In terms of Rules 65 of Public Procurement Rules, 2026 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director
9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
+92-301-541-1726
sarckarachi@parc.gov.pk
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
|
BDS Clause Number |
ITB Number |
Amendments of, and Supplements to, Clauses in the Instruction to Bidders |
A. Introduction |
||
|
1 |
1.1 |
Name of Procuring Agency: PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)) The subject of procurement is: REPAIR & MAINTENANCE OF DIFFERENT OFFICES OF PARC-SARC, KARACHI Expected commencement date: Sunday, December 27, 2026 |
|
2. |
2.1 |
Financial year for the operations of the Procuring Agency: 2026-27 Name and identification number of the Contract: P216576 |
| 3. | 3.1 | JV/Consortium or Association Allowed: Yes Number of JV/Consortium Members: 2 |
B. Bidding Documents |
||
|
4. |
6.2 & 6.4 |
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Saturday, December 5, 2026 |
| 5. | 7.2 |
Any addendum, in case issued, shall be published on PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)) website and on EPADS v2.0. |
C. Preparation of Bids |
||
| 6. |
8.1 |
List of documents required along with the bid:
|
| 7. | 9.1 |
The qualification criteria to establish the supply / production capability of the bidder. see Eligibility Criteria |
| 8. | 11.2 |
|
| 9. | 11.1 | Price schedule will be provided according to the format defined and acquired. see section price schedule. |
| 10. | 11.4 |
Specifications: see section of specifications. |
|
11. |
11.5 & 13.5 |
The price shall be Fixed. |
| 12. |
14.1 |
Currency of the Bids shall be : PKR |
| 13. |
16.1 |
The Bids/Bid Validity period shall be: 120 Days |
| 14. |
17.1 |
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6 |
| 15. | 17.2 |
The Bid Security shall be in the form of: Pay Order, Demand Draft |
| 16. | 15.1 |
Alternative Bids to the requirements of the bidding documents will not be permitted. |
D. Submission of Bids |
||
|
17. |
18.1 & 21.1 |
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following; 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province). Bids that are not submitted on EPADS v2.0 shall be disqualified. The deadline for Bids submission is: Tuesday, December 8, 2026 11:00 AM |
E. Opening and Evaluation of Bids |
||
|
18. |
24.1 |
The Bids opening shall take place on EPADS v2.0. Day : Tuesday Date: December 08, 2026 Time : 11:30 AM |
|
19. |
30.2 |
Selection technique adopted will be: Least Cost Based Selection (LCBS) |
F. Award of Contract |
||
|
20. |
41.1 & 41.2 |
The Performance guarantee shall: 5.00%. The Performance Guarantee shall be acceptable in the form of: Pay Order, Demand Draft |
| 21. | 45.1 |
Arbitrator shall be appointed by mutual consent of the both parties. |
G. Review of Procurement Decisions |
||
|
22. |
37 |
Grievance against this procurement shall be submitted online on EPADS v2.0. |
All Active Taxpayers shall be eligible to participate in the procurement process, unless expressly excluded or otherwise restricted under the Eligibility Criteria specified by the Procuring Agency.
| Required Registration |
|---|
| NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) PEC |
| Eligibility Criteria | Document |
|---|---|
| PEC C-6 license including validity till 202703 Years of experience – proven by job completion certificate / certificate of incorporationTurnover of Rs. 03 Million – Proven by last 3 Years Audit reportsMust have completed at least 2 public/private sector jobs/projects of similar natureMust provide a non-blacklisting affidavit | Yes |
| All relevant Documents will be required | Yes |
Least Cost Based Selection (LCBS)
Lot Title : REPAIR & MAINTENANCE OF DIFFERENT OFFICES OF PARC-SARC, KARACHI
Bid Security : 200000 PKR
| Job | Delivery Schedule | Quantity |
|---|---|---|
| Top Roof Treatment and Plumbing work VPCI Office Building at PARC-SARC, Karachi |
Address: 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
Schedule: 03-Months
Quantity: 1/Qty
|
1/Qty |
| Top Roof Treatment of IPI Office Building PARC-SARC, Landhi Farm, Karachi |
Address: 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
Schedule: 03-Months
Quantity: 1/Qty
|
1/Qty |
| Top Roof Treatment of ORAU Office Building at PARC-SARC, Malir Halt Karachi |
Address: 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
Schedule: 03-Months
Quantity: 1/Qty
|
1/Qty |
No
Lot Title: REPAIR & MAINTENANCE OF DIFFERENT OFFICES OF PARC-SARC, KARACHI
Specifications / Requirements:
| Sr. No | Sr# | Description | Unit | Qty | Rate | Ref | Amount |
|---|---|---|---|---|---|---|---|
| 1 | Toproof Treatment IPI Building Office Landhi Farm | ||||||
| 2 | 1 | Providing, laying and applying 4 mm thick Roof Grip or Hy-Grip water proofing PLASTOMAT SUNTAN or equivlent PP/PG 4000 modified bituminous membrane torch applied polymerized containing non woven Plaster coated on both side with APP modified bitumen compound having upper surface with slate granules and lower surface with polyethylene film and applying approved primer @ 3 to 4 Sq.M. area per litre on roof surface, walls or where required and unrolling, including overlapage 10 cm at side and 15 cm at ends, complete as per manufacturer’s recommendations and as directed by the Engineer Incharge detailed as under: | Sft | ||||
| 3 | 2 | a) Clearing the roof surface from all debris, dust or flaws by washing with pressure pumps. | Sft | ||||
| 4 | 3 | b) Repairing of cracks with filling of epoxy grout/ plaster where-ever required with 1:3 cement sand mortar using sulphate resistance cement. | Sft | ||||
| 5 | 4 | (Note: Five years warranty against any leakage /seepage shall be provided by the contractor). | Sft | 2250 | |||
| 6 | Toproof Treatment ORAU Office Building, PARC-SARC, Karachi Malir Halt | ||||||
| 7 | 1 | Providing, laying and applying 4 mm thick Roof Grip or Hy-Grip water proofing PLASTOMAT SUNTAN or equivlent PP/PG 4000 modified bituminous membrane torch applied polymerized containing non woven Plaster coated on both side with APP modified bitumen compound having upper surface with slate granules and lower surface with polyethylene film and applying approved primer @ 3 to 4 Sq.M. area per litre on roof surface, walls or where required and unrolling, including overlapage 10 cm at side and 15 cm at ends, complete as per manufacturer’s recommendations and as directed by the Engineer Incharge detailed as under: | Sft | ||||
| 8 | 2 | a) Clearing the roof surface from all debris, dust or flaws by washing with pressure pumps. | Sft | ||||
| 9 | 3 | b) Repairing of cracks with filling of epoxy grout/ plaster where-ever required with 1:3 cement sand mortar using sulphate resistance cement. | Sft | ||||
| 10 | 4 | (Note: Five years warranty against any leakage /seepage shall be provided by the contractor). | Sft | 4000 | |||
| 11 | Toproof Treatment VPCI Building PARC-SARC, Univeristty Campus Karachi | ||||||
| 12 | 1 | Dismantling / Removal of existing approx 2.5" to 2" thick PCC with care (using hilti hammer drill) and making surface smooth, cleaning with steel brush including shifting of removal items/debries outside area within 3Km including removal of water supply line if required etc complete in all respect. | Sft | 9500 | |||
| 13 | 2 | Providing and laying 20 mm thick Terrazzo floor using marble chips (1:2) with cement, over 1" to 2" thick (Avg) PCC 1:2:4 base of over roof top & parapet wall including making panels with marble strips not more than 16 sft including making slopes and grinding etc complete in all respect ensure to stop the water seepage. | Sft | 9500 | |||
| 14 | 3 | Repair & Maintenance overhead water tank (size 13'.11''X 9..03''X 7;.10'') and applying ratio 1/4 including the cost of leveling find finishing in mixing of water seepage chemical etc complete all respects | Job | 1 | |||
| 15 | Plumbing Work (VPCI) Building, PARC-SARC, Karachi | ||||||
| 16 | 1 | Providing, & fixing RCC pipes and collars of class A and fixing in trench including cutting fitting in trench and jointing with maxphalt composition and cement mortar (1:1) and including excavation and back filling etc complete in all respects. | Rft | ||||
| 17 | 2 | b) 9” dia | Rft | 200 | |||
| 18 | 3 | Providing & making Man-hole size 3'-0" X 3’-0" (inside) dimension and specification complete for 4" to 12" dia pipe with 18”x18” RCC cover with double angle iron frames of size 1-1/2” X 1-1/2” X 1/4” and 1-1/4” X 1-1/4” X 3/16” for sanitary manhole in RCC slab 4" thick 1:2:4 and 9" thick 1st Class Burnt brick masonry walls or solid Cement Blocks 8" thick set in 1:3 CSM with 4" thick 1:2:4 in foundation laid over 6” PCC 1:4:8, 1:2:4 in benching and 1/2" thick plaster in 1:3 walls inside including providing & fixing MS bar footrest at every foot of depth, excavation and back filling etc complete in all respects. | |||||
| 19 | 4 | a) Upto 4’ depth from invert to Surface | No | 8 | |||
| 20 | 5 | Providing & fixing UPVC Soil or equilevnt , Waste and vent pipies conforming to ISO 3633 type “B” or BS-4514/5255 Class ‘A’ pipes and fittings i.e elbow, bend, Tees, Terminal Guards including the cost of specified adhesive, imported rubber ring etc complete in all respects. | |||||
| 21 | 6 | a) 4” dia | Rft | 150 | |||
| 22 | 7 | b) 3” dia | Rft | 300 | |||
| 23 | 8 | c) 2” dia | Rft | 200 | |||
| 24 | 9 | (Pipes of Dadex Ltd, Shafisons Engineering (Pvt) Ltd Beta Pipes or Marley shall be used) | |||||
| 25 | 10 | Clearing & Cleaning of sewer line/ Manholes including removal of sludge/earth and its disposal outside and repair of manholes with CS morter 1:4 to Main Septic Tank or as directed by the Engineer In-charge. | Job | 1 | |||
| 26 | 11 | Providing & fixing UPVC D Calss pipe or eqivilent cold and hot water pipe fittings special clamps conforming to DIN 8077/8078 etc fixing cutting and fiting complete with and including th cost of breaking through wall floor and roof making good etc complete including brass threaded heads for fittings | |||||
| 27 | 12 | UPVC 1/2"dia or equivelent | Rft | 300 | |||
| 28 | 13 | PPR 3/4 dia (20mm) or equivlent | Rft | 800 | |||
| 29 | 14 | PPR25dia mm or equivlent | Rft | 500 | |||
| 30 | 15 | PPR 32 dia mm or equivlent | Rft | 200 | |||
| 31 | 16 | PPR 40 dia mm "(1-2/2) or equivlent | Rft | 300 | |||
| 32 | 17 | (Pipe of Dadex, firattherm or Retti Taly shall be used) | |||||
| 33 | 18 | Providing & fixing 3"to 4" dia UPVC drain pipe or equivlent etc complete in all respect | Rft | 200 | |||
| 34 | 19 | Providing & fixing UPVC or equilvent , PVC elbow bend with Z 3"dia joint filling etc complete in all respect | No. | 12 | |||
| 35 | 20 | Providing supplying valves (peet) strong gun metal high pressure full way value as per site requirement different size etc complete as per B.o.Q | |||||
| 36 | 21 | 1/2# dia | No. | 6 | |||
| 37 | 22 | 1"dia | No. | 6 | |||
| 38 | 23 | 1-1/2 dia | No. | 6 | |||
| 39 | 24 | 2"dia | No. | 6 | |||
| GRAND TOTAL: | Rs 4,999,594.00 |
Top Roof Treatment and Plumbing work VPCI Office Building at PARC-SARC, Karachi
Top Roof Treatment of IPI Office Building PARC-SARC, Landhi Farm, Karachi
Top Roof Treatment of ORAU Office Building at PARC-SARC, Malir Halt Karachi
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
The Supplier is:
The title of the subject procurement is: REPAIR & MAINTENANCE OF DIFFERENT OFFICES OF PARC-SARC, KARACHI
Number of GC Clause 2
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 3
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 4
Notices:
The addresses for the notices are:
Procuring Agency:
PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director
9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
+92-301-541-1726
sarckarachi@parc.gov.pk
Contractor/ Bidder:
[Name, address and telephone number]
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 6.1
The Authorized Representatives are:
For the Procuring Agency:
PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director
9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
+92-301-541-1726
sarckarachi@parc.gov.pk
For the Bidder:
Name: ………………………………………
Designation: ……………………..
Address: …………………………………………..
Number of GC Clause 7
Effectiveness of the contract
The Contractor/Bidder shall be effective within ….. days from the date of signature of the Contract by both parties
Number of GC Clause 8
Commencement of Contract:
The Contractor/Bidder shall provide Non-Consultancy Services from the effective date of contract.
Number of GC Clause 10.2
Expiration of Contract:
The time period shall be ……………………………
Number of GC Clause 14
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 16
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 20
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 1.00% to 2.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 21
Performance Guarantee:
The amount of performance guarantee shall be 5.00% of the contract price in acceptable form of Pay Order, Demand Draft
Number of GC Clause 27
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 28
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 29
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
For being Brand New, bearing relevant reference numbers of the equipment (Certificate from supplier)
For Physical Fitness having No Damages (Certificate from supplier)
For being Brand New, bearing relevant reference numbers of the equipment (Certificate from supplier)For Physical Fitness having No Damages (Certificate from supplier)
Copies of the Supplier’s invoice showing Goods’ description, quantity, unit price, and total amount;
Manufacturer’s or Supplier’s Valid Warranty Certificate;
The above documents would be required even if the equipment has already been imported and is available with the supplier ex-stock
Number of GC Clause 31
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder shall be referred to arbitration under the laws of Pakistan including Arbitration Act 1940.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place shall be Islamabad. The award shall be final and binding.
Date: [insert date (as day, month and year)]
Bid No.:P216576
To: PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
THIS AGREEMENT made the _____ day of __________ 20_____ between PARC-Southerzone Agricultural Research Centre (Pakistan Agriculture Research Council (PARC)), Assistant Director 9 & 10, Old Block, University Campus, University of Karachi., Gulshan-e-Iqbal Sub-Division, Karachi East (District), Karachi (Division), Sindh (Province).
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., REPAIR & MAINTENANCE OF DIFFERENT OFFICES OF PARC-SARC, KARACHI (P216576) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
As per BoQ
At least two completed similar civil repair, maintenance or waterproofing contracts in the preceding five years; work orders and completion certificates.
At least one PEC-registered civil engineer and one experienced site supervisor; registration, personnel details and availability undertakings.
|
Evidence of available funds or credit facilities of at least Rs. 1.25 million; bank certificate or recent bank statements (preceding six months) evidencing the required resources. |
|
At least two completed similar civil repair, maintenance or waterproofing contracts in the preceding five years; work orders and completion certificates. |
Must provide a non-blacklisting affidavit
Signed declaration of no applicable debarment, insolvency or conflict of interest and compliance with applicable eligibility requirements
At least one current Contract and its progress in percentage
|
Evidence of available funds or credit facilities of at least Rs. 1.25 million; bank certificate or recent bank statements (preceding six months) evidencing the required resources. |
Turnover of Rs. 03 Million – Proven by last 3 Years Audit reports