 135.27 | 60871.5 |
| 8 | 8 | weather shield paint on painted / old s1urface, one coat. CSR 10-3/25 | Sqm | 200 | 111.65 | 22330 |
| 9 | 9 | Painting Old surface Painting doors and windows any types (One coat) CSR 12-01/4-C | Sqm | 153.15 | 186.05 | 28493.5575 |
| 10 | 10 | C.I soil pipes (sand cast) having following daimeter with cement joints (1:2) 100 mm dia CSR 13-24/114-B | Mtr | 12 | 2563.35 | 30760.2 |
| 11 | 11 | Laying jointing fixing and testing GI or WI pipes lines with all specials inside buildings & trenches with internal diameter CSR 13-12/36 | Â | Â | Â | Â |
| 12 | a | 13mm dia Wash Rooms | Mtr | 40 | 379.74 | 15189.6 |
| 13 | b | 20mm dia | Mtr | 25 | 504.79 | 12619.75 |
| 14 | 12 | C.P Pillar cocks 13mm dia CSR 13-20/80 | each | 3 | 770.29 | 2310.87 |
| 15 | 13 | C.P bib taps 13mm dia CSR 13-20/82 | each | 4 | 741.85 | 2967.4 |
| 16 | 14 | Low level flushing cistern 13.5 litre capacity best quaility (Plastic) CSR 13-19/70 | each | 2 | 2854.61 | 5709.22 |
| 17 | 15 | Providing and fixing distribution board comprising incoming and outgoing cirucit breaker neutal link and auxiliry wiring completehoused in MS box of 1.62 mm thcik sheet having detachable inner cover and outer hinged type lockable door duly painted inside and outside with deco spray powdered paid. CSR 21-30/1 | each | 1 | 11303.61 | 11303.61 |
| 18 | 16 | Providing and fixing laminated board for wardrobe shutter complete in all respect. CSR 11-7/45 | Sqm | 3.38 | 3848.45 | 13007.761 |
| 19 | 17 | 13mm thick cemnt plaster 1:4 upto 6.00M hight CSR 10-1/5 | Sqm | 75 | 1237.95 | 92846.25 |
| 20 | 18 | Looking glass CSR 13-20/77 | each | 2 | 1103.85 | 2207.7 |
| 21 | 19 | Brass ball valves 20mm dia CSR 13-21/93 | each | 2 | 607.24 | 1214.48 |
| 22 | 20 | Stainless steel sink 50x125mm size CSR 13-19/6 | each | 1 | 6196.63 | 6196.63 |
| 23 | 21 | Chromium plated shower 13mm completed with CP arm 02-No. cp stop cock 01-No. CP bib cock & 1 CP shower CSR 13-22/97 | each | 2 | 4878.95 | 9757.9 |
| 24 | 22 | Chromium plated mixing valves CSR 13-22/98 | each | 2 | 2331.4 | 4662.8 |
| 25 | 23 | White glazed earthenware water closed squating type orris pattern domestic of best quality CSR 13-18/62 | each | 2 | 5175.63 | 10351.26 |
| 26 | 24 | Flooring comprising of glazed tiles 6mm thick laid in white cement mortar 1:2 over 20mm thick cement mortar 1:2 complete:Coloured CSR 9-3/16b | Sqm | 108.469 | 3279.94 | 355771.81186 |
| 27 | 25 | White / clour glazed tile dado 6mm thick jointed in white cement and jointed in white cement and laid over 1:2 cment sand motar 19mm thick including finishing CSR 9-5/26 | Sqm | 26.208 | 3469.19 | 90920.53152 |
| 28 | 26 | Providing and fixing steel window(openable) of stander tabuler frame1.5"x1.5"and sutters1.5"x1"as per engineer in chief and drawing CSR 20-4/37 | Sqm | 3.16 | 6762.25 | 21368.71 |
| 29 | 27 | Providing and fixing steel grills to openable steel windows as per drawing No CDO(W)301- CSR 20-4/39 | Sqm | 3.16 | 4905.07 | 15500.0212 |
| 30 | 28 | Providing and fixing wire gauze 144 mesh square in openable tabular window and C-window as per drawing No CDA(W)301- CSR 20-4/40 | Sqm | 3.16 | 2602.76 | 8224.7216 |
| 31 | 29 | Providing and fixing almirah as per standard design of WAPDA residences. CSR 11-4/22 | Sqm | 14.96 | 11656.22 | 174377.0512 |
| 32 | 30 | Wiring light or fan points with 1/1.13 (3.029)PVC insulated wire in 20 mm 1.50 mm thick Pvc Conduite recessed in the wall or colmn complete with switch plastic(P-21-4/26) | P/point | 30 | 2078.7 | 62361 |
| 33 | 31 | Providing and fixing / connecting surface type 2-pin 5 amps SP plug socket switch complete with SW board as replacement 21-24/13 | P/point | 6 | 160.29 | 961.74 |
| 34 | 32 | Wiring 2 pin plug control point on board with 1.13 (3/0.029)pvc insulated wire in 20 mm (3/4"Pvc conduit recessed in wall as required CSR 21-2/9 | P/point | 6 | 290.83 | 1744.98 |
| 35 | 33 | P/F fluorescent tubhe light complete with 4" long tube rod choke started and patti (LED Lights / ceiling lights ). CSR 23-14/120 | each | 40 | 653.4 | 26136 |
| 36 | 34 | Providing and fixing surface type 3 pin 15 amp plug socket and switch on complete with board 21-25/23 | each | 4 | 402.95 | 1611.8 |
| 37 | 35 | Floor trap 100mmx50mmm (i/c50mm concrete chamber all round ) with cp grating 13-23/108 | each | 4 | 723.99 | 2895.96 |
| 38 | 36 | 100mm i/d gully trap of cement including 300mm x305mm masonery chamber and C-I grating 150x150mm (p-13-23/109) | each | 4 | 3462.45 | 13849.8 |
| 39 | 37 | Providing lowering and laying into trenches and jointing cement concrete rain forced pipe line to correct alignment and grade i/c cutting of pipe whare necessary cost of jointing testing 150mm i/d Deduction lump sump Rs. 20000 / 842.61 = 23.736 Qty Actual =40 - Ded=23.736= 16.26 | M | 16.26 | 842.61 | 13700.8386 |
| 40 | Â | RATE Rs._________%ABOVE/BELOW | Â | Â | Â | Â |
| 41 | Â | Signature of the Contractor | Â | Â | Â | Â |
| GRAND TOTAL: | Rs 1,152,713.77 |
Special Repair of C-1 Flat situated at 132KV G/S Agriculture University Faisalabad.
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
Â
Â
Â
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
The Supplier is:
The title of the subject procurement is: Tender No.58 for Special Repair of C-1 Flat situated at 132KV Grid Station Agriculture University Colony FESCO Faisalabad
Number of GC Clause 2
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 3
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 4
Notices:
The addresses for the notices are:
Procuring Agency:
Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer
132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
+92-370-180-0277
pdgscfesco@gmail.com
Contractor/ Bidder:
[Name, address and telephone number]
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 6.1
The Authorized Representatives are:
For the Procuring Agency:
Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer
132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
+92-370-180-0277
pdgscfesco@gmail.com
For the Bidder:
Name: ………………………………………
Designation: ……………………..
Address: …………………………………………..
Number of GC Clause 7
Effectiveness of the contract
The Contractor/Bidder shall be effective within ….. days from the date of signature of the Contract by both parties
Number of GC Clause 8
Commencement of Contract:
The Contractor/Bidder shall provide Non-Consultancy Services from the effective date of contract.
Number of GC Clause 10.2
Expiration of Contract:
The time period shall be ……………………………
Number of GC Clause 14
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 16
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 20
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 0.10% to 10.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 21
Performance Guarantee:
The amount of performance guarantee shall be 10.00% of the contract price in acceptable form of Pay Order, Banker's Cheque, Call at Deposit, Demand Draft
Number of GC Clause 27
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 28
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 29
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
For being Brand New, bearing relevant reference numbers of the equipment (Certificate from supplier)
For Physical Fitness having No Damages (Certificate from supplier)
For the Country of Origin as quoted by the Supplier (Certificate from manufacturer)
For conformance to specifications and performance parameters, through Prior to delivery inspection (Inspection Report by Procurement Committee / Inspection Team)
For successful operation at site after complete installation, testing and commissioning of the equipment (Installation, Testing and Commissioning Report by Procurement Committee / Inspection Team)
Copies of the Supplier’s invoice showing Goods’ description, quantity, unit price, and total amount;
Original and two copies of the usual transport document (for example, a negotiable bill of lading, a non-negotiable sea waybill, an inland waterway document, an air waybill, a railway consignment note, a road consignment note, or a multimodal transport document) which the buyer may require to take the goods;
Copies of the packing list identifying contents of each package;
Insurance Certificate;
Manufacturer’s or Supplier’s Valid Warranty Certificate;
Inspection Certificate issued by the Nominated Inspection Agency (if any), and the Supplier’s Factory Inspection Report;
Certificate of Origin.
The above documents would be required even if the equipment has already been imported and is available with the supplier ex-stock
Number of GC Clause 31
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder shall be referred to arbitration under the laws of Pakistan including Arbitration Act 1940.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place shall be Islamabad. The award shall be final and binding.
Date: [insert date (as day, month and year)]
Bid No.:P192228
To: Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
THIS AGREEMENT made the _____ day of __________ 20_____ between Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., Tender No.58 for Special Repair of C-1 Flat situated at 132KV Grid Station Agriculture University Colony FESCO Faisalabad (P192228) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: Office of PD GSC FESCO (Faisalabad Electric Supply Company (FESCO)), Chief Engineer 132 kV Grid Statio, Agriculture University, Near Darbar Baba Qaim Sain, Daewoo Road., Faisalabad City, Faisalabad (District), Faisalabad Division (Division), Punjab (Province).
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}