In terms of Rules 48 of Public Procurement Rules, 2004 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director
Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
+92-319-599-2205
iescopmu@iesco.com.pk
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
|
BDS Clause Number |
ITB Number |
Amendments of, and Supplements to, Clauses in the Instruction to Bidders |
A. Introduction |
||
|
1 |
1.1 |
Name of Procuring Agency: IESCO-PMU (Islamabad Electric Supply Company (IESCO)) The subject of procurement is: NCB-238 Construction of Tower Foundation, RCC Pile Foundation, erection, stringing for Remodeling of 132 kV T/Line from location no 18 of New Wah POF East & POF North-POF west under Cost Deposit Head (21,851,660/- including 16 % PST) Expected commencement date: Wednesday, September 30, 2026 |
|
2. |
2.1 |
Financial year for the operations of the Procuring Agency: 2026-27 Name and identification number of the Contract: P53129 |
| 3. | 3.1 | JV/Consortium or Association Allowed: Yes Number of JV/Consortium Members: 2 |
B. Bidding Documents |
||
|
4. |
6.2 & 6.4 |
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Friday, July 31, 2026 |
| 5. | 7.2 |
Any addendum, in case issued, shall be published on IESCO-PMU (Islamabad Electric Supply Company (IESCO)) website and on EPADS v2.0. |
C. Preparation of Bids |
||
| 6. |
8.1 |
List of documents required along with the bid:
|
| 7. | 9.1 |
The qualification criteria to establish the supply / production capability of the bidder. see Eligibility Criteria |
| 8. | 11.2 |
|
| 9. | 11.1 | Price schedule will be provided according to the format defined and acquired. see section price schedule. |
| 10. | 11.4 |
Specifications: see section of specifications. |
|
11. |
11.5 & 13.5 |
The price shall be Fixed. |
| 12. |
14.1 |
Currency of the Bids shall be : PKR |
| 13. |
16.1 |
The Bids/Bid Validity period shall be: 90 Days |
| 14. |
17.1 |
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6 |
| 15. | 17.2 |
The Bid Security shall be in the form of: Call at Deposit, Bank Guarantee, Demand Draft |
| 16. | 15.1 |
Alternative Bids to the requirements of the bidding documents will not be permitted. |
D. Submission of Bids |
||
|
17. |
18.1 & 21.1 |
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following; Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory Bids that are not submitted on EPADS v2.0 shall be disqualified. The deadline for Bids submission is: Tuesday, August 4, 2026 11:00 AM |
E. Opening and Evaluation of Bids |
||
|
18. |
24.1 |
The Bids opening shall take place on EPADS v2.0. Day : Tuesday Date: August 04, 2026 Time : 11:30 AM |
|
19. |
30.2 |
Selection technique adopted will be: Least Cost Based Selection (LCBS) |
F. Award of Contract |
||
|
20. |
41.1 & 41.2 |
The Performance guarantee shall: 5.00%. The Performance Guarantee shall be acceptable in the form of: Bank Guarantee |
| 21. | 45.1 |
Arbitrator shall be appointed by mutual consent of the both parties. |
G. Review of Procurement Decisions |
||
|
22. |
37 |
Grievance against this procurement shall be submitted online on EPADS v2.0. |
| Bidder's Type | Required Registration |
|---|---|
| Sole Proprietorship Partnership Firm Company (Private Limited) Company (Public Limited) Company (Holding Company) Company (Limited by Guarantee) State Owned Enterprise (Private Limited) State Owned Enterprise (Public Limited) | NADRA CITIZENSHIP (CNIC/NICOP) FBR (NTN) FBR (GSTN) PEC |
| Eligibility Criteria | Document |
|---|---|
| The bidder submit Performance Guarantee in the form of Bank Guarantee issued by a Schedule bank of Pakistan having rating A+. | Yes |
| Bidders shall submit Bid Security from any scheduled bank for this tender in favor of Chief Engineer(Development)IESCO, Islamabad uploaded on E-PADS & original shall be submitted in the office of Chief Engineer (Development) IESCO, Islamabad on the day of bid opening | Yes |
| Bid Security Declaration Form-9 is not applicable | No |
| The work shall commence only after the Firm obtains the required security clearance from POF . In this regard, the Firm's performance shall be closely monitored by the GSC. If any delay is observed on the part of the Firm during submission of required documents demanded by POF, it shall be treated as a delay attributable to the Firm, and appropriate action may be taken in accordance with the contract. | Yes |
| The bidder shall include all applicable taxes, duties , levies , statutory charges , PST, GST etc as per PPRA EPADS v2 in the bid price. In case if the bidder failed to include all the taxes in the bid price then IESCO will consider bid price as inclusive of all taxes as per EPADs V2, then the same will be deducted from the invoices of bidder.Moreover, any excuse of the bidder for not adding the tax amount in the bid price shall not be accepted &IESCO will proceed as per bidding document clause | Yes |
| For clarification of unit rates, a detailed BOQ is attached as an annexure to be filled by the bidder, clearly indicating above/below and adding PST/FST as statutory charges. | Yes |
Least Cost Based Selection (LCBS)
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 85 | |
| Technical Evaluation Criteria | ||
| Average Annual Turn Over Rs. 36 Million (Quantitative)(Doc Required) | 10 | |
| Net worth for last year (with no negative net worth in the year ) Rs. 18 Million (Quantitative)(Doc Required) | 10 | |
| Financial Resources/Cash Flow Rs. 18 Million (Quantitative)(Doc Required) | 10 | |
| Bidder / JV must demonstrate at least two (02) No. of contracts that have been successfully completed within last Ten(10) years similar to the proposed work. The aggregate value of Contract Agreements / Work Orders will be equal to Rs. 18 Million. However, none of the work order should be less than 30% of Rs. 18 Million. (Quantitative)(Doc Required) | 25 | |
| Technical Staff (Quantitative)(Doc Required) | 5 | |
| Equipment/ Machinery (Quantitative)(Doc Required) | 20 | |
| Execution Schedule on MS Project (mandatory) if not provided, then technically it will be non-responsive (Quantitative)(Doc Required) | 20 | |
Jobs Without Lots :
| Job | Delivery Schedule | Quantity | Bid Security |
|---|---|---|---|
| NCB-238 Construction of Tower Foundation, RCC Pile Foundation, erection, stringing for Remodeling of 132 kV T/Line from location no 18 of New Wah POF East & POF North-POF west under Cost Deposit Head | Address: POF East , North, West Schedule: 180 days after signing of contract agreement Quantity: 1/job |
1/job | 589995 PKR |
No
Jobs Without Lots :
Job: NCB-238 Construction of Tower Foundation, RCC Pile Foundation, erection, stringing for Remodeling of 132 kV T/Line from location no 18 of New Wah POF East & POF North-POF west under Cost Deposit Head
Specifications / Requirements:
| Sr. No | Sr. # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|---|
| 1 | A1(a) | Tower Foundations (Non WCSR items) Installation of foundation of following type towers including but not limited to excavation in various soil as well in rock i/c dewatering, stub setting, leveling etc. providing slope protection where necessary i/c fixing of grounding sets as per specification i/c carriage of stub, grounding set from department store, installation of grounding sets. Tower type ZM1 foundation 20º drawing No.PDW/TC-198 | Footing | 28 | 95000 | 2660000 |
| 2 | A1(b) | Tower type ZM30 foundation 20º drawing No.PDW/TC-199 | Footing | 16 | 130000 | 2080000 |
| 3 | A1 (c ) | Tower type ZM60 foundation 20º drawing No.PDW/TC-200 | Footing | 36 | 150000 | 5400000 |
| 4 | A1(d) | Tower type EG (Dwg No.PDW/TC-805) G-1 | Footing | 4 | 350000 | 1400000 |
| 5 | B1(a)(i) | Erection of Steel Towers / Poles including Electric Welding of Towers & Transportation of Material (Non WCSR items) Transport from IESCO regional store to work sites and & Install 220/132 kV double circuit towers with all accessories in accordance with requirements of Contract Documents/ Drawings with all accessories including U-Bolts/ V-Shackles, Number plates, Danger signs, Phase plates & Anti-climbing device alongwith barbed wire etc & Electric Welding of towers Suspension Tower Type ZM - 1 Basic Body (without stubs) | No. | 7 | 70000 | 490000 |
| 6 | B1(a)(ii) | 6.0 m Leg Extension | Set | 7 | 14000 | 98000 |
| 7 | B1(b)(i) | Medium Angle Tower Type ZM - 30 Basic Body (without stubs) | No. | 2 | 97000 | 194000 |
| 8 | B1(b)(ii) | 3.0 m Leg Extension | Set | 2 | 14000 | 28000 |
| 9 | C1(a)(i) | Medium Angle Tower Type ZM - 60 Basic Body (without stubs) | No. | 7 | 136150 | 953050 |
| 10 | C1(a)(ii) | 3.0 m Leg Extension | Set | 7 | 25000 | 175000 |
| 11 | D1(a)(i) | 220KV Heavy Angle/Deadend Tower type EG Basic Body (without stubs) | No. | 1 | 315000 | 315000 |
| 12 | D1(a)(ii) | 2.0 m Leg Extension | No. | 4 | 18000 | 72000 |
| 13 | C-1 | Stringing of Conductor, Shield wire and Installation of Insulators & Dampers etc. i/c Transportation (Non WCSR items) Stringing / Sagging (Double Circuit) 03 No. conductors type ACSR LYNX including installation of Disc Insulators,Suspensation/Tension fitting,stock bridge dampers,midspan joints, repair sleeves etc including transportation from IESCO regional store to work sites.(including interfacing of terminal pole at POF NORTH G/S) | Km | 8.8 | 350000 | 3080000 |
| 14 | C-2 | Stringing 1 No. glavanized steel wire 9mm including installation of Disc Insulators,Suspensation/Tension fitting,stock bridge dampers,midspan joints etc including transportation from IESCO regional store to work sites.(including interfacing of terminal pole at POF NORTH G/S) | Km | 8.8 | 25000 | 220000 |
| 15 | D-1 | Dismantling charges of Existing Towers/Conductor along with hardware & returned to store Dismantling of Lnditive-1 without Stubs & Return to New Wah Store in scrap | No. | 43930 | 22 | 966460 |
| 16 | D-2 | Dismantling of Lnditive-60 without Stubs & Return to New Wah Store in scrap | No. | 5625 | 25 | 140625 |
| 17 | D-3 | Dismantling of existing conductor along with all allied accessories & returned to store.(ACSR zigalo length 25.5 Km) Total Weight of ACSR Scrap | KG | 8925 | 17.92 | 159936 |
| 18 | D-4 | Dismantling of existing Earth wire along with all allied accessories & returned to store.(Earth wire length 8.5 Km) Total Weight | KG | 2975 | 15 | 44625 |
| 19 | E-1 | MITIGATION MEASURES FOR ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN (EMMP) (Non WCSR items) Water quality monitoring/management analysis (Before Mobilization & After completion) Provision of clean driking water at site. | Job | 1 | 20772.64 | 20772.64 |
| 20 | E-2 | Other environmental & Social mitigation measurs (Demarcation of work area, SSEMP, First Aid Box, Fire Fighting Equipments, Proper Storage of Oil & Lubricants, Awareness Pan flexes (size 4x6 feet) minimu 15 Nos). | Job | 1 | 20169 | 20169 |
| 21 | E-3 | Site restoration (complete in all respects). | No. | 15 | 2000 | 30000 |
| 22 | E-4 | Air quality monitoring | Job | 3 | 18000 | 54000 |
| 23 | E-5 | Noise quality monitoring | Job | 4 | 24000 | 96000 |
| 24 | E-6 | Waste water quality monitoring | Job | 4 | 35000 | 140000 |
| 25 | Added 16% PST | 3014022 | ||||
| GRAND TOTAL: | Rs 21,851,659.64 |
Construction of Tower Foundations/RCC Pile Foundations of Towers, Erection including Electric Welding of Towers, Stringing of Conductor with all allied accessories and Transportation of Material from New Wah Store,EMMP of REMODELING OF 132 KV T/Line FROM LOCATION NO.18 OF NEW WAH-POF EAST & POF NORTH-POF WEST
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
The Supplier is:
The title of the subject procurement is: NCB-238 Construction of Tower Foundation, RCC Pile Foundation, erection, stringing for Remodeling of 132 kV T/Line from location no 18 of New Wah POF East & POF North-POF west under Cost Deposit Head (21,851,660/- including 16 % PST)
Number of GC Clause 2
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 3
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 4
Notices:
The addresses for the notices are:
Procuring Agency:
IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director
Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
+92-319-599-2205
iescopmu@iesco.com.pk
Contractor/ Bidder:
[Name, address and telephone number]
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 6.1
The Authorized Representatives are:
For the Procuring Agency:
IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director
Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
+92-319-599-2205
iescopmu@iesco.com.pk
For the Bidder:
Name: ………………………………………
Designation: ……………………..
Address: …………………………………………..
Number of GC Clause 7
Effectiveness of the contract
The Contractor/Bidder shall be effective within ….. days from the date of signature of the Contract by both parties
Number of GC Clause 8
Commencement of Contract:
The Contractor/Bidder shall provide Non-Consultancy Services from the effective date of contract.
Number of GC Clause 10.2
Expiration of Contract:
The time period shall be ……………………………
Number of GC Clause 14
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 16
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 20
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 0.07% to 10.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 21
Performance Guarantee:
The amount of performance guarantee shall be 5.00% of the contract price in acceptable form of Bank Guarantee
Number of GC Clause 27
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 28
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 29
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
The Committee comprising of the following officers is responsible for inspection of services i.e., Tools &Plants and skilled labor as proposed by the Contractors/ Engineers / Project Manager in order to ensure the quality of work. i. Project Director (GSC) ii. Director (PS&C) PMU iii. Deputy Director (Implementation)
In case the Tools & Plants were not found as per the data provided with the bid, your firm shall be recommended for blacklisting on basis of misrepresentation and concealing of information
1.The Employer shall retain 10 % from each interim payment certificate submitted by the Contractor until Completion of the whole of the Works. Upon the issue of Certificate of Completion of the Works by the Project Director, half the total amount retained shall be repaid to the Contractor along with release of Performance Guarantee if work is completed within time. On completion: 10% Retention and 5% Performance Guarantee
5% Retention will be withheld up to DLP and the Project Director has certified that all Defects notified by the Project Director to the Contractor before the end of this period have been corrected. The Contractor may substitute retention money with an “on demand” Bank guarantee
2.: If the work seems not to be completed within time, 10% retention amount will be withheld till the decision of the Extension of Time case. However, the 5% Performance Guarantee shall be released on completion of work on the delayed time, 10% retention money will be withheld with each payment invoice.On completion, a 5% Performance Guarantee will be returned
Number of GC Clause 31
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder shall be referred to arbitration under the laws of Pakistan including Arbitration Act 1940.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place shall be Islamabad. The award shall be final and binding.
Date: [insert date (as day, month and year)]
Bid No.:P53129
To: IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
THIS AGREEMENT made the _____ day of __________ 20_____ between IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., NCB-238 Construction of Tower Foundation, RCC Pile Foundation, erection, stringing for Remodeling of 132 kV T/Line from location no 18 of New Wah POF East & POF North-POF west under Cost Deposit Head (21,851,660/- including 16 % PST) (P53129) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: IESCO-PMU (Islamabad Electric Supply Company (IESCO)), Director Head Office, Street # 40, Sector G-7/4., Islamabad Capital Territory
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}
1. Bidder / JV must demonstrate at least two (02) No. of contracts that have been successfully completed within lastTen (10) years similar to the proposed work. The aggregate value of Contract Agreements / WorkOrders will be equal to Rs. 18 Million. However, none of the work order should be less than 30% of Rs. 18 Million. For the purpose, the bidder/JV shall provide relevant Work Order / Contract Agreement & Completion Certificates etc. TheBidder(s) /JV (s) must also demonstrate satisfactory performance of previous completed works.
2. Bidder shall provide End User Certificate for satisfactory operational performance of T/Line for at least 03 years
3. Experience in construction of 132 kV or higher voltage T/Lines including (specifically the Survey, Tower Stacking, Construction of pile foundations of Towers / Poles, Erection, Stringing, Testing & Commissioning)
and have successfully constructed / completed. In case a bid is submitted by joint venture, one of the construction partners must meet the above experience criteria.
4. Bidder must sign and stamp the form
1Non-performance of a contract did not occur within the last Five (5) years prior to the deadline for
application submission, based on all information on fully settled disputes or litigation.
2All pending litigation shall in total not represent more than Ten percent (10%) of the Bidder’s net worth and shall be treated as resolved against the Bidder
3bidder must sign stamp the forms
1.The cash flow and financial requirements of the contract in the amount of his bid proposed sources of Financing, working capital, lines of credit, and other financial means, net of current commitments, available to meet the total construction cash flow demands of the subject contract as indicated Amount of Rs. 18 Million as un- availed credit line based upon renewed facility letter or fresh firm commitment having validity period exceeding the project period being bided
incase of
1 single entity = 100% comply
2 incase of JV lead partner 60% and member 40%
2.Submission of audited balance sheets acceptable to the Employer, for the last three [3] years to demonstrate the current soundness of the bidder’s financial position and its prospective long-term profitability.
3.As a minimum a bidder’s net worth, calculated as the difference between total assets and total liabilities, should be an amount of Rs. 18 Million for the last year, with no negative net worth in the year.
incase of
1 single entity = 100% comply
2 incase of JV lead partner 100% and member 100%
Minimum average annual turnover, calculated as total certified payments received for contracts in progress or completed, within the last three (3) years be as follows: Rs. 36 Million incase of
1 single entity = 100% comply
2 incase of JV lead partner 60% and member 40%