In terms of Rule 48 of Public Procurement Rules, 2004, a Grievance Redressal Committee (GRC) is notified for the subject procurement and the notification copy is available on the procuring agency’s website and on Authority’s website at (www.ppra.org.pk).
Pakistan Airports Authority (Planning & Development Directorate), Director Planning & Development
Planning and Development Directorate, Headquarters,
Pakistan Airports Authority, Terminal-1, JIAP Karachi
+92-219-924-2773
director.pdev@paa.gov.pk
Sections of Prequalifica¬tion Documents
The following specific data for the Prequalification of Applicants shall complement, supplement, or amend the provisions in the Instructions to Applicants (ITA). Whenever there is a conflict, the provisions herein shall prevail over those in ITA.
PDS Clause Number
ITA Number
Amendments of, and Supplements to, Clauses in the Instructions to Applicants
PDS Clause Number 1
ITA Number 1.1
Identification Number of the Invitation for Prequalification: P108382
The Procuring Agency is: Pakistan Airports Authority (Planning & Development Directorate)
List of Service Contracts:
See section services and Lots
PDS Clause Number 2
ITA Number 2.1
The name of Procuring Agency is: Pakistan Airports Authority (Planning & Development Directorate)
The name of Project / Procurement is: PLANNING, DESIGN AND CONSTRUCTION SUPERVISION FOR THE NEW DEPARTURE LEVEL BRIDGE, EXTENSION OF CONCOURSES AND ALLIED WORKS AT ALLAMA IQBAL INTERNATIONAL AIRPORT (AIIAP), LAHORE
PDS Clause Number 3
ITA Number 4.2
Maximum number of members in a Joint Venture (JV): 3
PDS Clause Number 4
ITA Number 4.5
A list of debarred firms and individuals is available on PPRA website: https://ppra.gov.pk
PDS Clause Number 5
ITA Number 7.1
For clarification, the Applicant shall seek clarifications through: EPADS v2.0
PDS Clause Number 6
ITA Number 7.1 & 8.2
Information related to Prequalification shall be published on: EPADS v2.0
PDS Clause Number 7
ITA Number 7.2
Pre-Application Meeting: Clarification Date: Friday, September 18, 2026
PDS Clause Number 8
ITA Number 10.1
This Prequalification Document has been issued in the language: English
PDS Clause Number 9
ITA Number 11.1(d)
Additional documents to be submitted through EPADS v2.0:
No
PDS Clause Number 10
ITA Number 14.2
Source for determining exchange rates: Not Applicable
PDS Clause Number 11
ITA Number 16.1
Deadline for Application Submission:
Day: Friday
Date: Friday, September 25, 2026
Time: 11:00 AM
PDS Clause Number 12
ITA Number 17.1
Opening of Applications shall be conducted through: EPADS v2.0
Day: Friday
Date: Friday, September 25, 2026
Time: 11:30 AM
Virtual participation link: https://vendors.epads.gov.pk/
PDS Clause Number 13
ITA Number 21.1
Margin of Domestic Preference: Not Applicable
(Applicable only if authorized in Procurement Plan)
PDS Clause Number 14
ITA Number 29.1
Prequalification-related complaints / grievances shall be submitted in writing through: EPADS v2.0
A complaint may challenge:
| Bidder's Type | Required Registration |
|---|---|
|
Any |
FBR (NTN) SECP PEC |
| Eligibility Criteria | Document |
|---|---|
| Valid registration with the Pakistan Engineering Council (PEC) as a consultant including registration in Project Profile Codes 1215, and 1216 and Service Codes of 0532, 0537 and 0546. In the case of a Joint Venture (JV), at least one member of the JV must meet the requirement | Yes |
| All foreign consulting firms intending to participate in this procurement process must comply with the Pakistan Engineering Council (PEC) Bye-Laws. The firm must be registered with PEC in accordance with the Consulting Engineers/Consulting Firms Registration Regulations and possess a valid license for providing consultancy services in Pakistan. [If this requirement does not pertain to you, attach a single pager stating this requirement as not applicable] | Yes |
| Foreign Firms must form a joint venture (JV) with a Pakistani consulting firm duly registered with PEC, as per the PEC regulations. Letter of Intent to form JV on each firm’s letter head is required. [If this requirement does not pertain to you, attach a single pager stating this requirement as not applicable] | Yes |
| Registration with the Federal Board of Revenue (FBR) as an active taxpayer. For foreign firms participating in a JV, registration with the relevant authority in the jurisdiction of their registration is required. | Yes |
| Registration with Securities & Exchange Commission of Pakistan (SECP). In case of Foreign Firm participating in JV, Certificate of Incorporation of the firm in the Country of Origin is required. | Yes |
| Letter of Application (Annexure A), duly signed by an authorized representative of the Applicant. | Yes |
| Joint Venture agreement or a letter of intent to form such an agreement, duly signed by all members (in the case of a Joint Venture). [If this requirement does not pertain to you, attach a single pager stating this requirement as not applicable] | Yes |
| Power of Attorney (on non-judicial Stamp Paper valuing PKR 500) specifically authorizing the authorized representative to sign and submit the application for prequalification on behalf of the Applicant. | Yes |
| Affidavit of non-Blacklisting on judicial stamp paper to the effect that the firm/ JV/ Consortium partner(s) has never been blacklisted with any Government Department/ Agency/ Authority | Yes |
Quality Based Selection (QBS)
Weightage (Without Financial Criteria)
| Technical Evaluation % |
|---|
| 100 |
| Technical Marks | 100 | |
|---|---|---|
| Passing Marks | 70 | |
| Financial Soundness –Refer to Section 3.3.1.1 of Evaluation Criteria Annexure | ||
| Average Annual Turnover of the Applicant – Attach audited financial statements for any three of last five financial years duly certified by a Chartered Accounting Firm submitted with (Form A-4). Average Annual turnover for any three of last five financial years. Form A-4 shall be filled in this regard. [05 marks if average annual turnover of any three of last five financial years is PKR 500 million or above.] Average Turnover = (Year 1 + Year 2 + Year 3) ÷ 3 [For average turnover of less than PKR 500 million, marks shall be awarded as per following formula: (A × 5 / 500), where ‘A’ is average annual turnover in Million] (Qualitative)(Doc Required) | 5 | |
| Average Annual Working Capital – Attach audited financial statements for any three of last five financial years duly certified by a Chartered Accounting Firm submitted with (Form A-4). Average Annual Working Capital for any three of last five financial years. Form A-4 shall be filled in this regard. Average Working Capital = (Year 1 + Year 2 + Year 3) ÷ 3 [05 marks if average working capital any three of last five financial years is PKR 300 million or above] [For average working capital of less than PKR 300 million, marks shall be awarded as per following formula: (A × 5 / 300), where ‘A’ is average annual working capital in Million] (Qualitative)(Doc Required) | 5 | |
| General/Specific Experience - Refer to Section 3.3.1.2 of Evaluation Criteria Annexure | ||
| Experience in General Engineering Consultancy Services – Attach “Completion of Services (Design and/or Supervision)” and any other supporting document (clearly stating the date of completion of either Services and project cost) of the respective project with Form A-2 and A-3. A particular project for an engineering design service can only be claimed against one of the sub-criteria General Experience of all types of engineering design consultancy services in the last ten (10) years for projects having a minimum overall Estimated/Completion Cost of PKR 1,000 million for local/ US $ 3.5 Million for foreign JV partner. Three (03) marks shall be awarded for each successfully completed project. Maximum 10 Marks shall be awarded if ≥ 4 successfully completed project. (Qualitative)(Doc Required) | 10 | |
| Experience in Roads & Highways Projects - Attach “Completion of Services (Design)” and any other supporting document (clearly stating the date of completion of Services and project cost) of the respective project with Form A-2 and A-3. A particular project for an engineering design service can only be claimed against one of the sub-criteria Experience of Engineering Design Services for Road and Highways projects with a minimum cost of the project of Rs 2,000 million for local / US $ 7.0 Million for foreign JV partner in the last fifteen (15) years. [05 Points for each successfully completed project with maximum of 10 Points]. (Qualitative)(Doc Required) | 10 | |
| Specific Experience of Bridge/Flyover – Attach “Completion of Services (Design and/or Supervision)” and any other supporting document (clearly stating the date of completion of either Services and project cost) of the respective project with Form A-2 and A-3. A particular project for an engineering design service can only be claimed against one of the sub-criteria a) Experience of Engineering Design Consultancy services for a bridge/Flyover project having minimum cost of the project of Rs 1,000 million for local/ US $ 7 Million for foreign JV partner in the last fifteen (15) years. [Eight (08) Points for each successfully completed project with maximum of 16 Points] b) Experience of construction supervision Consultancy services for a bridge/Flyover/Metro having minimum cost of the project of Rs 2,000 million for local/ US $ 7 Million for foreign JV partner in the last fifteen (15) years. [Seven (07) Points for each successfully completed project with maximum of 14 Points]. (Qualitative)(Doc Required) | 30 | |
| Key Personnel - Refer to Section 3.3.1.3 of Evaluation Criteria Annexure. | ||
| Project Team Leader – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: M.Sc. Civil Engineering / Project Management Registered with PEC as Professional Engineer. Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Architect – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: B.Sc. Architecture Registered with PCATP Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Structural Design Engineer – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: M.Sc. Civil (Structures) Registered with PEC as Professional Engineer Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Pavement Design Engineer – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: M.Sc. Civil (Transportation) Registered with PEC as Professional Engineer Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Mechanical / HVAC Design Engineer – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: M.Sc. Mechanical Registered with PEC as Professional Engineer Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Electrical Design Engineer – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: M.Sc. Electrical Registered with PEC as Professional Engineer Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
| Network Design Engineer – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: B.Sc. Computer System / IT / Electronics / Telecom Registered with PEC as Professional Engineer Minimum Relevant Experience: 05 years (Qualitative)(Doc Required) | 5 | |
| Contract Specialist – Attach Form A-6 and A-7 for proposed Key Expert with Supporting documents Minimum Academic Qualification: B.Sc. Engineering Registered with PEC as Professional Engineer Minimum Relevant Experience: 10 years (Qualitative)(Doc Required) | 5 | |
The Annexure attached hereto shall constitute an integral, essential, and binding part of the PQ Documents. The Applicant shall download the aforesaid Annexures, duly sign and stamp each page thereof, and upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents
The Annexure attached hereto shall constitute an integral, essential, and binding part of the PQ Documents. The Applicant shall download the aforesaid Annexures, duly sign and stamp each page thereof, and upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The application forms attached as annexure shall be duly completed/filled, signed and stamped, together with all supporting documents required therein and the applicant shall upload the complete scanned copy as an integral part of its submission. Failure to comply with this requirement may render the application non-responsive, in accordance with the applicable procurement rules and the provisions of the PQ Documents.
The Annexure attached hereto shall constitute an integral, essential, and binding part of the PQ Documents. The Applicant shall download the aforesaid Annexures, duly sign and stamp each page thereof, and upload the complete scanned copy as an integral part of its submission.