In terms of Rules 48 of Public Procurement Rules, 2004 Grievance Redressal Committee (GRC) is notified for the subject procurement and notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
Allama Iqbal Open University (Directorate of Works), Director
Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
+92-519-572133
ali.arslan@aiou.edu.pk
The following specific data for the procurement of Goods to be procured shall complement, supplement, or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict, the provisions herein shall prevail over those in ITB.
|
BDS Clause Number |
ITB Number |
Amendments of, and Supplements to, Clauses in the Instruction to Bidders |
A. Introduction |
||
|
1 |
1.1 |
Name of Procuring Agency: Allama Iqbal Open University (Directorate of Works) The subject of procurement is: Renovation of Washrooms near Auditorium at Main Campus, Islamabad Expected commencement date: Monday, August 31, 2026 |
|
2. |
2.1 |
Financial year for the operations of the Procuring Agency: 2026-27 Name and identification number of the Contract: P58934 |
| 3. | 3.1 | JV/Consortium or Association Allowed: No Number of JV/Consortium Members: Nil |
B. Bidding Documents |
||
|
4. |
6.2 & 6.4 |
The Bidders may seek clarifications through EPADS v2.0: Clarification Date: Monday, July 27, 2026 |
| 5. | 7.2 |
Any addendum, in case issued, shall be published on Allama Iqbal Open University (Directorate of Works) website and on EPADS v2.0. |
C. Preparation of Bids |
||
| 6. |
8.1 |
List of documents required along with the bid:
|
| 7. | 9.1 |
The qualification criteria to establish the supply / production capability of the bidder. see Eligibility Criteria |
| 8. | 11.2 |
|
| 9. | 11.1 | Price schedule will be provided according to the format defined and acquired. see section price schedule. |
| 10. | 11.4 |
Specifications: see section of specifications. |
|
11. |
11.5 & 13.5 |
The price shall be Fixed. |
| 12. |
14.1 |
Currency of the Bids shall be : PKR |
| 13. |
16.1 |
The Bids/Bid Validity period shall be: 90 Days |
| 14. |
17.1 |
The amount of Bid Security shall be as defined in Bid Security Section for items and lots given in BDS 6 |
| 15. | 17.2 |
The Bid Security shall be in the form of: Pay Order, Call at Deposit, Demand Draft |
| 16. | 15.1 |
Alternative Bids to the requirements of the bidding documents will not be permitted. |
D. Submission of Bids |
||
|
17. |
18.1 & 21.1 |
Bid shall be submitted online on EPADS v2.0 whereas hard copy of the bid security should be submitted to the following; Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad Bids that are not submitted on EPADS v2.0 shall be disqualified. The deadline for Bids submission is: Wednesday, August 5, 2026 10:30 AM |
E. Opening and Evaluation of Bids |
||
|
18. |
24.1 |
The Bids opening shall take place on EPADS v2.0. Day : Wednesday Date: August 05, 2026 Time : 11:00 AM |
|
19. |
30.2 |
Selection technique adopted will be: Least Cost Based Selection (LCBS) |
F. Award of Contract |
||
|
20. |
41.1 & 41.2 |
The Performance guarantee shall: 10.00%. The Performance Guarantee shall be acceptable in the form of: Pay Order, Call at Deposit, Bank Guarantee, Demand Draft |
| 21. | 45.1 |
Arbitrator shall be appointed by mutual consent of the both parties. |
G. Review of Procurement Decisions |
||
|
22. |
37 |
Grievance against this procurement shall be submitted online on EPADS v2.0. |
| Bidder's Type | Required Registration |
|---|---|
| Sole Proprietorship Partnership Firm Company (Private Limited) | FBR (NTN) FBR (GSTN) PEC |
Least Cost Based Selection (LCBS)
Jobs Without Lots :
| Job | Delivery Schedule | Quantity | Bid Security |
|---|---|---|---|
| Renovation of Washrooms near Auditorium at Main Campus, Islamabad | Address: Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad Schedule: 6 Months Quantity: 1/job |
1/job | 60000 PKR |
No
Jobs Without Lots :
Job: Renovation of Washrooms near Auditorium at Main Campus, Islamabad
Specifications / Requirements:
| Sr. No | Ref. No. | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|---|
| 1 | Civil Works | |||||
| 2 | 1 | Dismantling cement tiled floor, dado or skirting in basement, plinth and ground floor including base mortar and stacking salvaged material (serviceable) and disposing of surplus stuff as directed within three chains (91.5 m).... | Sft | 1850 | ||
| 3 | 2 | Dismantling C.C. work cast in situ in first floor including disposing of the material as directed within three chains (91.5 m). | Cft | 200 | ||
| 4 | 3 | Taking out carefully shutters of doors and windows in ground floor and stacking as directed within three chains (91.5 m). | Each | 12 | ||
| 5 | 4 | Taking out door and window frames with or without hold fasts in ground floor including cutting walls, stacking salvaged material (serviceable) and disposing of unserviceable material as directed within three chains. | Each | 10 | ||
| 6 | 5 | Distempering three renewal coats with vinyle distemper (Paintex ICI Dulux) of approved make and shade to walls and ceiling etc., including scraping cleaning the old surface in any floor . | Sft | 1300 | ||
| 7 | 6 | Painting wood work with synthetic enamel paint of approved make and shade two coats over and including the cost of one priming coat complete at any height in any floor . | Sft | 400 | ||
| 8 | 7 | Provide, fill, compact, level, cure etc. 1:2:4 mass concrete in raise Floor. | Cft | 200 | ||
| 9 | 8 | Provide and fixing floor approved coloured glazed tiles more then from 1 Sq.ft to 2 ft size master make or equivalent first grade in ground floor laid over 1" thick cement morter 1:2, including filling the joints and washing the tiles with white cement slurry a matching color and curing and cleaning etc. complete (Ground Floor) | Sft | 500 | ||
| 10 | 9 | Providing and fixing 1/4 inches or 6.4 mm (approx.) thick approved Pakistani make glazed tiles upto 1.50 sq.ft to 3. sq. ft size in dado and skirting in ground floor, over 1/2 inch (13 mm) thick base of cement mortar 1:3 setting of tiles in slurry of grey cement over mortar base including filling the joints and washing the tile with white cement slurry curing and cleaning etc. complete (Ground Floor) | Sft | 2200 | ||
| 11 | 10 | Providing & fixing best quality earthern ware vanity basin (porta or equivalent) standard size (white/light color) and including the cost of 1-1/4" rubber plug and chrome plated brass chain pvc waste pipe 1-1/4" dia of apporved pattern etc. complete | Each | 4 | ||
| 12 | 11 | Providing and fixing floor waste 6"x6" (stainless steel) Jali etc. complete. | Each | 10 | ||
| 13 | 12 | Providing & fixing chromium plated Muslim bib-cock with Muslim Shower of approved quality. | Each | 8 | ||
| 14 | 13 | Providing and fixing best quality white glazed earthenware One piece toilet (commode) coupled with flush tank (Porta or equivalent) complete with and including cost of plastic seat with Buffers, with internal fittings complete. | Each | 2 | ||
| 15 | 14 | Providing and fixing best quality squatting type earthern ware W.C. pan (Porta or equivelent complete with and including the cost of 13.6 litre best quality low level plstic slushing cisternwith intrenal fittings complete. P.V.C flushing pipe suitable for squatting type wiyh extra bends and length with fittings, PVC trap 4 inches dia and making requisite number of hles in walls, plinth and floor for pipe connection and making good in cement conrete 1:2:4. | Each | 5 | ||
| 16 | 15 | Providing and fixing un platisized polyvinyl chloride pipe (U.P.V.C) “D” class (Acid Proof) of "Dadex" with specials such as bend Tee elbo reducer union floop trap etc. and clamps etc, including cutting and fitting complete with and including the cost of breaking through walls and roof and making good etc., after cleaning the pipe and cartage within 10 miles (16.09 km). | ||||
| 17 | 15.1 | 3" Dia | Rft | 64 | ||
| 18 | 15.2 | 4" Dia | Rft | 64 | ||
| 19 | 16 | Providing and fixing CP Mixer 1/2 inches (15 mm) (Faisal/Master or equivelent) lever type Paksitani complete in all respect. | Each | 4 | ||
| 20 | 17 | Providing and PPRC pipe PN-20 with specials, and clamps etc, including cutting and fitting complete with and in-cluding the cost of breaking through walls and roof and making good etc; after cleaning the pipe and cartage within 10 miles, (Internal) 25 mm dia. | Rft | 160 | ||
| 21 | 18 | Providing and fixing 1-1/2 inch (38 mm) thick best quality deodar wood shutters fully panelled with same wood, approved iron hinges and tower bolts, etc., as required.. | P.Sft | 196 | ||
| 22 | 19 | Providing and fixing on door frame etc. with sunken iron screw best quality dedoar wood moulding/beading/ architrave etc. of approved design (2-1/4" x 5/8" x 3/8" Taper), as per drawing (A-08 & Gen-01) complete. | Rft | 200 | ||
| 23 | 20 | Providing and fixing M.S. moulded steel door frames of 5.73" x 2-1/2" (146 mm x 63 mm) manufactured from mild steel sheet of 18 gauge (1.41 mm) conforming to B.S.S. 1245 having a double rebate size 1- 1/2" x 1/2" (38 mm x 12 mm) provision of 3 Nos. M.S. plate, section 1- 1/2" x 1/4" (38 mm x 6 mm) (2 Nos. 6 inch long welded with frame at not less than 10 points and 1 Nos. 12 inch long welded with frame at not less than 20 points), with holes and threads for fixing steel hings, fitted with one locking box of same sheet (point welded inside the frame), 6 Nos. 6 inches long flat iron fixing lugs of 1-1/4" x 3/16" section, treated with special red oxide primer coat all around including cutting holes and filling the cavity with cement concrete 1:2:4 etc. in any floor at any height complete as directed by the Engineer-in-Charge | Rft | 170 | ||
| 24 | 21 | Repainting two coats with weather shield paint of (ICI) Dulux make and shade on plaster surface (External) including cleaning, sand papering the surface as directed by the Engineer-in-charge in any floor. | Sft | 900 | ||
| 25 | 22 | Providing & Fixing Machine made Guttca brick tiles facing 1-1/2" to 2" thick in cement marter 1:3 cement pointed in deep cut grooves and in any pattern as per direction of the Engineer including in any floor in any hight. | Sft | 640 | ||
| 26 | 23 | Plastering 3/4" (19 mm) thick in patches in cement sand mortar 1:4 including curing and scraping old damaged portion in regular shape and removal of rubbish from the site etc. complete as per direction of Engineer-in-Charge in ground floor. | Sft | 600 | ||
| 27 | Electrical Works | |||||
| 28 | 1 | Wiring for light or fan point with (3/.029") PVC insulated wire in 20 mm², (3/4") dia uPVC conduit recessed in the wall, column, roof , including 1mm² single core PVC insulated wire as ECC as required. | Point | 8 | ||
| 29 | 2 | Supply, installation, testing and commissioning of LED tube /Batten Lights including driver warm / Neutral White / cool white color 80-90 im/watts efficiency , 0.9 or above power factor , 10000-15000 hours life cycle, including connection , complete in all respect as approved by the Engineer Incharge (Philips/Signify, Osram, GE, Thorn) (18-20 Watts) | Each | 10 | ||
| 30 | 3 | Providing & fixing 10 Amps Polycarbonate flame retardant S.P switch with fancy "Ivory" gang plate fixed on die fabricated, powder coated, metal board recessed in the wall or column including connection as required. (MATRIX / SOK / TJ SERIES/TRUST make) | Each | 16 | ||
| 31 | 4 | Providing & installing 30 Cm ( 12") sweep, Plastic body Exhaust fan complete with blades, motor, etc fixed in existing hole including connection with 14/.0076" flexible wire complete as required Pak, Royal, GFC,Younas,Millat. | Each | 4 | ||
| 32 | Miscellaneous Works | |||||
| 33 | 1 | Removing of existing bath room accessories/ earthenware (Commode, Wash Basin, Bib Cocks, Tee cock, Shower Set Towel rail, Soap Dish, Toilet paper holder and Flushing Cistern etc) including the cost of removing of carefully handing over to directorate of works. | Job | 8 | ||
| 34 | 2 | Providing and fixing Looking glass imported Belgium or approved 5mm thick i/c edging of approved 6 Sft size fixing with clamps C.P screws good quality complete as per direction of Engineer Incharge. | Sft | 16 | ||
| 35 | 3 | Removing of existing installed electrical accessories (Tubelights/ceiling lights/Fans etc.) carefully including the cost of removing of wiring (cable and duct etc) and handing over to the directorate of works as required and directed by the engineer in-charge. | Each | 10 | ||
| 36 | 4 | Providing and fixing approved quality C.P. Soap Dish (Faisal, Porta & Sonex) or as approved by Engineer Incharge. | Each | 4 | ||
| 37 | Total | 2851511 | ||||
| GRAND TOTAL: | Rs 2,851,511.00 |
The site of work is in Islamabad, and the scope of work includes:
For Individual Jobs
| # | Job Title | Quantity | Unit Price (PKR) | Total Price (PKR) | Delivery Location | Delivery Period / Year | Country of Origin |
|---|---|---|---|---|---|---|---|
| 1 | |||||||
| 2 |
| # | Lot Title | Total Lot Price (PKR) | Country of Origin |
|---|---|---|---|
| 1 | [Lot 1 Title] |
The following Special Conditions of Contract shall supplement the General Conditions of Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the Conditions of Contract. The corresponding clause number of the GCC is indicated in parentheses.
Number of GC Clause
Amendments of, and Supplements to, Clauses in the General Conditions of Contract
Number of GC Clause 1
Definitions
The Procuring Agency is: Allama Iqbal Open University (Directorate of Works), Director Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
The Supplier is:
The title of the subject procurement is: Renovation of Washrooms near Auditorium at Main Campus, Islamabad
Number of GC Clause 2
Applicable/Governing Law:
The Contract shall be interpreted in accordance with the laws of Islamic Republic of Pakistan
Number of GC Clause 3
Language:
The language of the Contract, all correspondence and communications to be given, and all other documentation to be prepared and supplied under the Contract shall be in English.
Number of GC Clause 4
Notices:
The addresses for the notices are:
Procuring Agency:
Allama Iqbal Open University (Directorate of Works), Director
Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
+92-519-572133
ali.arslan@aiou.edu.pk
Contractor/ Bidder:
[Name, address and telephone number]
The Contractor/ Bidder’s Representative(s)
[Name, address, telephone number and e-mail address]
Number of GC Clause 6.1
The Authorized Representatives are:
For the Procuring Agency:
Allama Iqbal Open University (Directorate of Works), Director
Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
+92-519-572133
ali.arslan@aiou.edu.pk
For the Bidder:
Name: ………………………………………
Designation: ……………………..
Address: …………………………………………..
Number of GC Clause 7
Effectiveness of the contract
The Contractor/Bidder shall be effective within ….. days from the date of signature of the Contract by both parties
Number of GC Clause 8
Commencement of Contract:
The Contractor/Bidder shall provide Non-Consultancy Services from the effective date of contract.
Number of GC Clause 10.2
Expiration of Contract:
The time period shall be ……………………………
Number of GC Clause 14
Termination
In the event of termination of the contract due to any reason as already defined in the General Conditions of Contract, the Bidder shall be responsible for providing to the Authority the Goods till the time of alternate arrangements.
Number of GC Clause 16
Conflict of Interest:
The Procuring Agency reserves the right to determine on a case-by-case basis whether the Bidder should be disqualified from providing goods or services due to a conflict of a nature described in Clause GCC 17.
Number of GC Clause 20
Liquidated Damages
If the Bidder fails to provide services as required under the contract or in case of any data loss/data breach or any incident compromising the data security or other such failures related to any services, the Bidder shall pay to the Procuring Agency as Liquidated Damages at a rate of 0.10% to 10.00% of the Contract value, in accordance with the extent of performance failure & the cost of investigating such incidents as judged by the Authority.
Number of GC Clause 21
Performance Guarantee:
The amount of performance guarantee shall be 10.00% of the contract price in acceptable form of Pay Order, Call at Deposit, Bank Guarantee, Demand Draft
Number of GC Clause 27
Currency of Payment:
All the payment to be released to the contractor/Bidder shall be in Pakistani Rupees.
Number of GC Clause 28
Payment terms:
Payment will be made to the Bidder against the procured Goods and services according to the actual invoice or running bills submitted by the Bidder against the services provided within the time given in the conditions of the contract.
Number of GC Clause 29
Identifying Defects:
The Authority reserves the right at any time to inspect the premises of the provider to inspect the goods and monitor the goods being provided.
For all the items to be installed at site, a prior approval from the Employer shall be mandatory.
The employer shall inspect the executed works and confirm their execution as per the scope, specs, and BOQs.
For conformance to specifications and performance parameters, prior delivery inspection by the employer shall be must.
A designated committee of the employer shall inspect and test all the works items as per BOQs and specs.
The samples of all the works items must be submitted before bringing them to site and should be approved by the Employer, invariably.
Copies of the Supplier’s invoice showing the executed works against the running bill.
Measurement sheets with each running bill showing executed BOQs against respective bill and consolidated completion of tasks up to that running bill against the total BOQs.
Inspection Certificate issued by the Directorate of Works.
Number of GC Clause 31
Following is the guidance for Dispute Resolution
Notwithstanding any reference to the arbitration herein, the parties shall continue to perform their respective obligations under the Contract.
Rules of procedure for arbitration proceedings:
Any dispute between the Authority and a Bidder shall be referred to arbitration under the laws of Pakistan including Arbitration Act 1940.
Place of Arbitration and Award:
The arbitration shall be conducted in English language and place shall be Islamabad. The award shall be final and binding.
Date: [insert date (as day, month and year)]
Bid No.:P58934
To: Allama Iqbal Open University (Directorate of Works), Director Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid Securing Declaration.
We accept that we will be blacklisted and henceforth cross debarred for participating in respective category of public procurement proceedings for a period of (not more than) six months, if fail to abide with a bid securing declaration, however without indulging in corrupt and fraudulent practices, if we are in breach of our obligation(s) under the Bid conditions, because we:
We understand this Bid Securing Declaration shall expire if we are not the successful
Bidder, upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder; or (ii) twenty-eight (28) days after the expiration of our Bid.
THIS AGREEMENT made the _____ day of __________ 20_____ between Allama Iqbal Open University (Directorate of Works), Director Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
(hereinafter called “the Procuring Agency”) of the one part and [name of Bidder] of [city and country of Bidder] (hereinafter called “the Bidder”) of the other part:
WHEREAS the Procuring Agency invited Bids for provision of goods, viz., Renovation of Washrooms near Auditorium at Main Campus, Islamabad (P58934) and has accepted a Bids by the Bidder for the provision of Goods in the sum of [contract price in words and figures] (hereinafter called “the Contract Price”).
NOW THIS CONTRACT WITNESSETH AS FOLLOWS:
1. In this Contract words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this Contract, In the event of any ambiguity or conflict between the Contract Documents listed below, the order of precedence shall be the order in which the Contract Documents are listed below:-
3. In consideration of the payments to be made by the Procuring Agency to the Bidder as hereinafter mentioned, the Bidder hereby covenants with the Procuring Agency to provide the Goods related services and to remedy defects therein in conformity in all respects with the provisions of the Contract.
4. The Procuring Agency hereby covenants to pay the Bidder in consideration of the provision of Goods and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the contract at the times and in the manner prescribed by the contract.
IN WITNESS whereof the parties hereto have caused this Contract to be executed in accordance with their respective laws the day and year first above written.
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Procuring Agency:
………………………………………………
Signed, sealed, delivered by __________________the ________________ (for the Procuring Agency)
Witness to the signatures of the Bidder: …………………………………………………
Contract Number: Contract Value: Contract Title:
Dated:
[Name of Supplier] hereby declares that it has not obtained or induced the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or any administrative subdivision or agency thereof or any other entity owned or controlled by it (GoP) through any corrupt business practice.
Without limiting the generality of the foregoing [Name of Supplier] represents and warrants that it has fully declared the brokerage, commission, fee etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder's fee or kickback, whether described as consultations fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.
[Name of Supplier] certifies that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representative or warranty.
[Name of Supplier] accepts full responsibility and strict liability for making and false declaration, not making full disclosure, misrepresenting fact or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right interest, privilege or other obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.
Notwithstanding any rights and remedies exercised by GoP in this regard, [Name of Supplier] agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder's fee or kickback given by [Name of Supplier] as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.
To: Allama Iqbal Open University (Directorate of Works), Director Directorate of Works, Allama Iqbal Open University, Sector H-8/2, Islamabad
WHEREAS [name of Bidder] (hereinafter called “the Bidder”) has undertaken, in pursuance of Contract No. [reference number of the contract] dated [insert date] for provision of Goods(hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the said Contract that the Bidder shall furnish you with a Bank Guarantee by a reputable bank for the sum specified therein as security for compliance with the Bidder’s performance obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Bidders guarantee:
THEREFORE, WE hereby affirm that we are Guarantors and responsible to you, on behalf of the Bidder, up to a total of [amount of the guarantee in words and figures], and we undertake to pay you, upon your first written demand declaring the Bidder to be in default under the Contract and without cavil or argument, any sum or sums within the limits of [amount of guarantee] as aforesaid, without your needing to prove or to show grounds or reasons for your demand or the sum specified therein.
This guarantee is valid until the: [insert date]
Signature and seal of the Guarantors
_____________________________________________________________________
[name of bank or financial institution]
_____________________________________________________________________
[address]
_____________________________________________________________________
[date}